An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Report on SWGWTP Deep Well Drilling Phase 2 September 9, 2009

  2. SWGWTP Deep Wells Ph. 2 Engineer: Carollo Engineers with Bowen Collins & Assoc. Supplier: Zim Industries, Inc. Contract Award Date: 2/13/2008 Original Contract Amount: $1,097,300 Final Contract Amount: $1,118,451.50

  3. SWGWTP Deep Wells Ph. 2 Change Order #1: $6,100 – DW7 final well design Change Order #2: $5,600 – DW7 Additional development Change Order #3: $3,040 – Additional well videos Change Order #4: $39,169 – DW6 Final well design Change Order #5: $9,440 – Additional air-lift development Change Order #6: ($41,797.50) – Project closeout

  4. SWGWTP Deep Wells Ph. 2 DW6 – 9911 S. 2700 W. Depth: 602’ Feet of Screen: 152’ Diameter: 16” 24-hour Pump Test: 1,380 GPM Equipped Flow Rate: 800 GPM

  5. SWGWTP Deep Wells Ph. 2 DW7 – 10940 S. 2700 W. Depth: 645’ Feet of Screen: 179’ Diameter: 16” 24-hour Pump Test: 2,400 GPM Equipped Flow Rate: 1,500 GPM