Tab 10: Competitive Renewable Energy Zone (CREZ) Update

Tab 10: Competitive Renewable Energy Zone (CREZ) Update. Woody Rickerson Director, Grid Coordination. Board of Directors Meeting ERCOT Public November 13, 2012. 1. CREZ Timeline. Initial ERCOT CREZ Study Completed. ERCOT CREZ Transmission Optimization Plan Completed. PUCT

claus
Download Presentation

Tab 10: Competitive Renewable Energy Zone (CREZ) Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Tab 10: Competitive Renewable Energy Zone (CREZ) Update Woody Rickerson Director, Grid Coordination Board of Directors Meeting ERCOT Public November 13, 2012 1

  2. CREZ Timeline Initial ERCOT CREZ Study Completed ERCOT CREZ Transmission Optimization Plan Completed PUCT Chooses TSPs for Projects ABB Reactive Study SB 20 is Passed ROWs Chosen 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 ~42 months PUCT Opens Docket 33672 designating the CREZ zones CREZ Construction Begins Construction Complete Today Tab 10 ERCOT Public

  3. ERCOT 345-kV system before and after the addition of the CREZ lines New CREZ lines Tab 10 ERCOT Public

  4. Approximate 345-kV Circuit Miles in ERCOT Grid 345-kV circuit-miles Tab 10 ERCOT Public

  5. CREZ Completion Dates in TPIT (Transmission Project Information Tracking) Tab 10 ERCOT Public

  6. CREZ Projects to be Completed in 2012 Completed Prior to 2013 New CREZ lines Tab 10 ERCOT Public

  7. CREZ-Related Construction Outages

  8. Outage Coordination Tab 10 ERCOT Public