An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Sign Manufacturing and Maintenance David Cook, P.E. State Maintenance Engineer, SCDOT

  2. Sign Shop Consolidation • 3 Manufacturing facilities • 3 Sign Shop Supervisors • 2 Delivery Trucks • 25 Total Employees • Long wait time (up to 100 days) • 1 Manufacturing facility • 1 Sign Shop Supervisor • Free Shipping! • 9 Total Employees • Orders filled in 30 days or less • Reduced production cost by over $500,000 per year Before After

  3. How We Got There • Production Analysis • Production Goals • Staffing Estimates • SMART Goals • Monitor Performance

  4. Production Analysis • Time Studies - Employees were observed performing tasks. • Prep time and volume was considered • A reliable maximum production value was identified

  5. Standard Signs • Screen Printing • Rolling and Trimming • Large investment in set-up time is for setting up screen printer, making screens, & clean-up

  6. Screen Printing Production 100 screened signs 65 minutes

  7. Roll & Trim Production Times

  8. Hand Laid Signs • Hand laid sign production was more difficult to quantify • Assumptions and estimates were used • We used a 24”x 72” sign for an average size • Made allowances for the unique nature of these types of signs

  9. Production Goals • From our production study we determined maximum production values • Observed maximum production was modified to expected daily production • Safety meetings, training, ancillary duties, facility maintenance, etc. • This value was further adjusted with yearly realistic reductions • Annual leave, sick leave, holidays, special projects, equipment down time

  10. Estimating Sign Demand • 750,000 signs in South Carolina • 10 year replacement schedule • 12.5% additional for new and damaged signs. • About 84,000 signs per year

  11. Required Production • 52 weeks X 4 days = 208 days/year • Holidays = 13 days/year • Sick days = 8 days/year • Annual leave = 12 days/year • Special projects = 3 days/year • Inventory = 5 days/year • Annual average work days = 167 • Required production 84,000/167 • = ~ 500/day

  12. Staffing by Production Estimates 1-Supervisor 1-Screen Printer 2-Roll and Trim 2-Hand laid signs 1-Admin 1-Shipping/receiving

  13. Performance Monitoring • SMART production goals are part of the position description • Production is monitored daily • Coaching and counseling is used for underperforming employees • All current employees are meeting or surpassing required production goals

  14. Cost Comparison • Costs were compared to measure efficiency of new sign production process • Private vendors were queried but would only give verbal estimates • SCDC Prison Industries produces signs and has a current contract for various types of signs • SCDOT production costs encourage in-house sign production

  15. Sign Maintenance

  16. History • In 2003, SCDOT implemented HMMS • Need to inventory assets to know what needed to be managed • Sign Inventory • Barcode signs and assemblies

  17. Barcode Information • Sign • Manufacturing Process • Manufacture Date • Sign Type • Sheeting Type • Sign Legend • Installation Process • Install date • Directional Information • Linked assembly

  18. Barcode Information • Assembly • Installation Process • Location • County, Route, Milepoint • GPS • Associated signs

  19. Data Collection Method • All barcode information was manually recorded and entered into HMMS • Paperwork Lost • Entry Delay • Entry Errors • Inefficient • ….Inaccurate database • IT Presentation – Barcode Readers and Tablet PCs

  20. Sign Management • Retroreflectivity– Minimum standards • 23 CFR Part 655 • 2009 MUTCD • Regulatory, Warning, and Ground Mounted Guide by January 22, 2015 • Overhead Guide by January 22, 2018 • Management Method • “Blanket Replacement Method” • “Expected Life Method”

  21. Technology Enhancements • Scanners for Sign Manufacturing Shop • iPads and Bluetooth Scanners for Sign Crews

  22. 200056

  23. Cost Savings • 90 sign trucks statewide • 15signs per day per truck – (avg. daily prod) • Reduction of data collection and entry by 2 minutes per sign • Results in a savings of 45hours per day • Average loaded rate of $21.75 /hour and 217 actual days worked per year. • Total Annual Savings: $213,000 • Additional benefits: • Real time data • Accurate data

  24. Lessons Learned • Need to have sense of ownership from IT • Need to cache data so it isn’t dependent on cellular service

  25. Future Improvements • Research Project – Life Expectancy • Develop more specific replacement schedules • Sheeting color • Direction • Sheeting type • …? • Remove unnecessary signs

  26. Questions?