1 / 49

Redditch Branch Enhancement

Redditch Branch Enhancement. Introduction. Roger Clarke – NWR Project Manager Bob Aldridge – NWR Scheme Project Mgr Marc Riley – BGCL Contracts Manager Dominic Eldridge – BGCL Project Manager Susan Fisher – LM Estates Manager Karen Allington – LM Bus Replacement. Focus of Presentation.

danno
Download Presentation

Redditch Branch Enhancement

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Redditch Branch Enhancement

  2. Introduction • Roger Clarke – NWR Project Manager • Bob Aldridge – NWR Scheme Project Mgr • Marc Riley – BGCL Contracts Manager • Dominic Eldridge – BGCL Project Manager • Susan Fisher – LM Estates Manager • Karen Allington – LM Bus Replacement

  3. Focus of Presentation • Provide information on forthcoming works (4x29hr weekend possessions & 8 week blockade). • Advise what alternative transport arrangements are proposed whilst the train service is disrupted. • Meeting will not centre on previous complaints – purpose is to be “informative”.

  4. Scheme Details • Install a 3km length of passing loop between Alvechurch and Redditch • Aim to increase capacity on the Redditch Branch Line from 2 to 3 trains per hour Main Lines Redditch Branch

  5. Existing Layout North to Barnt Green Station South to Redditch Station O/Br. 12 Grange Lane Alvechurch Station 55 MP 55 ¼ MP 54 MP 53 ¼ MP Cutting O/Br.10 Station Road Embankment

  6. Proposed Layout North to Barnt Green Station South to Redditch Station Down Line Alvechurch Station 55 MP 55 ¼ MP 54 MP 53 ¼ MP New Up Line New Platform & Footbridge

  7. Existing Arrangement

  8. Proposed Arrangement

  9. Alvechurch Station 1950s

  10. Alvechurch Station Existing Looking South towards Redditch

  11. Alvechurch Station Proposed Looking South towards Redditch New Footbridge & Lifts New OLE New Up Line

  12. Grange Lane Existing Looking North towards Alvechurch

  13. Grange Lane Proposed Looking North towards Alvechurch New OLE New Up Line

  14. 29 Hour Possessions • Week 11 – 00:10 Sun 8th June to 05:30 Mon 9th June • Installation of OLE gantries to South • Delivery of points to Alvechurch • Installation of track drainage through station • Placement of bottom ballast • Installation of OLE foundations • Week 12 - 00:10 Sun 15thJune to 05:30 Mon 16thJune • Installation of OLE gantries to South to mid-point • Delivery of points to Weights Lane • Installation of track drainage south of station • Placement of bottom ballast • Delivery of station footbridge • Installation of OLE foundations

  15. 29 Hour Possessions • Week 13 – 00:10 Sun 22nd June to 05:30 Mon 23rd June • Installation of OLE gantries to Mid-point to north of Grange Lane • Placement of bottom ballast • Installation of OLE foundations • Wingwall retaining wall to Overbridge at Station Road • Week 14 - 00:10 Sun 29thJune to 05:30 Mon 30thJune • Installation of OLE gantries to Grange Lane to Alvechurch • Placement of bottom ballast • Wingwall retaining wall to Overbridge at Station Road

  16. Blockade Works • Install new signal panel at Saltley PSB • Removal of 72 no. OLE gantries & cantilevers • Removal of 85 no. existing OLE foundations • Relay 1500m of existing track on Down Line • Slew 1700m of existing track on Down Line • Install new 3000m track. • Install S&C (2no.) • 10 no. engineering trains • 12 no. tamping shifts • Install 116 no. OLE gantries - 7900m of wire runs • Install signalling equipment • Install CCTV, PA systems, CIS etc at Station • Testing & commissioning • Open Line & Station

  17. Working next to Existing Line Existing OLE Gantries New OLE Gantries Bottom ballast installed prior to blockade Existing Track Foundation Excavation Exclusion Zone

  18. Redditch Branch Enhancement Blockade Works

  19. Stage 2b – Blockade Works Five Ways 43.18 Selly Oak 45.50 Main Blockade Works Longbridge 49.12 Northfield 48.12 52.40 Kings Norton 46.59 University 44.73 Bournville 46.58 Barnt Green 51.67 Hazelwell 45.07 Alvechurch 53.40 • Blockade Shortened back to Redditch Branch Only. Redditch 56.60 Area affected by works

  20. Blockade Overview

  21. Week 1 & 2 of the Blockade 00:45 Sun – 05:45 Mon 03:45 Mon – 03:45 Wed 03:45 Wed – 03:45 Sun 03:45 Wed – 03:45 Fri 19:45 Fri – 04:15 Sat 04:15 Sat – 04:15 Tue 04:15 Sat – 18:15 Sat 04:15 Tue– 18:15 Sat

  22. Week 3 to 6 of the Blockade 13:15 Sun– 12:00 Thu 04:00 Sat – 12:00 Fri

  23. Weeks 7 to 8 of the Blockade 04:45 Mon – 04:00 Mon

  24. Remove OLE 8 Week Blockade North to Barnt Green Station South to Redditch Station Week 1 DOWNSIDE 55 MP 55 ¼ MP 54 MP 53 ¼ MP UPSIDE • Isolation to include Barnt Green Station – first 27hrs only • Install Earth Section & Remove OLE (2 Days)

  25. Gantry Removal 8 Week Blockade North to Barnt Green Station South to Redditch Station Week 1 - 2 DOWNSIDE 55 MP 55 ¼ MP 54 MP 53 ¼ MP UPSIDE

  26. Thimble North Rails (570m) 8 Week Blockade North to Barnt Green Station South to Redditch Station Week 1 DOWNSIDE 55 MP 55 ¼ MP 54 MP 53 ¼ MP UPSIDE

  27. Remove North Sleepers 8 Week Blockade North to Barnt Green Station South to Redditch Station Week 1 DOWNSIDE 55 MP 55 ¼ MP 54 MP 53 ¼ MP UPSIDE

  28. Excavate to Formation 8 Week Blockade North to Barnt Green Station South to Redditch Station Week 2 DOWNSIDE 55 MP 55 ¼ MP 54 MP 53 ¼ MP UPSIDE

  29. Place Bottom Ballast 8 Week Blockade North to Barnt Green Station South to Redditch Station Week 2 DOWNSIDE 55 MP 55 ¼ MP 54 MP 53 ¼ MP UPSIDE

  30. Install S&C via PEMS 8 Week Blockade North to Barnt Green Station South to Redditch Station Week 2 UPSIDE 55 MP 55 ¼ MP 54 MP 53 ¼ MP DOWNSIDE

  31. Install North Sleepers 8 Week Blockade North to Barnt Green Station South to Redditch Station Week 2 DOWNSIDE 55 MP 55 ¼ MP 54 MP 53 ¼ MP UPSIDE

  32. Install North Rails 8 Week Blockade North to Barnt Green Station South to Redditch Station Week 2 DOWNSIDE 55 MP 55 ¼ MP 54 MP 53 ¼ MP UPSIDE

  33. Install S&C via PEMs 8 Week Blockade North to Barnt Green Station South to Redditch Station Week 2 DOWNSIDE 55 MP 55 ¼ MP 54 MP 53 ¼ MP UPSIDE

  34. Install South Sleepers 8 Week Blockade North to Barnt Green Station South to Redditch Station Week 2 DOWNSIDE 55 MP 55 ¼ MP 54 MP 53 ¼ MP UPSIDE

  35. Install South Rails 8 Week Blockade North to Barnt Green Station South to Redditch Station Week 2 DOWNSIDE 55 MP 55 ¼ MP 54 MP 53 ¼ MP UPSIDE

  36. 1 of 2 No. Autoballasters 8 Week Blockade North to Barnt Green Station South to Redditch Station Week 3 DOWNSIDE 55 MP 55 ¼ MP 54 MP 53 ¼ MP UPSIDE

  37. Tamp Down Line incl. S&C 8 Week Blockade North to Barnt Green Station South to Redditch Station Week 3 DOWNSIDE 55 MP 55 ¼ MP 54 MP 53 ¼ MP UPSIDE

  38. Rail Drop 8 Week Blockade North to Barnt Green Station South to Redditch Station Week 3 DOWNSIDE 55 MP 55 ¼ MP 54 MP 53 ¼ MP UPSIDE

  39. 1 of 2 Sleeper Trains 8 Week Blockade North to Barnt Green Station South to Redditch Station Week 3 DOWNSIDE 55 MP 55 ¼ MP 54 MP 53 ¼ MP UPSIDE

  40. Thimble Rail to Up Line 8 Week Blockade North to Barnt Green Station South to Redditch Station Week 3 DOWNSIDE 55 MP 55 ¼ MP 54 MP 53 ¼ MP UPSIDE

  41. 1 of 3 Ballast Trains 8 Week Blockade North to Barnt Green Station South to Redditch Station Week 3 DOWNSIDE 55 MP 55 ¼ MP 54 MP 53 ¼ MP UPSIDE

  42. Tamp Up Line 8 Week Blockade North to Barnt Green Station South to Redditch Station Week 3 DOWNSIDE 55 MP 55 ¼ MP 54 MP 53 ¼ MP UPSIDE

  43. Install Cantilevers & RC 8 Week Blockade North to Barnt Green Station South to Redditch Station Week 4 & 5 DOWNSIDE 55 MP 55 ¼ MP 54 MP 53 ¼ MP UPSIDE

  44. Install Catenary & Contact 8 Week Blockade North to Barnt Green Station South to Redditch Station Week 5 & 6 DOWNSIDE 55 MP 55 ¼ MP 54 MP 53 ¼ MP UPSIDE

  45. Autoballasters 8 Week Blockade North to Barnt Green Station South to Redditch Station Week 6 DOWNSIDE 55 MP 55 ¼ MP 54 MP 53 ¼ MP UPSIDE

  46. Final Tamp 8 Week Blockade North to Barnt Green Station South to Redditch Station Week 6 DOWNSIDE 55 MP 55 ¼ MP 54 MP 53 ¼ MP UPSIDE

  47. Final OLE Adjustments 8 Week Blockade North to Barnt Green Station South to Redditch Station Week 6 DOWNSIDE 55 MP 55 ¼ MP 54 MP 53 ¼ MP UPSIDE

  48. Communications with NWR • All communications will be via the help line:- 08457 11 4141 Public Relations team have been advised of forthcoming works and will be able to provide updated information.

More Related