1. Lifter Project By:
Ryan Matsui, Justin Carland,
Indar Lange, Derek Hanson
2. Objectives Successfully build a working Lifter
Explain the unknown phenomenon
Take Physical properties learned to engineer and solve problems at hand.
Improve on existing engineering design
3. Theories Biefeld-Brown effect
Ionic-Wind
Electrogravitics
4. Preparation In-depth research on what is already known on the lifter.
Materials
Safety practices- check list of things to do before and after experiments
5. SafetyHigh Voltage All Metal Removed From Body
Electrically Insulated Flooring
Wooden Safety Rod
De-energizing Switch Nearby
A Labeled Designated Area For Testing
Fire Extinguisher
First Aid Kit Available
Cellphone Designated for 911
A Person Designated for CPR
6. Issues Weight
Environmental
Shape
Limitation on altitude.
Maneuverability
7. Timeline Sep. 19 - Prototypes built
Oct. 5 - Conduct experiment with full assembly
Oct. 19 – Troubleshoot and Test
Nov. 2 – Data acquisition
Nov. 16 - Improve Lifter (Shape, weight, height of flight)
Dec. 8 - Final Due date
8. Aloha
Thank you!
Questions anyone…