1 / 17

Cohesion Fund Monitoring Committee CR 1164/94

ISPA Measure 2001 BG 16 P PE 004 FGD Plants at Units 5&6 of TPP Maritsa East 2. Cohesion Fund Monitoring Committee CR 1164/94. Cohesion Fund Monitoring Committee CR 1164/94. Works Contract. Commencement Date: 14 th January 2009 Completion Date: 01 st September 2011

danno
Download Presentation

Cohesion Fund Monitoring Committee CR 1164/94

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ISPA Measure 2001 BG 16 P PE 004 FGD Plants at Units 5&6 of TPP Maritsa East 2 Cohesion FundMonitoring Committee CR 1164/94

  2. Cohesion FundMonitoring Committee CR 1164/94 Works Contract • Commencement Date: 14th January 2009 • Completion Date: 01st September 2011 • Physical Execution: 100 % • Financial Execution: 57 % • Protokol 15 signed: 30 August 2012 • Contract terminated by the Employer: 14 December 2012

  3. Cohesion FundMonitoring Committee CR 1164/94 FGDP at Units 5&6 of TPP ME2 Construction Works Section 1 (Unit 6) Gas Ducts Section 1 (Unit 6) Gas Duct Connection to ID Fan

  4. Cohesion FundMonitoring Committee CR 1164/94 FGDP at Units 5&6 of TPP ME2 Construction Works Section 1 (Unit 6) MCC Room Section 1 (Unit 6) Oil Station Room

  5. Cohesion FundMonitoring Committee CR 1164/94 FGDP at Units 5&6 of TPP ME2Construction Works Section 2 (Unit 5) Gas Duct Connection to Existing Part Section 2 (Unit 5) Erection of ID Fan

  6. Cohesion FundMonitoring Committee CR 1164/94 FGDP at Units 5&6 of TPP ME2Construction Works Section 2 (Unit 5) Oil Station with Sealing Air Fan Section 2 (Unit 5) Gas Duct Connection to Existing Electro-filters

  7. Cohesion FundMonitoring Committee CR 1164/94 FGDP at Units 5&6 of TPP ME2Construction Works Section 2 (Unit 5) Gas Duct Connection to Electro-filters Section 2 (Unit 5) Gas Duct Out of ID Fan

  8. 9th Cohesion FundMonitoring Committee CR 1164/94 FGDP at Units 5&6 of TPP ME2Construction Works Section 3 – Limestone Slurry Preparation Building – Reinforcement Works

  9. Cohesion FundMonitoring Committee CR 1164/94 FGDP at Units 5&6 of TPP ME2Construction Works Section 3 – Wet Stack Support Structure Section 3 – Wet Stack Support Structure Stepping on the Absorber Section 3 – Absorber Inside

  10. Cohesion FundMonitoring Committee CR 1164/94 FGDP at Units 5&6 of TPP ME2Construction Works Section 3 – Slab at level 14.34 m, Pump Station 2 Section 3 – Steel Support Structure for Pump Station 2

  11. Cohesion FundMonitoring Committee CR 1164/94 FGDP at Units 5&6 of TPP ME2Construction Works Section 3 – Pump Station 2 and Absorber Section 3 – Reinforcement Works for Pump Station 2 – slab at level 18.84 m

  12. Cohesion FundMonitoring Committee CR 1164/94 FGDP at Units 5&6 of TPP ME2Construction Works Section 3 – Erection of Gas Duct Connection to Absorber Inlet Nozzle Section 3 – Foundation for Limestone Slurry Preparation Building

  13. Cohesion FundMonitoring Committee CR 1164/94 FGDP at Units 5&6 of TPP ME2Deliveries GRP Pipes for Limestone Slurry Recirculation GRP Elements for Wet Stack Elements for Wet Stack Support Structure Transformer T 35

  14. Cohesion FundMonitoring Committee CR 1164/94 FGDP at Units 5&6 of TPP ME2Signboards

  15. Cohesion FundMonitoring Committee CR 1164/94 Supervision Contract • Commencement Date: 18th Sept. 2006 • Completion Date: 18th July 2014 • Physical Execution: 90 % • Financial Execution: 83 %

  16. Cohesion FundMonitoring Committee CR 1164/94 Compliance with Article 8of the Financing Memorandum Art. 8.4 (a) Whereas the requirement of Art. 8.4 (a) is not a condition related to payment, formal confirmation of EC for its fulfillment is not expected. Art. 8.5 (a) Monitoring programme has been prepared as part of the Basic Design and will be further elaborated with the Detailed Design for Section 3 of the facility. Art. 8.5 (b) Measures for ensuring air quality are being taken. All other conditions under Article 8 of the FM are considered fulfilled, except for the unavailability of EBRD financing.

  17. Thank you for your attention!

More Related