200 likes | 295 Views
Combining offshore wind and interconnection Paul Cooley. Who is SSE?. Parent company of Airtricity UK’s broadest based energy company Energy Networks £4.7bn (RAV) Energy Supply 9 million customers Generation Over 10,700MW
E N D
Combining offshore wind and interconnection Paul Cooley
Who is SSE? • Parent company of Airtricity • UK’s broadest based energy company • Energy Networks £4.7bn (RAV) • Energy Supply 9 million customers • Generation Over 10,700MW • Renewable Generation Over 2,200MW(wind, hydro, biomass)
3.5GW renewable portfolio UK and Ireland • Plus 1.5GW either under construction or consented
Interconnected HVDC/AC pan-European grid • Vision of pan-European grid will inevitably require significant offshore grid development • Concentrations of HVDC terminals, offshore wind parks and increased interconnection • Fundamental shift in how we view offshore transmission grids
Den Helder Site • 14km by 13km offshore wind farm site located ~100km off the Dutch coast and ~150km off the UK coast • Four phases of construction (468MW already consented) leading to a total capacity of approx. 1.8GW • Construction 2012 - 2015 • Connection Study • Identify potential points of common coupling with existing grid systems • Four solutions considered; two in the UK and two in the Netherlands • Conceptual modular design and costing for the offshore collector arrays, offshore substations, transmission link and onshore substations • Technical and economic feasibility of the HVDC connection options and set against AC alternatives • Identified opportunity to integrate connection of wind farm with interconnector.
Why are offshore supergrids not developing? • Lack of regulatory framework and alignment between member states - licencing, legal framework etc • Member states focused on meeting national targets • Differing trading and green certificate mechanisms within EU • Difficulty in defining long term economic benefits at the project level
+ + - - + + - - Shetland Blackhillock
Opportunity – Den Helder as test case • Unique interface issues between UK and NL regulatory regimes • OFTO • Green Certs/ROCs • Interconnector licensing • EU/UK interface issues common to any North Sea or Irish Sea developments • 1.8GW site mid-way between two EU states • Economics of scale and distance justify interconnection • UK/Scotland - very large on & offshore wind penetration (30GW by 2020) • NL on and offshore wind developing rapidly – 6GW by 2020 • Existing interconnection with NL • Onshore grid challenges
Difficulties • Technical • Technology available but detail examination required • Some level of alignment – role for ENTSO-E? • Licensing • OFTO vs Interconnection vs TSO • Multiple licenses for same project? • Need to define boundaries & interfaces – role for ACER? • Markets • Scenarios demonstrate complex power flows • Actual power flow vs movement of green certificates • Metering points & arrangements critical
Options • Use existing legislation & regulatory framework • Modify existing arrangements • Create new arrangements specific to integrated offshore wind/interconnection hybrid • Timescale critical…..& • Need a solution which fits with all previous scenarios
Path Forward Scope document completed Working group with key stakeholders Analysis of existing arrangements Proposal paper from SSE/Airtricity