1 / 32

e POH Inc.

e POH Inc. . Consultants: Hope Baumgarner Tyler Gibson Wes Hudkins Joseph Nick Josh Stephens. e POH Inc. . Addition of a Cylcohexane Production Process to Independent Refineries Inc. Overview: Based on our findings for project 3, the addition of the cyclohexane unit is not profitable

dacia
Download Presentation

e POH Inc.

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ePOH Inc. Consultants: Hope Baumgarner Tyler Gibson Wes Hudkins Joseph Nick Josh Stephens

  2. ePOH Inc. Addition of a Cylcohexane Production Process to Independent Refineries Inc. • Overview: • Based on our findings for project 3, the addition of the cyclohexane unit is not profitable • Large price increase in cyclohexane would be required to make process profitable • Current market value Cyclohexane: $4.10/gal • For process to be profitable price would have to be 5 times the current market value Project 3

  3. ePOH Inc. Addition of a Cylcohexane Production Process to Independent Refineries Inc • Economic Analysis: • Total Capital Investment: TCI = FCI + WC =$4,690,000 • Fixed Capital Investment: FCI = DC + IC = $3,640,000 • Annual Product Cost: $243 MM to $357 MM when a 4% inflation rate is taken into account • Process considered profitable when ROR > 8% • Annual Cash Flow: CF = (S-C) x (1-Φ)+dΦ Project 3

  4. ePOH Inc. Addition of a Cylcohexane Production Process to Independent Refineries Inc • Economic Analysis: • Annual Cash Flow: Project 3

  5. ePOH Inc. Addition of a Cylcohexane Production Process to Independent Refineries Inc • Economic Analysis: • Net Present Worth: Criterion used to determine profitability • Payout Time: Time required to recover investment • Positive values indicate that investment will be recovered • Negative values indicate investment will not be recovered • Return on Investment: Describes how much money is earned per dollar invested • When ROI>ROR the process is profitable Project 3

  6. ePOH Inc. Addition of a Cylcohexane Production Process to Independent Refineries Inc Economic Analysis: Project 3

  7. ePOH Inc. Addition of a Cylcohexane Production Process to Independent Refineries Inc • Equipment Cost & Specifications • Mixer & Splitter: • Diameter = 4.9 ft • Height = 19.6 ft • Volume = 185 ft3 • Material: Carbon Steel • Cost included in the piping cost • Heat Exchangers: • Shell & Tube • Carbon Steel tubes and shell Project 3

  8. ePOH Inc. Addition of a Cylcohexane Production Process to Independent Refineries Inc Equipment Cost & Specifications: Project 3

  9. ePOH Inc. Addition of a Cylcohexane Production Process to Independent Refineries Inc • Equipment Cost & Specifications: • Flash Tank: • Vertical liquid gas gravity settling separator • Cross sectional area: 57 ft2 • Tank Diameter: 9 ft • Cost: $81,000 Project 3

  10. ePOH Inc. Addition of a Cylcohexane Production Process to Independent Refineries Inc • Equipment Cost & Specifications: • Reactor: • Tubular reactor • 30 tubes • L= 20 ft • OD = 3 inches • 40% of the cross sectional area dedicated to tubes • Cost: $9,000 • Compressor: • Power Requirement: 53 kW • Adiabatic Efficiency: 80% • Type: Centrifugal • Cost: $80,000 Project 3

  11. ePOH Inc. Addition of a Cylcohexane Production Process to Independent Refineries Inc • Equipment Cost & Specifications: • Distillation Column, Condenser & Reboiler: • Size based on estimated superficial velocity for flooding to occur • Operation 80% of vapor speed • Based on Perry’s Chemical Engineer’s Handbook it suggest that about 15% of total cross sectional area be devoted to downcomer envelope • Number of Trays: 28 • Reboiler: Specified as a kettle Project 3

  12. ePOH Inc. Addition of a Cylcohexane Production Process to Independent Refineries Inc • Equipment Cost & Specifications: • Distillation Column, Condenser & Reboiler: • Column Cost: $140,000 • Condenser Cost: $40,300 • Reboiler Cost: $515,600 • Total Cost: $781,400 Project 3

  13. ePOH Inc. Fluid Transport and Economic Analysis • Design of the pipe network • Stainless Steel • Currently operating at unsafe pressures • Pipes need to be increased to schedule 80 • Piping dimensions proposed by IRI found to be less than optimal • ePOH’s recommendations could save $500,000 • Adding fiberglass insulation will decrease NPW by $1 million Project 4

  14. ePOH Inc. • Two-phase flow • Pro II was used to determine what flow regimes are inside the two-phase flow pipes in the process • The Reynolds number was calculated for single phase flow from the thermodynamic parameters given by Pro II, and then the flow regimes for the two-phase streams were taken from the simulation report • All the single-phase streams are in the turbulent flow regime, and all the two-phase flow streams are in the stratified wavy flow regime Fluid Transport and Economic Analysis Project 4

  15. ePOH Inc. • Pressure Drop in Streams • Pressure drops in the pipes are much smaller than the overall pressure gradient in the system • Current compressor pushes the stream up to 500 psia while they exit the system at atmospheric pressure • There is no need to add additional pumps and compressors to overcome the pressure drop in the pipes Fluid Transport and Economic Analysis Project 4

  16. ePOH Inc. Fluid Transport and Economic Analysis • Performed risk analysis on the cyclohexane unit • High risk, very low return • Less than 20% chance of breaking even • The difference between cyclohexane (product) and benzene (raw material) would need to increase to $1.51/gallon • ePOH does NOT recommend constructing the cylcohexane unit • Could use Diels Alder reaction as an alternative way to produce cylcohexane Project 4

  17. ePOH Inc. NPSHA vs. Flow Rate Project 5

  18. ePOH Inc. Project 5 System Head vs. Flow Rate

  19. ePOH Inc. Project 5 Pumping section PFD

  20. ePOH Inc. • Reactor Material Chosen: Type 304 Stainless Steel • Advantages of material: • resist to corrosion • high alloy metal • very high tensile strength Project 5 Reactor Specifications

  21. ePOH Inc. Project 5 Piping and Insulation Specifications

  22. ePOH Inc. Pump Specifications Project 5

  23. ePOH Inc. Pumping Section: Fixed Capital Investment Project 5

  24. ePOH Inc. CH-Plant:Heat Exchanger Study E2 E1 E3 Project 6

  25. ePOH Inc. Heat Exchanger: Hand Design • Exchanger E1 designed for two cases: • Single-Pass Tubes • Double-Pass Tubes • Equipment cost determined for each design • T-Q Diagram compared Project 6

  26. ePOH Inc. • Single-Pass Tubes • Double-Pass Tubes Project 6

  27. ePOH Inc. T-Q Diagrams: E1 • Single-Pass Tubes • Double-Pass Tubes Project 6

  28. ePOH Inc. Heat Exchanger: Rigorous Model • Rigorous heat exchanger model used for exchanger E1 • Tube length and diameter and shell diameter were varied to produce the smallest heat transfer area • Designed using Pro II Process Simulator * Minimize heat transfer area to Minimize cost! Project 6

  29. ePOH Inc. Heat Exchanger: Rigorous Model Square Pitch 236 tubes, each 16 feet long 1275 ft2 heat transfer area 11,600,000 Btu/hr heat duty Project 6

  30. ePOH Inc. Heat Exchanger 2 and 3 Designed using the simple heat exchanger models with Pro II Project 6

  31. ePOH Inc. Cost of Heat Exchangers Project 6

  32. ePOH Inc. Cyclohexane Tower Dimensions • 7 feet in diameter, 56 feet tall • 28 trays inside column • 2 foot spacing between column • Condenser duty: -3,300 Btu/sec • Reboiler duty: 3,700 Btu/sec • Column sized assuming vapor velocity is 80% of that required for flooding from the following correlation: Project 6

More Related