INFLOW RUNOFF - Runoff Curve Number Direct Precipitation

INFLOW RUNOFF - Runoff Curve Number Direct Precipitation. Runoff Equation. RO= [P - Ia] 2 [P - Ia] + S Ia=0.2S, S= 1000/CN-10, therefore = [P - ((200/CN) - 2)] 2 [P + (800/CN) - 8] where, P>0.2S. 50% Chance Event. How does a 50% chance of 7 days

darena
Download Presentation

INFLOW RUNOFF - Runoff Curve Number Direct Precipitation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. INFLOW RUNOFF - Runoff Curve NumberDirect Precipitation

  2. Runoff Equation • RO= [P - Ia]2 • [P - Ia] + S • Ia=0.2S, S= 1000/CN-10, therefore • = [P - ((200/CN) - 2)]2 • [P + (800/CN) - 8] • where, P>0.2S

  3. 50% Chance Event • How does a 50% chance of 7 days • or 14 days runoff differ from runoff • generated from a 24 hour 2 year • frequency storm????

  4. Runoff Curve Number (RCN) • EFM (EFH) Ch. 2 or EFM2 Computer Program NRCS Engineering Hydrology or • NRCS Engineering Hydrology Training Series Module 104 (Runoff Curve Number Computations)

  5. CN Information Needed • Hydrologic Soil group • Cover Description • Condition of Cover • Acres or Percent of Total Area Training Series Module 104 (Runoff Curve Number Computations) part of pre-course assignment.

  6. Muti-year Crop Rotation • - For assistance with computation of the RCN for seasonal adjusted cropland, refer to Appendix A.

  7. Adjustment from Type II ARC (During Growing Season) • ARC Type 5-Day Antecedent Rainfall (AMC) • I < 1.4 in. • II between 1.4 in. • and 2.1 in. • III > 2.1 in. • Table 6.1

  8. Dormant Season Adjustment • ARC Type 5-Day Antecedent Rainfall(AMC) • I < 0.5 in. • II between 0.5 in. • and 1.1 in. • III > 1.1 in. • Table 6.1

  9. CN Adjustment from Type II ARC • CN for CN for CN for • Type II Type I Type III • 65 45 82 • 70 51 85 • 75 57 88 • 80 63 91 • 85 70 94 • Table 6. 2 (From NEH Sec. 4 Table 10.1)

  10. Steps for Determining Runoff • 1. Compute RCN for drainage area • 2. Determine the growing season • 3. Determine the appropriate inundation or saturation period • 4. Obtain daily precipitation data • (30 years minimum)

  11. RO Steps continued • 4a. - Compute each runoff event • - determine maximum continuous runoff for given number of day for each year • - obtain 50% chance value by ranking

  12. Direct Precipitation • The Runoff (RO)= [P - (200/CN) - 2]2 • [P + (800/CN) - 8] • for example: RO = 0.17 in. • CN for Type II ARC = 85 • Trial & Error Equation is: • 0.17= [P - (200/85) - 2]2 • [P + (800/85) - 8]

  13. Average Precipitation Value • PARC I = 0.0 + P70 • PARC II = 1.4 + P85 • PARC III = 2.1 + P94 • P = (PARC I + PARC II + PARC III ) / 3

  14. Break