1 / 35

SPP/FIELDS System Engineering Preliminary Design Review

SPP/FIELDS System Engineering Preliminary Design Review. Keith Goetz University of Minnesota Goetz@umn.edu. SPP Level-1 Requirements. FIELDS Level-1. Level-1 Flow to FIELDS. FIELDS Level-3 Driving Requirements. FIELDS Level-4 Flowdown – IRD.

darva
Download Presentation

SPP/FIELDS System Engineering Preliminary Design Review

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SPP/FIELDSSystem EngineeringPreliminary Design Review Keith Goetz University of Minnesota Goetz@umn.edu

  2. SPP Level-1 Requirements

  3. FIELDS Level-1 Level-1 Flow to FIELDS

  4. FIELDS Level-3 Driving Requirements

  5. FIELDS Level-4Flowdown – IRD • Requirements are flowed from SPP L3 document to FIELDS subsystems with IRD • APL: 7434-9051_Rev_Dash • SPF_SYS_010_Instrument_Requirements - IRD - SE-001-01B • L3 includes references to the FIELDS QA Matrix, Environmental Spec, EME Spec, Contamination Control, GI ICD, FIELDS ICD, etc. • L3 includes Instrument Functional and Performance Requirements • FIELDS IRD • Requirements linked up to the L3 PAY requirements • Requirements linked down the subsystem L5 or specifications • Subsystem specifications refer to their requirements from the IRD and how the design meets those requirements • Flight and SOC Software Requirements documents flow their requirements from the IRD down to the software modules • IRD specifies how each requirement is to be verified (Test, Analysis, etc) • System Engineer has validated that the subsystem specifications describe an instrument that meets requirements

  6. Requirement Flow-down to Subsystems FIELDS Subsystems

  7. Example - An IRD snippet – RFS Requirement Flow-down to Subsystems

  8. Verification • IRD identifies briefly how each requirement is verified • Verification, Validation, Test, and Calibration Plan describes a plan for how requirements are verified • Discussed in I&T section • Requirements are verified as early as possible at a low level • Verifies subsystems, retires risk • Requirements are verified at the highest level of assembly possible • Often involves verifying a requirement at several levels • System Engineer tracks Verification against IRD • Reports on status at PER, PSR

  9. SPP Spacecraft

  10. FIELDS MAG Boom

  11. FIELDS Block Diagram

  12. Interface Control Documents • Spacecraft to FIELDS • General Instrument ICD is at rev - (7434-9066) • FIELDS Specific ICD (7434-9055) • Minor open issues don’t preclude ETU development • MOC-SOC ICD • Well developed and familiar from RBSP and STEREO • FIELDS to SWEAP ICD (SPF_MEP_105_SWEAP_ICD) • Preliminary release signed on both sides • Subsystem ICDs are well along • MEP, CDI, RFS, TDS, DFB, MAG, AEB, LNPS, PA, SCM • Connectors and pin-outs (SPF_MEP_110_Connectors) well defined

  13. Software • DCB • Software Development Plan (SPF_MGMT_008_SDP) • Software Requirements (SPF_FSW_002_SRS) • TDS • Software Development Plan (SPF_TDS_002_SDP) • Software Requirements (SPF_TDS_004_SRS) • SOC • Software Development Plan (SPF_MGMT_016_SOC_SDP) • More later

  14. Environmental • FIELDS to survive all environments to be encountered during ground operations, launch, and on orbit • FIELDS to operate in spec over all environments to be encountered during ground functional tests, on-orbit commissioning and science phases • Full science performance achieved after MAG boom and FIELDS antennas are deployed (during commissioning) • SPP Environmental Requirements called out in 7434-9039 (dash) • SPP EMC Requirements called out in 7434-9040 • FIELDS Verification Plan described in SPF_IAT_002 • Describes how FIELDS will verify compliance with requirements, including environmental requirements • Plan discussed in more detail in I&T section

  15. Environmental Test Matrix

  16. Mechanical • Instrument designed to Environmental Specification Requirements • Limit Loads, Stiffness, Venting, Shock • Mechanical Interfaces, mass NTE called out in the FIELDS ICD • Instrument tested per Environmental Spec • Mass Properties at component level • Mass, CG • MOI by analysis • Sine, Random vibration at component level • ETU to qualification levels • FM to acceptance levels • No acoustic test planned (no acoustically sensitive parts) • More mechanical later

  17. Thermal • SPP – of course – presents its thermal challenges • FIELDS interface temperatures called out in the EDTRD and ICD • MEP Operational: -25ºC to +55ºC • FIELDS components conductively coupled to spacecraft structures • FIELDS’ various thermal designs to be verified by analysis and thermal vacuum testing • Analysis to include launch transients (heating) • Modeling and Analysis performed cooperatively between FIELDS and APL • Boom verification testing (Thermal Balance) described in I&T section • Verification testing (Thermal Vacum) described in I&T section • More thermal later

  18. EMC for FIELDS • FIELDS is a driver for EMC/ESC/MAG requirements • Power supply conversion control • Limited radiated and conducted noise • Electrostatics – S/C exterior an equipotential surface • ΔV from point to point must be small (less than ~1V) • Spacecraft must be magnetically clean • STEREO and RBSP are good models • Spacecraft EMC testing plan needs to be worked • FIELDS antennas and radiated emissions

  19. EMC/ESC • EMC • MEP box design includes EMC closeout • stair-step joints, vent shielding, connector close-out • DC-DC converter frequency is 150kHz synchronized • DC-AC MAG heater is 150kHz synchronized • RF receiver is synchronized to a multiple of 150kHz chopping frequency • All sampling is synchronized to 150kHz chopping frequency • Supply has front end filtering, soft start • Verification by EMC tests: • ETU (CE on bench) • FM (CE, CS, RE, RS, BI, On/Off transients) • ESC • Exterior surfaces are conductive and connected to chassis ground • ESC Verification at the component level • surface resistance measurements

  20. DDD/Radiation • Components inside boxes are generally immune • Harnessing is not immune • Components connecting to external harnesses have considered DDD issues • For example – in peer reviews • Immunity will be demonstrated by analysis • Immunity will be tested with ETU • Radiation environment inside spacecraft is fairly benign (20kRad) • Most EEE parts have no problem • Some parts require additional screening – possibly latch-up circuitry • PMPCB in the loop • Electronics outside the spacecraft analyzed separately • PMPCB providing guidance and assistance • Spot shielding may be added in some locations • Planned for SCM preamplifier

  21. Resources – Mass FIELDS mass tracking Shows 11.9% CBE to NTE

  22. Resources – Power • FIELDS power summary • MEP Power shows ample contingency: 27% • At room temperature • New power estimates at 55C show much higher power needs • Contingency is negative • Heater power has been an issue • Operational heating • Below .25AU is reasonable • Above .25AU needs work • But is apt to be ok • Limited heating on MAG sensor has caused problems

  23. Resources – Power Detail • FIELDS power tracking • Power broken out to indicate dissipation location • Heating broken into • Operational and survival • Above .25AU and below

  24. Resources – Telemetry • Telemetry bit-rate allows us to meet our science requirements • Survey data goes to S/C C&DH SSR – 15Gb/perihelion • Select data goes to large FIELDS internal flash storage • Selected data comes down during cruise – 5Gb/perihelion • More bits is always more good! • Telecommand requirements are modest

  25. Trades and Changes • Survival/operational heating additions • RTAX4000 selection – implemented on daughter boards (3 places) • FIELDS MAG boom to be built at APL • Accept virtual PPS from S/C • V1-4 Antennabrackets will accommodate one TPS shift • FIELDS Clocks – synchronized to power supply • Split FIELDS into two halves to enhance reliability • Open Trades • Location of FIELDS boom sensors • Length of FIELDS boom • Length of FIELDS whips

  26. FIELDS/TDS Evolution FIELDS was proposed as a single string instrument Within FIELDS, TDS was proposed as a single science board

  27. TDS Evolution • In early 2013, we recognized that FIELDS was central to meeting threshold science – occupying 4 of 9 threshold blocks • A single failure would mean a failure to meet threshold science • LNPS or DCB failure

  28. System-6 • FIELDS then suggested a number of alternatives • increasing reliability • Eventually, we settled on System-6 • Split • FIELDS1/2 • LNPS • LNPS1/2 • AEB • AEB1/2 • DPU function • DCB/TDS

  29. FIELDS Clocks • FIELDS instrument to use unified clocking • Receivers, sampling, power supplies, clocks • FIELDS LF instruments to operate in sync • FIELDS HF instrument relies on picket-fence for RF sensitivity • Power supplies chop – making lines noise as a function of frequency • Un-avoidable but controllable chopping at controlled frequencies • All S/C power supplies must be controlled • N * 50 kHz with N starting at 3 – e.g. 150 kHz, 200 kHz and so on • Frequencies are crystal controlled (±100PPM) • Make RF observations as a function of frequency in between lines of noise • In earlier analog super-heterodyne receivers, we used sharp crystal filters to create the picket fence • Observing in between lines of noise

  30. Picket Fences

  31. FIELDS HF Clocks • In the past, we used sharp crystal filters to create the picket fence • With our new all-digital receiver, we implement sharp picket-fence filteringwith simple high speed time series and poly-phase filtering • Samples must be in sync with FIELDS’ and S/C power supplies • FIELDS/HFR high end is about 20 MHz – sampling at ~40 MSa/s • Exact frequency must fall on the picket fence with room for an FFT • Master RFS sampling frequency is thus of the form 150 kHz * 2^N • Master sampling frequency is 150,000 * 256 Hz is 38,400,000 Hz • (±4 kHz)

  32. FIELDS LF Clocks • Other FIELDS instruments will be operated in synchronization with power supply chopping frequency (SWEAP too) • Power supply chopping frequency is 150,000 Hz • For lower frequencies we’ll shift down by powers of two • For lowest sample rates we’ll shift down by powers of two to ~293 Sa/s • 150,000 Hz / 512 (292.968750 Sa/s) • However, making convenient and compressible packets still requires a packet sizes and cycle times corresponding to a power of 2 samples • A standard packet should start with 256 samples • Giving a FIELDS internal cycle time of .87 seconds/cycle • 131,072 / 150,000 Hz • FIELDS’ New York second

  33. FIELDSSynchronized Sampling • MAGs produce samples at ~293 vectors per second • MAGs produce chunks/packets at 256 vectors per cycle • Out-board MAG survey data down-sampled at ~36.3 vectors/second • In-board MAG survey data down-sampled at ~2.3 vectors/second • DFB can sample from all 4 SCM axes and all 5 electric axes • Sampled at 150,000Sa/s • Low frequency DFB packets • DFB samples in sync with DC MAGs • 256 vectors at 293Sa/s covering .87s and 1 cycle in duration – lowest resolution • DFB mid-frequency spectra • DFB mid-frequency select time series • TDS time series triggered bursts – V,E, B and SWEAP • ~2MSa/s (1.92MSa/s = 38,400,000 / 20) • RFS spectra • Sampled in sync at ~40MSa/s

  34. Issues • Mass margin is tight • +11.9% (16.51kg CBE vs 18.48kg NTE) • Power margin is tight – especially when operating hot • -0.7% (22.71W CBE vs 22.56W NTE) • +27.8% (17.66W CBE vs 22.56W CBE) at 20C • Heater power has been an complex issue • DC MAG sensors should be warmer • +53.4% (3.98W CBE vs 6.10W NTE) in the best operational case • -29.0% (8.59W CBE vs 6.10W NTE) in the worst operational case • +2.5% (10.05W CBE vs10.30W NTE) in the worst survival case • LVDS over-voltage protection solution has proved elusive • DCB and TDS • Monitoring non-op FIELDS Boom sensor temperatures remains open • MAGi, MAGo, SCM

  35. Conclusion Issues are workable Requirements are understood Preliminary FIELDS system design meets requirements Documentation is in place FIELDS is ready to move into ETU development

More Related