E N D
1. IAEA.PNRA.05.05 Stetkar & Associates 1 INITIATING EVENTS GROUPING by
John W. Stetkar
Presented to
National Training Course on Probabilistic Safety Assessment
Islamabad, Pakistan
May 2 - 6, 2005
IAEA Project C7-PAK/9/028-001
2. IAEA.PNRA.05.05 Stetkar & Associates 2 GROUPING OF INITIATING EVENTS PLANT THERMAL / HYDRAULIC RESPONSE
FUNCTIONAL SUCCESS CRITERIA
SYSTEM SUCCESS CRITERIA
SUPPORT SYSTEM IMPACTS
OPERATOR ACTIONS
LEVEL 2 PSA IMPACTS
3. IAEA.PNRA.05.05 Stetkar & Associates 3 NUMERICAL SCREENING
4. IAEA.PNRA.05.05 Stetkar & Associates 4 NUMERICAL SCREENING MOST MODERN PSAs INCLUDE FAIRLY "STANDARD" SET OF INITIATING EVENTS FROM FRONTLINE SYSTEM FAILURES (TRANSIENTS, LOCAs, ETC.)
NUMERICAL ARGUMENTS TYPICALLY USED TO LIMIT SCOPE OF SUPPORT SYSTEM INITIATING EVENTS AND EXTERNAL INITIATING EVENTS
NUMERICAL CRITERIA ARE OFTEN NOT JUSTIFIED OR ARE NOT CONSISTENT WITH QUANTIFICATION OF OTHER PSA INITIATING EVENTS
SIGNIFICANT PROBLEM IN SOME REVIEWS
5. IAEA.PNRA.05.05 Stetkar & Associates 5 NUMERICAL SCREENING CANNOT BE JUSTIFIED ONLY BY ESTIMATED INITIATING EVENT FREQUENCY
MUST CONSIDER RISK CONSEQUENCES
LEVEL 1 PSA MODELS / SUCCESS CRITERIA
OPERATOR ACTIONS
LEVEL 2 PSA CONSEQUENCES
RISK CONTRIBUTORS
HIGH FREQUENCY / LOW CONSEQUENCES
MEDIUM FREQUENCY / MEDIUM CONSEQUENCES
LOW FREQUENCY / HIGH CONSEQUENCES
6. IAEA.PNRA.05.05 Stetkar & Associates 6 NUMERICAL SCREENING - LIVING PSA IMPROVED PSA MODELS AND NUMERICAL RESULTS
REFINED THERMAL / HYDRAULIC ANALYSES
REFINED SUCCESS CRITERIA
OPERATOR RECOVERY ACTIONS
IMPROVED DATA
SCREENING BASED ON PRELIMINARY MODELS / RESULTS OFTEN NOT VALID FOR FINAL MODELS / RESULTS
MUST CONSISTENTLY REEVALUATE SCREENING CRITERIA AFTER EVERY PSA UPDATE
7. IAEA.PNRA.05.05 Stetkar & Associates 7 NUMERICAL SCREENING** GENERAL RULE ** QUANTIFY THE INITIATING EVENT
LET THE PSA MODELS CONFIRM ITS ACTUAL SIGNIFICANCE
8. IAEA.PNRA.05.05 Stetkar & Associates 8 NUMERICAL SCREENINGPERSPECTIVES The 7 astronauts aboard the space shuttle Challenger would have been very thankful for a realistic assessment of the risk from low temperature failures of "passive" O-rings.
The 229 passengers and crew aboard Swissair Flight 111 would have been very thankful for a realistic assessment of the risk from pilot performance and ground personnel decisions during a specific type of small, localized fire scenario.
9. IAEA.PNRA.05.05 Stetkar & Associates 9 NUMERICAL SCREENINGPERSPECTIVES The 69 passengers and crew (52 children) aboard Bashkir Airlines Flight 2937 and the 2 DHL cargo plane pilots would have been very thankful for a realistic assessment of the integrated risk from maintenance of collision avoidance systems, air traffic control personnel actions, and pilot responses to automatic alarms.
The 7 astronauts aboard the space shuttle Columbia would have been very thankful for a realistic assessment of the risk from impacts by "insignificant" pieces of insulation.
10. IAEA.PNRA.05.05 Stetkar & Associates 10 INITIATING EVENT GROUPS
11. IAEA.PNRA.05.05 Stetkar & Associates 11 GROUPING PRINCIPLES GROUPS IMPROVE PSA MODELING AND QUANTIFICATION EFFICIENCY
GROUPS DECREASE PSA DETAIL
COMBINE INDIVIDUAL INITIATING EVENTS INTO FUNCTIONAL GROUPS
GROUP FREQUENCY = SUM OF INDIVIDUAL INITIATING EVENT FREQUENCIES
GROUP PSA IMPACTS = MOST LIMITING COMBINED IMPACTS FROM ALL INDIVIDUAL INITIATING EVENTS
12. IAEA.PNRA.05.05 Stetkar & Associates 12 GROUPING PRINCIPLES(continued) FOCUS ON INTEGRATED IMPACTS FROM EACH INITIATOR
PLANT RESPONSE
PSA SUCCESS CRITERIA
IMPACT ON PSA SYSTEMS
IMPACT ON PSA OPERATOR ACTIONS
"CONSERVATIVE CONDENSATION"
COMBINE LOWER FREQUENCY, LESS SEVERE INITIATORS WITH HIGHER FREQUENCY, MORE SEVERE INITIATORS
USE WITH CAUTION
13. IAEA.PNRA.05.05 Stetkar & Associates 13 GROUPING PRINCIPLES*** CAUTIONS *** DO NOT FOCUS ONLY ON TURBINE TRIP OR REACTOR TRIP SIGNALS AS BASIS FOR GROUPING
DO NOT COMBINE SUPPORT SYSTEM INITIATING EVENTS WITH FRONTLINE INITIATORS
BEWARE OF LEVEL 2 PSA IMPACTS – NEED TO SUBDIVIDE GROUPS FOR LATER ANALYSES
IF THERE ARE ANY QUESTIONS, QUANTIFY INITIATING EVENTS SEPARATELY
14. IAEA.PNRA.05.05 Stetkar & Associates 14 CONSEQUENTIAL IMPACTS INITIATING EVENT STARTS SERIES OF POSSIBLE RESPONSES
EQUIPMENT SUCCESSES / FAILURES
OPERATOR ACTIONS
DO NOT COMBINE INITIATOR AND CONSEQUENCES
THE FOLLOWING CONSEQUENTIAL CONDITIONS ARE NOT INITIATING EVENTS
STATION BLACKOUT
ATWS
INDUCED LOCAs
OVERCOOLING
15. IAEA.PNRA.05.05 Stetkar & Associates 15 TRANSIENTS AND LOCAS TOO MUCH EMPHASIS ON LOCAS
SIZE, LOCATION, FREQUENCY
COMPLEX SUCCESS CRITERIA
TOO LITTLE EMPHASIS ON TRANSIENTS
BROAD INITIATING EVENT GROUPS
TREATMENT OF TRANSIENT-INDUCED IMPACTS
SCOPE OF SUPPORT SYSTEM INITIATING EVENTS
FULL-SCOPE LEVEL 1 PSA RESULTS OFTEN DOMINATED BY TRANSIENTS AND SUPPORT SYSTEM FAILURES
16. IAEA.PNRA.05.05 Stetkar & Associates 16 TRANSIENT-INDUCED IMPACTS PRIMARY OVERPRESSURE
SECONDARY OVERPRESSURE
OVERCOOLING
ATWS
MAKEUP / LETDOWN
REACTOR COOLANT PUMP SEAL FAILURE
ENVIRONMENTAL / PHYSICAL DAMAGE
CONTAINMENT
17. IAEA.PNRA.05.05 Stetkar & Associates 17 LEVEL 2 PSA IMPACTS ENERGY RELEASE INTO CONTAINMENT
CONTAINMENT HEAT REMOVAL
CONTAINMENT BYPASS
CONTAINMENT ISOLATION
18. IAEA.PNRA.05.05 Stetkar & Associates 18 COMMON PROBLEMS / CONSIDERATIONS LOSS OF MAIN CONDENSER VACUUM
LOSS OF MAIN CONDENSATE
LOSS OF MAIN FEEDWATER
LOSS OF TURBINE BYPASS STEAM RELIEF
FEEDWATER CONTROL / ISOLATION VALVE FAILURES
PARTIAL / TOTAL LOSS OF MAIN FEEDWATER
PARTIAL / TOTAL LOSS OF STARTUP / STANDBY FEEDWATER
POSSIBLE IMPACT ON EMERGENCY FEEDWATER
19. IAEA.PNRA.05.05 Stetkar & Associates 19 COMMON PROBLEMS / CONSIDERATIONS(continued) BOUNDARY BETWEEN OFFSITE AND ONSITE POWER
GRID / TRANSMISSION LINES / SWITCHYARDS
MAIN / AUXILIARY / STANDBY TRANSFORMERS
IN-PLANT BUSWORK
POTENTIAL POWER RECOVERY
IMPROPER GROUPING OF AC AND DC POWER FAILURES
AC AFFECTS MOTIVE POWER
DC AFFECTS INSTRUMENTATION, ACTUATION SIGNALS, AUTOMATIC / MANUAL CONTROLS
20. IAEA.PNRA.05.05 Stetkar & Associates 20 COMMON PROBLEMS / CONSIDERATIONS(continued) IMPROPER GROUPING OF ELECTRIC POWER FAILURES WITH FRONTLINE SYSTEM FAILURES
IMPROPER GROUPING OF COOLING WATER FAILURES WITH "MOST IMPORTANT" COOLING LOADS
IMPROPER GROUPING OF HARDWARE FAILURES WITH EVENTS THAT INCLUDE CREDIT FOR OPERATOR ACTIONS
IMPROPER GROUPING OF INTERFACING SYSTEM LOCAs WITH LOCAs INSIDE CONTAINMENT
21. IAEA.PNRA.05.05 Stetkar & Associates 21 NUMBER OF INITIATING EVENTS IMPROVED PSA SOFTWARE AND HARDWARE REDUCE NEED FOR INITIATING EVENT GROUPING
INCREASED USE OF RISK-INFORMED PSA APPLICATIONS OFTEN REQUIRES MORE DETAILED ANALYSIS OF SPECIFIC INITIATING EVENTS
NUMBER OF INITIATING EVENTS / GROUPS DEPENDS ON PLANT-SPECIFIC CONSIDERATIONS
MANY MODERN PSAs QUANTIFY 25 TO 50 SEPARATE INTERNAL INITIATING EVENTS (GROUPS + INDIVIDUAL INITIATORS)
22. IAEA.PNRA.05.05 Stetkar & Associates 22 ELECTRIC POWERINITIATING EVENT EXAMPLE
23. IAEA.PNRA.05.05 Stetkar & Associates 23 EXAMPLE ELECTRIC POWER SYSTEM
24. IAEA.PNRA.05.05 Stetkar & Associates 24 EXAMPLE ELECTRIC POWER SYSTEMOFFSITE POWER CONNECTIONS 220KV TRANSMISSION LINES (3)
220KV SWITCHYARD (2 BUSES)
MAIN TRANSFORMER (18KV / 220KV)
MAIN GENERATOR OUTPUT BREAKER (220KV)
SERVICE TRANSFORMER (220KV / 6KV)
STARTUP / STANDBY TRANSFORMER (220KV / 6KV)
25. IAEA.PNRA.05.05 Stetkar & Associates 25 EXAMPLE ELECTRIC POWER SYSTEMIN-PLANT 6KV BUSES "NON-ESSENTIAL" BUSES
SERVICE BUS 2160
SERVICE BUS 2161
COMMON BUS 2160
COMMON BUS 2161
"SAFETY-RELATED" BUSES
SAFEGUARDS BUS 2160
SAFEGUARDS BUS 2161
26. IAEA.PNRA.05.05 Stetkar & Associates 26 EXAMPLE ELECTRIC POWER SYSTEMNORMAL POWER ALIGNMENT SERVICE BUSES
NORMAL SUPPLY FROM SERVICE TRANSFORMER
BACKUP SUPPLY FROM STARTUP / STANDBY TRANSFORMER VIA COMMON BUSES
COMMON BUSES
ONLY SUPPLY FROM STARTUP / STANDBY TRANSFORMER
SAFEGUARDS BUSES
NORMAL SUPPLY FROM STARTUP / STANDBY TRANSFORMER VIA COMMON BUSES
BACKUP SUPPLY FROM DIESEL GENERATORS
27. IAEA.PNRA.05.05 Stetkar & Associates 27 EXAMPLE ELECTRIC POWER SYSTEM INITIATING EVENT CONSIDERATIONS LOSS OF OFFSITE POWER INITIATING EVENT
REGIONAL GRID
220KV TRANSMISSION LINES
220KV SWITCHYARD
OFFSITE POWER RECOVERY MODELS AND DATA
FAILURE OF MAIN TRANSFORMER
EQUIVALENT TO MAIN TURBINE-GENERATOR TRIP
FAILURE OF GENERATOR OUTPUT BREAKER DISABLES SERVICE TRANSFORMER SUPPLY
28. IAEA.PNRA.05.05 Stetkar & Associates 28 EXAMPLE ELECTRIC POWER SYSTEM INITIATING EVENT CONSIDERATIONS FAILURE OF SERVICE TRANSFORMER
LOSS OF NORMAL POWER TO SERVICE BUSES 2160 AND 2161
SERVICE BUSES REQUIRE ACTIVE POWER TRANSFER FROM COMMON BUSES
POWER SUPPLY CANNOT BE RECOVERED QUICKLY
29. IAEA.PNRA.05.05 Stetkar & Associates 29 EXAMPLE ELECTRIC POWER SYSTEM INITIATING EVENT CONSIDERATIONS FAILURE OF STARTUP / STANDBY TRANSFORMER
LOSS OF NORMAL POWER TO COMMON BUSES 2160 AND 2161
SERVICE BUSES REQUIRE NORMAL POWER FROM SERVICE TRANSFORMER
SAFEGUARDS BUSES REQUIRE POWER FROM DIESEL GENERATORS
POWER SUPPLY CANNOT BE RECOVERED QUICKLY
30. IAEA.PNRA.05.05 Stetkar & Associates 30 EXAMPLE ELECTRIC POWER SYSTEM INITIATING EVENT CONSIDERATIONS FAILURE OF SERVICE TRANSFORMER AND STARTUP / STANDBY TRANSFORMER
ELECTRICALLY EQUIVALENT TO LOSS OF OFFSITE POWER
COMMON BUSES AND SERVICE BUSES DEENERGIZED
SAFEGUARDS BUSES REQUIRE POWER FROM DIESEL GENERATORS
POWER SUPPLY CANNOT BE RECOVERED QUICKLY
31. IAEA.PNRA.05.05 Stetkar & Associates 31 EXAMPLE ELECTRIC POWER SYSTEM INITIATING EVENT CONSIDERATIONS FAILURE OF SERVICE BUS
DISABLES ALL BUS LOADS
POWER SUPPLY CANNOT BE RECOVERED QUICKLY
FAILURE OF COMMON BUS
DISABLES ALL BUS LOADS
DISABLES ALTERNATE SUPPLY TO SERVICE BUS
DISABLES NORMAL SUPPLY TO SAFEGUARDS BUS
POWER SUPPLY CANNOT BE RECOVERED QUICKLY
32. IAEA.PNRA.05.05 Stetkar & Associates 32 EXAMPLE ELECTRIC POWER SYSTEM INITIATING EVENT CONSIDERATIONS FAILURE OF SAFEGUARDS BUS
DISABLES ALL BUS LOADS
POWER SUPPLY CANNOT BE RECOVERED QUICKLY