1 / 14

LS Power

LS Power. Great Basin Transmission, LLC (GBT) Southwest Intertie Project. February 2010. LS Power. LS Power is a power generation and transmission group. Power Generation. Transmission. Acquisition. Over 20,000 MW of development, construction, or operations experience

corin
Download Presentation

LS Power

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LS Power Great Basin Transmission, LLC (GBT) Southwest Intertie Project February 2010

  2. LS Power • LS Power is a power generation and transmission group Power Generation Transmission Acquisition • Over 20,000 MW of development, construction, or operations experience • Active development of renewable and fossil generation resources • Advanced development of 500+ mile, 500-kV Southwest Intertie Project • Designated to build 200+ miles of 2-345 kV in Texas to support renewable resources • Active development of transmission infrastructure • Over $4 billion in private equity capital dedicated to energy sector • Acquired ~ 15,000 MW of power generation Functional Expertise Project Development Licensing & Environmental Regulatory & Transmission Power Marketing Project Finance Construction & Operations

  3. Project Portfolio

  4. Western Transmission Projects • Southwest Intertie Project (SWIP) • Southern Nevada Intertie Project (SNIP) • Overland Transmission Project (OTP) • Wyoming-Colorado Intertie (WCI)

  5. Southwest Intertie Project (SWIP) • Great Basin Transmission, LLC • 510-mile 500 kV AC line • ~2,000 MW of transfer capability • MOUs with Western Area Power Administration and NV Energy (NVE) • Target in service 2012 Idaho Midpoint Nevada Robinson Summit Harry Allen

  6. Southern Nevada Intertie Project (SNIP) Nevada Harry Allen Eldorado • Great Basin Transmission, LLC • ~60 mile 500 kV AC line running between Harry Allen and Eldorado 500 kV Stations • ~2,000 MW of transfer capability • Target in service 2013

  7. Overland Transmission Project • Jade Energy Associates, LLC • ~560-mile long 500 kV± DC line running between southeast Wyoming and southern Idaho • ~2,000-3,000 MW of transfer capability • Target in service 2015 The ROW routes shown on this diagram are for illustrative purposes only and may not depict the actual route that could eventually be selected. The substation locations may also be modified.

  8. Wyoming-Colorado Intertie Project • Wyoming Colorado Intertie, LLC • ~180-mile long 345 kV AC line running between southeast Wyoming and Colorado front range • ~850 MW of transfer capability • Public-private partnership with WIA and with the assistance of Western • Target in service 2015

  9. GBT Projects in the SSPG Footprint Southwest Intertie Project (SWIP) Southern Nevada Intertie Project (SNIP)

  10. Idaho Midpoint Nevada Robinson Summit SWIP Harry Allen SNIP Eldorado SWIP/SNIP Stations and Segment Lengths SWIP • Southern Portion Harry Allen – Robinson Summit (235 miles) • Northern Portion Robinson Summit – Midpoint (275 miles) SNIP • Harry Allen – Eldorado (60 miles)

  11. SWIP Phases

  12. SWIP/SNIP Plan of Service (Proposed) Phase I • SWIP-South/ON Line (New) • ~ 235 mi 500kV AC Line • Fold-in of NVE’s Falcon-Gonder 345 kV Line to New Robinson Summit Station • Series Compensation on Falcon-Robinson Summit 345 kV Line • 600+ MW Rating Phase II • SWIP-South/ON Line (Additions) • 70% Series Compensation • 2-345kV PST on Falcon-Gonder Line • SVC at Robinson Summit • ~2000 MW Rating • SWIP-North and SNIP (New) • ~ 275 mi 500kV AC Line (SWIP-North) and 60 mi 500kV AC Line (SNIP) • 70% Series Compensation • ~2000 MW Rating

  13. SWIP Status • Commercial Arrangements • MOU/Term Sheet with NV Energy as anchor shipper and co-owner of SWIP-South • MOU/Term Sheet with Western Area Power Administration for financing under the Recovery Act of 2009 • Negotiating contracts for sale of excess capacity pursuant to Open Season • Southern Portion • Performing final design • Bidding construction and supply contracts • Phase II of WECC Rating Process • Target construction start – Q3 2010 • Target in-service – Q4 2012 • Northern Portion • Finalizing BLM COM Plan • Finalizing real estate acquisition in Idaho • Phase II of WECC Rating Process • Target construction start – 2011 • Target in-service – 2013

  14. SNIP Status • Ongoing Activities • Real estate acquisition • Engineering studies • Biological field studies • Interaction with local government agencies • Initial UEPA permit application filed with Public Utilities Commission of Nevada • Next Steps • Complete real estate acquisition • BLM Environmental Assessment & Right-of-Way Grant • Local special use permits • UEPA permit from Public Utilities Commission of Nevada • Target construction start – 2011 • Target in-service – 2013