320 likes | 343 Views
Storm Water Project. ‘Proposed for co-financing under the 2007-2013 Programming Period. Structure of the Presentation. Part One Background and Context of “The Project” – originally one project area Part Two
E N D
Storm Water Project ‘Proposed for co-financing under the 2007-2013 Programming Period
Structure of the Presentation Part One • Background and Context of “The Project” – originally one project area Part Two • The Project as a National Storm Water Project – rethinking with various components Part Three • Milestones – for submitting the Project Application
(Part One)Background and Context • 2004-2006 Originated as the ‘Birkirkara-Msida Flood Relief Project’ and submitted in the OP 1 • 2006-2007 The Storm Water Master Plan focused on it as the Priority Project • 2007-2008 JASPERS assistance identified other options and carried out economic analysis • 2006 to 2008 MEPA – led us to prepare an Environmental Appraisal Report (EAR) • 2008 and on … further liaison with MEPA: rethinking original project in view of all the above
2004-2006‘Birkirkara-Msida Flood Relief Project’ • Major projects for flood relief taken by Government, especially following the September 2003 floods • Projects executed/proposed in Qormi/Marsa and Burmarrad areas while designs were developed for Birkirkara-Msida localities • Underground solution deemed most suitable for the Birkirkara-Msida areas but entailed much higher costs • Project submitted under OP 1 with targets: • Creation of infrastructure with potential of 720,000 cu m reuse • Reduction of flooding from 5 in 1 year to 1 in 5 year events 2006 Birkirkara-Msida Flood Relief Proposal
2006-2007Storm Water Master Plan (SWMP) • Contract was awarded to TAHAL in September 2006 and is still being managed under the lead of WSC • The SWMP consultants were required to harmonise ongoing projects and strategic vision of The Plan together • The SWMP focuses on Birkirkara-Msida as a priority and gives six alternatives, including tunnels and/or culverts • SWMP also makes proposals for other localities and for water conservation at larger geographical scale • SWMP Final Draft completed in November 2007 and review and final revision are also ongoing • The SEA on the SWMP was commenced in 2007 (ongoing) SWMP Birkirkara-Msida Alternatives
2007-2008 JASPERS Assistance • Reviewed TAHAL’s proposals as basis for Birkirkara-Msida project application but remarked on gaps in: • Higher level National Water Policy • SWMP strategic vision (resonating the above) • Concern over economic viability of the earlier SD and TAHAL’s proposals for Birkirkara-Msida • Identified other smaller-scale alternatives. • Options Analysis carried out on a new set of alternatives. • Economically preferred option not same as SWMP proposal • Smaller tunnels under Birkirkara-Msida and discharge to Ta’ Xbiex. Alternatives Identified for Options Analysis
2006 to 2008MEPA and the EAR • October 2006 Submission of a PDS to start EIA of the ‘Birkirkara-Msida Flood Relief Project’ as submitted in OP 1 • April 2007 - Further details with alternatives (by TAHAL) given to MEPA in a bid to obtain EIA TORs • June 2007 – Draft TORs received from MEPA – generic and all inclusive and requiring Environmental Appraisal of Alternatives and a revised PDS prior to the EIA TORs • 2008 – EAR carried out on the range of alternative studied by JASPERS (incl. SD’s and TAHAL’s main proposals): • SD’s (large tunnels) environmentally most preferable • Small tunnels + Ta’ Xbiex discharge, second best
2008 and on … • Issues pertaining to the OP 1 have arisen because of the performance targets and nature of the project vis-à-vis: • Simply resizing of the project to make it feasible brings it far below the original 720,000 cu m target for reuse. • Water conservation from Birkirkara-Msida alone has itself also been shown to be untenable, making the project a flood relief project.
Further liaison with the MEPA • Upon completion of the SWMP Final Draft and other alternatives for the Options Analysis: • Environmental implications of all sites concerned were looked into • Other (in some cases more) appropriate sites and forms of development were identified • Preliminary site assessments and draft EIA TORs if works are to be proposed on the sites • Consultative rethinking of the project
A rethinking of the original project is aimed to: • Improve Economic Feasibility by: • Limit scale of costly Birkirkara-Msida tunnels component and • Maximise on other flood relief benefits nation-wide and integrate these into water conservation interventions as far as possible • Reinforce Environmental Nature by: • Aiming at OP quantitative targets for water conservation through aquifer recharge, attainable by inter-linking catchment areas • Selecting sites with least environmental issues and best scope for integrating flood relief and water conservation • Improve Environmental Acceptability by: • Avoiding highly problematic sites altogether • Scaling down development in possibly sensitive sites • Scaling up of interventions and rehabilitation of dilapidated sites • Re-Package proposals as a National Storm Water Project
(Part Two) The National Storm Water Project ‘To manage storm water away from where it is a hazard to where it is a resource.’
Purpose and Aims A Multi-Pronged Storm Water Project that aims to: • Integrate flood relief and water conservation needs at local and national levels as far as practical • Make interventions for specific needs in seven different urban/rural areas • Develop infrastructure that is suitable for future management of catchments and watercourses • Adopt a catchment-based approach to address issues originating beyond the local level and holistically
Concerns in Urban Areas Flooding in Urban Areas • Highest levels of risk to life and property in the most densely populated areas • Need to divert concentrated water run-off efficiently • Flooding is most acute in the most developed areas due to urbanisation of original watercourse and valley beds • Most difficult to construct large storm water infrastructure • Most difficult to retain water for reuse • High levels of investment in flood prone areas • Land is scarce and expensive Urbanisation and Flood Prone Areas Flood Aftermath
Concerns in Rural Areas • Need to create and connect larger water bodies • Existing water harvesting infrastructure is scattered and difficult integrate with water reuse • Enhance water storage capacity in rural areas • Coordinate efforts aquifer recharge • Need for rehabilitation of watercourses • Mitigate problems rural and downstream urban areas • Ensure proper management and better water reuse/conservation along the watercourse • Integrated Valley Management:Wider Environmental, Social and Economic Values • Ecological rehabilitation of dilapidated sites • Creation of amenity value • Tourism, Recreation and Cultural heritage • Scientific Importance and education Flooding in non-urban areas Catchment Areas and Water Reuse Infrastructure
Project Components Geographic Scope • Focuses mainly on seven large basins: • Includes specific flood relief and water conservation measures depending on locality and catchment conditions • Controls the risks and damages associated with flash floods and storm events of up to 1 in 5 year magnitude with direct benefits to between 4 and 5 % of the population. • Integrates flood relief with water conservation to enhance water harvesting and recharge potential of Malta's largest catchments by more than 2 million cu m per annum.
Birkirkara-Msida • Mainly for the protection of life and property in the densely populated Birkirkara, Msida, Balzan and other localities • Also minimise inconvenience and traffic congestion during and after average rain events for the larger population • Provide scope for selective harvesting of runoff, and link to other catchments for aquifer recharge Counted Dependent on other catchments 1200 3,300 150,000 200,000 45,000,000 19,300,000
Attard-Qormi • Flood relief in the lower Qormi urban area • Retention and aquifer recharge form Wied Incita Quarries • Rehabilitation, locally distributed water storage and recharge along Wied is-Sewda • Dispersion of runoff from adjacent Birkirkara-Msida catchment Estimated 1740 5,400 10,000 1,052,000 2,088,000 14,650,000 6,300,000
Zebbug-Marsa • Eliminate flooding in the Zebbug centre area • Minimise inconvenience and traffic congestion during and after average rain events • Provide scope for water conservation and reuse, and rehabilitate Wied Qirda and Wied il-Kbir Estimated 620 2,200 10,000 51,000 40,000 2,250,000 966,000
Mosta-Burmarrad • Reduce the impact of flash floods on the Burmarrad agricultural flood plain of this large catchment • Reinstate the life-supporting and water retaining capacities of the upper water course in Wied il-Qlejgha • Mitigate damages of large storms to infrastructure • Minimise inconvenience and traffic congestion after storm events • Provide greater scope for water conservation and reuse Agricultural 1.5 sq km 250 50,000 45,000 90,000 5,000,000 2,150,000
Zabbar-Marsascala • Flood relief of parts of Zabbar and Marsascala • Minimise inconvenience and traffic congestion during and after average rain events • Creation of storage infrastructure in proximity to agricultural areas between Zabbar and Marsascala • Rehabilitation of part of the original valley Estimated Depends on valley rehabilitation 430 3,800 13,000 28,000 2,390,000 1,025,000
Gzira • Reduce risks to life and damages to property and infrastructure of Gzira urban areas • Minimise inconvenience and traffic congestion during normal rain events • Connect to Birkirkara-Msida catchment to provide for additional flood relief and scope for water conservation Estimated 530 2,000 30,000 12,000 24,000 1,845,000 792,000
Birzebbugia • Reduce frequency of flooding of urban thoroughfare are • Minimise inconvenience and traffic congestion during normal rain events • Provide greater scope for water conservation Estimated 190 900 3,000 10,000 20,000 215,000 19,300,000
Benefits and Costs of the Seven Project Components • Flood relief benefits to property and population • Benefits to water conservation • Other social and environmental benefits • Estimated Costs
Milestones for the Project Application (Part Three) • Project Definition • Project Acceptance • PDS, EIA TORs, and EIA Contract • Technical Input, Feasibility Study, CBA • National Water Policy Framework • First Review of the SWMP
Milestones for the Project Application imminent decisions • Project Definition – National LevelFinalise the Country’s Proposal: • Geographical Scope, Purpose and Project Components • Project Acceptance – EU LevelNegotiate Changes to the OP 1 Proposal: • Targets in OP 1 attainable over wider geographic domain • Water reuse targets attainable through aquifer recharge • Wider flood mitigation measures
Milestones for the Project Application completion of prerequisite studies • PDS, EIA TORs, and EIA ContractMove on with the MEPA: • Submit a comprehensive PDS covering ALL components • Issue EIA tender and finalise TORs prior to award • Technical Input, Feasibility Study, CBA • Technical refinement of theproposals (parallel with EIA) • Feasibility study and Cost-Benefit Analysis • Finalise proposal with EIA and fill in the application
Milestones for the Project Application in tandem with the precedent activities • National Water Policy FrameworkClarify vision and context for execution and operation • Set out strategic goals, objectives, measures and actions • Establish institutional and organisational set-ups • Legal and financial arrangements • First Review of the SWMPResume iterative planning process and coordinate the Plan with: • The Framework of the National Water Policy • Feedback from the SEA • Refinements in project components based on appraisal studies
Milestones for Submitting the Project Application Envisaged Targets