Ottawa County Drain Commissioner PARK WEST DRAINPark Township, Ottawa County, Michigan Project Information Meeting August 4, 2011
PARK WEST DRAIN Final Route Project Schedule Estimated Cost Apportionment Methodology
FINAL ROUTE • Outlet at Winstrom Creek • Perry St • 168th Ave • Riley St • Greenly St • Quincy St • Estate Dr • 160th Ave
FINAL ROUTE • 21 Easements • Project Length • Trunkline Pipe – 5.5 Miles • Branch Pipe – 2.5 Miles • Ditches – 7.5 Miles • Total – 15.5 Miles
PROJECT SCHEDULE Three Phases
PROJECT SCHEDULE • Phase I • Spring 2012 • Work Includes: • Perry St • 168th Ave • Power Line Easement • Portions of Riley St, Greenly St, & 160th Ave
PROJECT SCHEDULE • Phase II • Winter 2012-2013 • Work Includes: • Ottawa Beach Rd Crossing • Sediment Basins
PROJECT SCHEDULE • Phase III • Spring 2013 • Work Includes: • Inlets on 168th Ave • Riley St • Greenly St • Quincy St • Estate Drive • 160th Ave
ESTIMATED COST • $5.9 million • Construction • Engineering • Easement/Property Acquisition • Legal/Administrative Costs
APPORTIONMENT METHODOLOGY • Costs paid by: • Park Township at-large • Ottawa County at-large • Landowners
APPORTIONMENT METHODOLOGY • Benefit Factors • Location • Land Use • Parcel Size • Stormwater Management
APPORTIONMENT METHODOLOGY • Apportionment will be based on: • Acreage Within District • Composite Benefit Factor