An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Final Design Authorization Comanche Peak Steam Electric Station Automated Design Change Control System Overview Lee Windham TXU June 17-20, 2007Charleston, SC

  2. Why Go Automated Not Just Electronic ? • Direct tie to the corrective action program • Work product quality improvement • Tribal knowledge standard task assumed by the application • Regulatory requirements programmed into the application • Review requirements highlighted to the engineer • Elimination of Duplicated Work • In Engineering • In reviewing organizations • The Desire to Make a Large Leap Forward

  3. The FDA Application • IS NOT simply an electronic form • IS NOT a work tracking process • IS an integrated design change application • Document Management System • CADD • Text Design Documents • Vendor Design Drawings (electronic and non electronic) • Work Order System (implementation documents) • Employee Training and Qualification records • IS a semi-automated process

  4. Assignment / Qualification • Required Disciplines are determined from Affected Documents and Components listed on the FDA • All Documents at CPSES have been assigned to a discipline • All Components at CPSES have been assigned to a discipline • Additional disciplines can be manually added by the Responsible Engineer • Assignments made by Discipline Design Qualification • Each engineer is qualified by the CPSES training program specifically in one or more disciplines • Assignments are populated to the work tracking system

  5. Electronic Form • Electronic Form Captures Scope and Justifications • Work Scope • Design Inputs • Design Details • Testing Requirements • Engineering Basis • Calculation Impact Log • 50.59 Review • Design Verification

  6. Automated Reviews • Impact Reviews for Internal and External Organizations are Automatically Determined • 55 Established site programs / organizations that could be affected by a design change • Screening questions identified by the affected program owner • The application queries data entered onto the form and determines the answers to these questions and thus which reviews are required • The specialist for each review either completes the review or is notified that another person is completing the review • Identified Impacts can be tied to various completion status of the design change

  7. Electronic Document Mark-Ups • The application creates an electronic version of the drawing or text file for the engineer to mark up • The file is marked-up in the native application and linked to the FDA • New drawings including vendor submittals are entered into the system • Non-Electronically stored documents can be converted to electronic format or have a scanned attachment

  8. Electronic Signatures • Signature / Review process totally electronic • When it is time for individuals to sign they are notified via E-Mail • Once an Individual has signed, their ability to edit the document is restricted, If it is opened in edit mode their signature is removed. • When the final approval signature is applied the application updates all the required databases and computer files and restricts all further editing.

  9. Automated Document Revision • Document revisions processed automatically when Field Work Orders are complete • The application verifies that the current document revision is the same as the affected revision • if so the next revision is automatically issued (95%) • The Document management system is updated electronically • The new revision of the document is created from the version file electronically with no human intervention • If not the responsible document group is notified (5%) • The revision conflict is resolved • The electronic issue process is restarted • Non-Electronic documents are statused in the appropriate databases

  10. Automated Database Updates • The Master Equipment List is updated • Setpoint design document • Pipeline design information • Configuration control references for component modifications • Work Tracking Data updated

  11. Mobility • Access available across a secure connection • TXU engineers can access the system from their home computers • Engineering Firms contracted to do work at CPSES can access the system from their home office to issue change documents in our system.