HOSPITAL PENAWAR. DEVELOPMENT AND IMPROVEMENT 07.03.2012. NEW PHYSIO SPORT AND REHAB. QUOTATION. NEW PHYSIO SPORT AND REHAB. TO BEGIN RENOVATION RIGHT AFTER LAYOUT APPROVE – DUE DATE 12/03/2012
E N D
HOSPITAL PENAWAR DEVELOPMENT AND IMPROVEMENT 07.03.2012
NEW PHYSIO SPORT AND REHAB • TO BEGIN RENOVATION RIGHT AFTER LAYOUT APPROVE – DUE DATE 12/03/2012 • FINALIZE EQUIPMENT QUOTATION (ON PROGRESS - 7 QUOTATION). STILL WAITING FOR OTHER COMPANY QUOTATION. • WILL PRESENT THE QUOTATION AND GET APPROVAL FROM DR ON 13/03/2012.
PHOTO GALLERY 23 February 2012
PROGRESS Things done 30 Jan • Check materials for outdoor gallery • Request quotation for outdoor gallery 9 Feb • Received quotation 23 Feb • Check materials for photo frames (indoor gallery) at supplier shop • Choices – wooden frames & acrylics • Request quotation
Next to do…. 27 Feb – 2 Mar • Categorizing photo • Select/choose photo to print • Print photo • Issue PO for outdoor & indoor gallery
OUTDOOR GALLERY Approved site
Why this site… Common walkway for the public Only 2 panels are selected – Café customers view not totally distracted
DESCRIPTION Display board size: 37”(H) x 119”(W) Material: Aluminium composite base Photo frame: Acrylic plastic sheet with screws, Size: 23(H)”x17”(W) (2 A4 sized photo in each frame or 1 A3 sized photo in each frame) Price: RM 950.00 x 2 panel = RM 1,900.00
INDOOR GALLERY 1 AFTER BEFORE
INDOOR GALLERY IDEAS Acrylic frames Black wooden frame
WARD IT SYSTEM • - TROLLEY INSTALLED AT WARD 2 AT WARD 3 • - TRAINING ON-GOING • - ANY PROBLEM - WILL BE RECTIFY ON THE SPOT
F & B MANAGEMENT • - WARD MODULE AND KITCHEN MODULE - IN PROGRESS
SAFETY & HEALTH COMMITEE • Objective : • 1. To make sure HP comply with OSHA ACt requirement2. To ensure all notification from JKKP wil be settle down before due dateJob Done Last Week • 1. Meeting with Chairman on 20th February 2012- matters discuss :- Formation of safety & health comittee 2012- Highlighted issue by JKKP ( CHRA, Incident Report and safety comitee)2. Meeting with JKKP office , Menara TJB- matters disucss:- To fill up chemical register according format given by JKKP - by respective department- CHRA : To appoint competent person/ assessor to provide the CHRA report for the company- MSDS - To follow up with supplier Job to do this week • 1. To get quotation from assessor for CHRA report2. To complete chemical register by friday 09.02.2012
NEUROSURGERY • - Planning to send Pn Aishah and SRN Noraziawati for attachment- Jobs Done last week# Follow up with matron hasmah - to confirm back by this week# Matron notify - no attachment from outside during March- Jobs to do this week# To confirm with matron - slot in for attachment for April
NEW EQUIPMENT - OT • OPERATION THEATRECAMERA SYSTEM1 - OTV-S7 OLYMPUS DIGITAL CCD PAL VIDEO CAMERA SYSTEM # 1 x CAMERA CONTROL WITH RGB/YC/COMPOSITE/DIGITAL VIDEO # 1 x CAMERA HEAD OTV-S7H-1N # 1 x KEYBOARD FOR DATA INPUT # 1 x RGB/YC & COMPOSITE CABLE - RM 30,000.002 - CLV-S40 OLYMPUS 300 WATT XENON LIGHT SOURCE # 1 x 300 WATT XENON LIGHT SOURCE # 1 x CABLE LIGHT CONTROL - RM 26,200.00COMPANY : ENDODYNAMICS (M) SDN BHD LAST WEEK PROGRESS- PURCHASE ORDER ( DONE )THIS WEEK PLAN1 - FOLLOW UP ENDODYNAMIC 2 - SOURCE NEW CTG M/C ( IMPORT )
THE FLOWERS CAFÉ PROMOTION MARCH 2012 BREAKFAST PROMOTION SET NASI LEMAK KUKUS RM 4.00 + AIR (SEJUK/PANAS) OTHER CHOICES LUNCH PROMOTION SET NASI AYAM RM 6.00 + AIR (SEJUK/PANAS) OTHER CHOICES ALA CARTE PROMOTION SET CHICKEN CHOP RM 9.90 + JUS ORANGE/APPLE OTHER CHOICES
PROJECT NEW TRANSIT WD 2 1.LOUNCHING DATE : 1 APR 2012 2.DATE PROPOSE WALL PAPER : 7 FEB 2012 3.CURTAIN DATE : 12 MARCH 2012 4.FURNITURE DATE : 15 MARCH 2012 5.TESTING BELL, FINISHING : 19 MARCH
PROPOSAL DESIGN NEW TRANSIT • # WAITING DESIGN FROM ASILAH
PROJECT RADIOLOGIST ROOM • LAUNCHING DATE :1 APR 2012 • WALL DEMOLISH DATE : 5 MARCH • CARPET DATE : 14 MARCH • PAINTING + WALLPAPER DATE : 15 MARCH