260 likes | 392 Views
Safely Delivering the Department of Energy’s Vision for the East Tennessee Technology Park Mission. Dynamic Radiological Inventory Control at the Tank W-1A Remediation Project. Presented by: Gary Coleman Jr., M.S ., Nuclear Safety Engineer
E N D
Safely Delivering the Department of Energy’s Vision for the East Tennessee Technology Park Mission Dynamic Radiological Inventory Control at the Tank W-1A Remediation Project Presented by: Gary Coleman Jr., M.S., Nuclear Safety Engineer Energy Facility Contractors Group (EFCOG) Safety Analysis Workshop May 4-10, 2012, Santa Fe, New Mexico WM-2012-0026
Dynamic Radiological Inventory Control at the Tank W-1A Remediation Project • Presented by Gary Coleman Jr. M.S., Staff Augmentation Nuclear Safety Engineering support to UCOR Oak Ridge via Energy Solutions • Co-Authored by Jerry Gnoose, M.S., Staff Augmentation Waste Coordinator support to UCOR Oak Ridge via Energy Solutions • Special Thanks to Jimmy Massey, UCOR Project Manager for the Tank W-1 A Remediation Project, and Karen Balo, UCOR Deployed Nuclear Safety Manager for the Tank W-1A Remediation Project
Background information on Tank W-1A • Tank W-1A is located within the main campus of the Oak Ridge National Laboratory (ORNL) • Tank W-1A was installed in the 1950’s, and removed from service in 1986 • While in service, Tank W-1A collected wastes from several high radiation analytical facilities at ORNL
Background information on Tank W-1A • During it’s operation, transfer lines to the tank leaked causing soil and groundwater contamination in the vicinity of the tank • Remediation has been completed, and included removal of contaminated soil, the tank, and the concrete saddles and pad that supported the tank
Methodology • Due to the close proximity of the project to other working facilities and personnel, there is a need for strict inventory control at the facility footprint • The Tank W-1A Detailed Inventory Spreadsheet (TWDIS) was constructed to control and track dynamic inventory of Tank W-1A boxes of soil and waste staged within the Tank W-1A footprint
Methodology • ALARA concerns for workers on the site - footprint limited the number of filled containers to 24 • A maximum of 6 boxes that had not been through confirmatory NDA were allowed to be on site
Methodology • The initial condition (IC) for inventory control was derived from the ALARA Design Plan, which formed the Specific Administrative Control (SAC) for inventory control • Because of the high radiation levels from the soil, it was necessary to limit the number of containers on site to prevent unacceptable exposure at the project site boundary • The Material at Risk (MAR) with the worst case 24 boxes were calculated to support the values used in the Safety Basis Hazard Evaluation (HE)
The Tank W-1A Detailed Inventory Spreadsheet • The TWDIS Spreadsheet was developed as an aid to control and track the inventory of processed boxes within the project boundary • The spreadsheet was developed and controlled in accordance with company Information Technology (IT) requirements for level 2 “Safety Significant Software” • The spreadsheet was accessed by the Waste Coordinator and two back-up designees. Others were given “Read-Only” access as needed
The Tank W-1A Detailed Inventory Spreadsheet • The TWDIS Spreadsheet contains warning notes for the user when the container count exceeds 80 % of the DSA limit • The user has advanced warning to prevent inadvertent exceedance of the respective DSA limit • There were several other warning parameters loaded into the spreadsheet, to manage inventories inside the Weather Enclosure, and outside on the facility footprint
Results • Excavation operations began in September of 2011 and concluded in April of 2012 • 316 B-25 boxes were filled, surveyed, characterized, and shipped off-site • There were no inventory control violations, as the operations crew worked very closely with the Waste Coordinator to communicate container movements in accordance with the DSA SAC’s
Conclusion • The TWDIS Spreadsheet is a cost-effective yet rigorous method for protecting the assumptions listed in the project DSA, and flowed into the operating procedures • A search of the DOE Lessons Learned system revealed several examples of radiological inventory control violations that were related to lack of vigorous controls with regards to inventory movement and control • Operations in Category 2 Nuclear Facilities should be held to the highest standards with regards to Conduct of Operations
Conclusion • The TWDIS spreadsheet is just one small example of the rigor needed to safely and effectively conclude clean-up operations at a Category 2 Nuclear Facility
References • BJC/OR-3420 Removal Action for Tank W-1A at the Oak Ridge National Laboratory, Oak Ridge, Tennessee, Project and Facility ALARA Design Review Checklist, Bechtel Jacobs Company LLC, May 2010 • DSA-OR-TW1A-0051 Rev.7, Documented Safety Analysis for the Tank W-1A (Corehole 8) Removal Action, URS/CH2M Oak Ridge (UCOR), February 2012
Thank you for your attention! • Any Questions? • I can be contacted at : gary.coleman@ettp.doe.gov