T-76.4115 Iteration Demo. Tempus PP-Iteration 17.10.2005. Project status ( 15 min) achieving the goals of the iteration Timeline mostly met Core use cases defined Documentation available Tools in use (Wiki, Dotproject) Project group formed and responsibilities and main roles defined
E N D
T-76.4115 Iteration Demo Tempus PP-Iteration17.10.2005
Project status (15 min) achieving the goals of the iteration Timeline mostly met Core use cases defined Documentation available Tools in use (Wiki, Dotproject) Project group formed and responsibilities and main roles defined Project architechture Development environment mostly defined project metrics Timeline Reported working hours Work results (10 min) presenting the iteration’s results Documentation Use cases Research Technologies Used work practices (10 min) Agenda
Introduction to the project • What is this project about? • The main goal of this project is to develop, test, document and deliver a SIP-based calendar solution for the customer, Nokia Research Center. • Developed by extending the open source Mozilla Calendar Project • Design is based on IEFT SIP calendaring event draft, which will most likely be revised as the project progresses.
Status of the iteration’s goals • Define the main roles of the project group • ok • Understand the domain, especially SIP and network calendaring • ok • Understand the goals of the project • ok • Define the core requirements on a high level • ok • Perform as much additional requirements work as possible • Not much achieved • Plan and set up the process infrastructure such as working and communication methods • Mostly ok • Set up the technical infrastructure such as servers and software tools • ok
Status of the iteration’s deliverables • Project plan • OK • Requirements document • Only contains proposed core requirements • Quality handbook • Ok for this iteration, still needs work • Risk Management Plan • Ok for this iteration, ongoing process
Working hours by person Realized hours in this iteration • Reporting problems with the Dotproject system may have lost hours. This is being worked on.
Quality assessment Legend Coverage: 0 = nothing 1 = we looked at it 2 = we checked all functions 3 = it’s tested Quality: J = quality is good K = not sure L = quality is bad