An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LS1 & Buildings 115, 507 and 601

  2. Building 601 • Building 601 (kitchen & entrance): • Power has been cut and disconnected (Patrick Gallay EL) • All items removed by the users • All electrical cabinets and distribution have been removed (recuperated) • Tourniquet has been removed and is stored for later use in 508 (Nino Rama) • Preparation finishing for the desamiantage – treatment of the asbestos parts in roof and floor

  3. DesamiantageBat 601 finished

  4. Building 115 • Power has been cut and disconnected (Patrick Gallay EL) • All items (Solid State Lab) have been removed by the users – checked by RP • Workshop machines have gone into storage • All electrical cabinets and distribution have been removed (recuperated) • Airco units have been recuperated (users) • Remaining the fiber optics connection: To be disconnected (after desamiantage) • De-classification (Class C) done by RP (AlexandreDorsival, ChristelleSaury, MatthieuDeschamps) – paperwork to be finished • Gas bottles in the gas point to be removed

  5. Packing, thanks to the diligent in-house teams

  6. Empty building 115

  7. Packing workshop

  8. DesamiantageBat 115 finished

  9. Building 507: • Power has been cut and disconnected (Patrick Gallay EL) • All items (Laser Labs) have been removed by the users – checked by RP • All electrical cabinets and distribution have been removed (recuperated) • Signal cabling to be pulled back into the hall for later use in the new 508 (GeorgieGeorgiev EL) • (unfortunately some signal cables got unforeseen cut from the Collaps Lab side) • Water has been cut upstream (Isolde water station) but there is a leak on the valve – to be changed before demolishing starts • De-classification (Class C) will start

  10. Recuperation: electrical cabinets and power outlets

  11. Signal patch panels in 507 to be removed &recuperated. • Cables will be pulled back into the hall to be reused in 508 (ongoing):

  12. New access stairs have been put in place to replace the ladder.

  13. Access: • Temporary access by card reader on the hall 170 door has been put in place (with buzzer 10 min) (Nino Rama & team) – ok with RP • Existing staircase from Rue Democrite will be re-used during work on the site. • Fencing in place to separate access site from construction site • Building 170: • New access stairs have been put in place to replace the ladder. They will give safe and easier access to the to be installed barrack on the 170 roof for released air measurements (Daniel Parchet)

  14. New Access during Building works

  15. New Access • Access via old existing staircase (leaves and fence have been removed now). Access area blocked off from work site. Card reader on the Isolde hall door:

  16. Situation

  17. Situation with respect old buildings BottomFloor: 450 m2 Top Floor: 250 m2

  18. Bulding 508 / BottomFloor I COLLAPS LASER LAB COLLAPS CONTROL ROOM SSP Laser Laboratory Access ISOLDE Hall Classified C Chemicalstore Chemicallab PAC 66 m2

  19. Bulding 508 / BottomFloor II CRISLASER LAB Detector Laboratory CRIS LASERControl Room Workshop 26 m2 EmisssionChanneling Diffusion Meas. Vibrations Isolated Access tothepublic

  20. Building 508 / part I View tothe ISOLDE Hall Office 19 m2 VISITORS ROOM 68 m2 Office 19 m2

  21. Building 508 / part II Toilets men Kitchen 19 m2 DAQ Room 28 m2 Toilets Women

  22. Planning • Asbestos: Desamiantage of bat 601 and 115 finished 5 July 2013 • Inspectionof buildings: VIC nextweek • Demolition: 14th July – 5th of August • Drains and waternetworks: 5th August – 31st of August • ConcretGround : September – Mid-October • Mounting Modules : November • MISSING for 2014: Electricity Water Air conditioning Opticalfiber Computernetwork

  23. Planning