1 / 21

Breakout Session # 2 Nick Sanders, Director, Government Contracts Practice

Navigating the Cost Impact Process – The New FAR Part 30. Breakout Session # 2 Nick Sanders, Director, Government Contracts Practice PricewaterhouseCoopers LLP July 28, 2006. A Maze of Overlapping Requirements. CASB rules, regulations & Standards

cole
Download Presentation

Breakout Session # 2 Nick Sanders, Director, Government Contracts Practice

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Navigating the Cost Impact Process – The New FAR Part 30 Breakout Session # 2 Nick Sanders, Director, Government Contracts Practice PricewaterhouseCoopers LLP July 28, 2006

  2. A Maze of Overlapping Requirements • CASB rules, regulations & Standards • 48 C.F.R. § 9900 revised (in pertinent part) June 2000 • FAR Part 30: Administration of CAS and CAS-covered contracts • Revised March 2005 • CAS clauses incorporated into contracts • 52.230-1 thru 52.230-7 • 52.230-6 revised March 2005 • 52.230-7 added March 2005

  3. Evolving and Conflicting Guidance • Court decisions • Perry v. Martin Marrietta • 47 F.3d 1134, 1995 • Lockheed Martin v. United States • U.S. Court of Federal Claims, 2006 • DoD guidance • DPAP, January 2002 • What is a “change in cost accounting practice”? • DPAP, Sept. 2002 – modification to January 2002 guidance • DCAA, January 2002 – format and calculation of cost impacts

  4. Navigating the Process Requires Knowledge of All Relevant Areas Cost Impact Process

  5. Overview of the New FAR 30.6 • Three Types of Changes • Required change • Unilateral change • Desirable change • Two Proposal Formats • Gross Dollar Magnitude (GDM) • Detailed Cost Impact (DCI)

  6. Contractor Pre-Award 52.230-7 Disclosure Statement Post-Award Changes Noncompliances Government Pre-Award CFAO DCAA Post-Award CFAO DCAA Key Responsibilities

  7. The Cost Impact Process • CFAO Notification • DCAA’s Five-Step Process • Compute increased/decreased cost estimates and/or accumulations for CAS-covered contracts/subcontracts • Combine contract impacts by type (FP vs. Flexibly priced) • Handling T&M contract types? • Combining between groups? • Evaluating non-CAS-covered contracts and future awards?

  8. DCAA’s Five-Step Process (Cont’d.) • Net contracts (within each type) together to determine increased or decreased costs paid by Government for each type - Include profit/fee/incentives

  9. DCAA’s Five-Step Process (Cont’d.) 4. Combine bottom-line impacts of each contract type together to determine increased or decreased costs “in the aggregate” • Increased costs in the aggregate to be recovered by Government—except for desirable changes • Decreased costs in the aggregate will not be recovered by contractor—except for required changes

  10. DCAA’s Five-Step Process (Cont’d.) 5. Settle Impact • Contract adjustments • Indirect rate adjustments • Cash payment

  11. Gross Dollar Magnitude Proposal • Show impacts on a representative sample of contracts, or • Show change in indirect cost rates muliplied by estimated contract base(s), or • Must show fixed-price impact separate from flexibly priced impact • “Any other method that provides a reasonable approximation of the total increase or decrease in cost accumulations for all affected fixed-price and flexibly-priced contracts and subcontracts.”

  12. Gross Dollar Magnitude Proposal • May be in any format acceptable to CFAO, but format must show: • Impacts by Executive Agency • Impacts by contract type • Fixed-price vs. flexibly priced • For unilateral changes, contractor must be able to identify all affected CAS-covered contracts when required to do so by CFAO

  13. Detailed Cost Impact Proposal • CFAO may require DCI if GDM is not adequate • Contractor may elect to submit DCI in lieu of GDM proposal • DCI shows impacts on each affected CAS-covered contract and subcontract • Parties may agree to limit impact to contracts over a certain dollar threshold • Same minimum format requirements as GDM

  14. Calculating the Cost Impact • Unilateral changes • Compare estimated cost to complete under old and new practices • Calculate impacts to profit, fees, and incentives based on changes to contract costs • Required or Desired Changes • Estimated change in contract costs is the basis for calculating increases to ceilings, prices, targets

  15. CAS Noncompliances • Three Types of Noncompliance • Estimating • Cost Accumulation • FAR Part 31 • Many Types of Reviews/Audits • Disclosure Statement (adequacy and compliance) • Desirable vs. Unilateral Changes • Materiality of impact • Adequacy of GDM

  16. More About the New FAR Part 30.6 • Prescribes Calculation of Cost Impacts • “Increased cost to the Government” • “Decreased cost to the Government” • “Increased costs in the aggregate” deliberately not defined • But see recent Lockheed Martin COFC case, which is likely to be appealed • CFAO discretion on Resolving Cost Impacts • Adjust a single contract, several contracts, all contracts • Or “any other suitable method”

  17. Wrap-Up • The Good • Permits retroactive changes (to beginning of FY) • Single change: Cost flows between multiple segments or implementation of a common practice among segments • Contemplates that GDM proposal may be sufficient to resolve impact • Permits submission of DCI proposal in lieu of GCM proposal • Permits negotiation of GDM/DCI formats

  18. Wrap-Up • The Bad • Difficult, if not impossible, to combine changes into one impact unless all changes increase costs to Government (vs. DoD WG 78-8) • Remedies for subcontractor issues expressly at prime contractor level

  19. Wrap-Up • The Ugly • “Affected CAS-covered contract” includes closed contracts and closed fiscal years (like TINA) • Two EACs for T&M contract types • Individual EACs for each Task Order in ID/IQ contract types • Applicability of rule to contracts awarded before April 2005 • CASB DS-1 determination of adequacy prior to award of CAS-covered contract

  20. Conclusion • Was the old process broken, or simply not well understood? • New regulations clarify some issues, but raise new problems • Gray area – “increased costs in the aggregate” – still gray • For Your Consideration • Education • Preparation • Execution

More Related