When is Enough, Enough?. Opening Remarks and Comments. Presentation Purpose. History of Environmental Compliance Actions Existing Deicing Facilities, Collection Systems and Operating Protocols System Improvements Current Conceptual Consideration (Stormwater Management and Treatment).
E N D
History of Environmental Compliance Actions Existing Deicing Facilities, Collection Systems and Operating Protocols System Improvements Current Conceptual Consideration (Stormwater Management and Treatment) Presentation Setup and Approach
Structure Allegheny County Airport Authority incorporated in November 1999to succeed the Allegheny County Department of Aviation
Hub Focus City O&D Current Operating Role
Airfield Layout Runways (4)
Airfield Layout Terminal Buildings
Airfield Layout Cargo, Military Bases, FBO & Maintenance
1998 Administrative Order “. . . Cease unauthorized discharges of deicing/anti-icing chemicals . . .”
Overall ACAA Deicing Pad Military Deicing Pad Cargo Defrosting Area YankeeNorth Charlie FBO YankeeSouth 911th Echo Sierra PANG
Echo and Charlie Pads Dedicated to deicing 12 pedestal-mounted booms Icehouse Collection systems Initial Pads $10MM
Echo Pad Second set of trench drains Echo and Charlie Type II fluid system 1994 Improvements $12.3MM
Charlie Pad Trench drain modifications New pavement Piping and above-ground storage for impacted runoff 1998 Improvements $13.3MM
Echo and Charlie Pads Relocation of boom pedestals Replaced boom cabs Converted diversion vault valves to positive seals (gate valves) 2000 Improvements $14.4MM
Sierra Pad New deicing pad to accommodate wide-body aircraft Yankee South Pad Expanded pad and installed liner 2001 Improvements $41.8MM
Central piping systemto transfer collectedfluids to onsite recycling facility Echo and Charlie Pads Joint and slab rehab/replacement 2002 Improvements $45 MM
2003 Improvements $50.3MM • Echo and Charlie Pads • Addition of forced air • Third party vendor forced air equipment
Grand total of capital improvements of $50.3MM Operational costs on an annual basis of $1.7MM per year Capture 60 – 65% of applied aircraft deicing fluid by volume Summary of SystemImprovements
Data Collection and Evaluation Stormwater Management Treatment Current Concept Engineering Evaluation
5+ years of flow and water quality data Intensive and periodic 15 minute continuous rainfall datasince May 1948 Wetland delineation in 2004 Stream assessments in 2004 PG and pavement deicer quantities Data
Stream Bacteriological Report Thiothrix Beggiatoa Zoogloea
Stormwater Evaluation • Modeling • H&H and water quality • Conceptual Design Capture Area • Conceptual Design Capture Volume • Treatment Rate
Stormwater Evaluation Top of Dam
Stormwater Evaluation Top of Dam