An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. In-Orbit Commissioning Phase :IOCPKey-Point 009 December 2009 ( L + 37 Days )ESAC – Villafranca

  2. IOCP KP-0 Agenda • Updated Agenda : Issue 1 / 04-December-2009 • KP-0 Objective : Authorise and Kick-Off MIRAS PLM Comm’g. • Introduction ( HB ) • Reports of the LEOP Phase ( CNES : MVe , DP , MLD ) • Reports of the SODAP Phase ( ESA : MZ , GB , MMN , NW ) • Status of , Events observed during LEOP + SODAP phases ( All ) • System Configuration ( On-board + Ground ) for IOCP ( All ) • AOB’s ; Need for Splinters ( All ) • Conclusions – Kick-Off of the MIRAS PLM Commissioning : • Splinters ( as needed ) : This evening + Tomorrow morning .

  3. IOCP Main Phases • The In-Orbit Commissioning Phase comprises 4 main phases : • Launch and Early Orbit Phase ( LEOP / 3 RED Weeks ) : • Completed : 02 to 19 November : As per LEOP Plan / SOE’s • Switch-On and Data Acquisition Phase ( SODAP / 3 YELLOW W ) : • Started on : 17 November ( PLM Switch-ON Steps 1 + 2 ) • Under Completion until : Friday 11 December • MIRAS Payload Commissioning ( PLM Comm. / 5 BLUE Weeks ) : • Due to start on : Monday 14 December => KP-0 Decision • Pseudo-Operational Phase alternating Dual and Full-Pol modes

  4. 0 3 1 2 IOCP Main Phases ( Calendar ) LAUNCH CW 45 CW 46 CW 47 LEOP CW48 CW49 CW50 CW51 KP0 SODAP CW53 CW52 CW01 CW02 PAYLOAD XMAS (24-Dec till 2-Jan) CW03 CW04 CW05 CW06 6 months (27 weeks) Dual-Full KP1 CW07 CW08 CW09 CW10 MICRORAD (WASHINGTON) Key Point CW11 CW12 CW13 CW14 PLM Switch ON KP2 CW15 CW16 CW17 CW18 OCEAN FROM SPACE (VENICE) KP3 1 week

  5. 3 2 0 1 IOCP Main Phases ( Numbering ) LAUNCH LEOP 1 2 3 4 KP0 SODAP 5X 5 6 7 PAYLOAD XMAS (24-Dec till 3-Jan) 8 9 10 11 6 months (27 weeks) Dual-Full KP1 12 13 14 15 MICRORAD (WASHINGTON) Key Point 16 17 18 19 PLM Switch ON KP2 20 21 22 23 L2 Collocation OCEAN FROM SPACE (VENICE) KP3 1 week

  6. 0 XMAS 1 2 3 IOCP Detailed Time-line LAUNCH LEOP SODAP 1 2 3 4 Cold Sky View 5X 5 6 7 Long Calibration First Image 8 9 10 11 Thermal Stability 6 months (27 weeks) 12 13 14 15 Electrical Stability 16 17 18 19 Default Mode 20 21 22 23 Full Pol Dual Pol Key Point 1 week

  7. LEOP Week-1 PLM Switch ON LAUNCH LEOP Week-1 : 02 / 08 November 2009 : Monday 02-November-2009 : Launch / L0 : 01:50:51.014 Separation : 03:00:44 ( EOGS + 4207 s ) TM Reception : 03:03:03 ( HBK-1) + 03:25:21 ( KRN-1 ) PLM Partial S-ON 16:59:39 ( KRN-3 + SAUS-3 ) Tuesday 03-November-2009 : PLM Deployment Pyro-Seq. 1 ( 9 pyros ) : 04:23:05 ( SAUS-5 + KRN-9 ) PLM Deployment Pyro-Seq. 2 ( 3 pyros ) : 18:00:08 ( KRK-1 + AUS-1 ) Thursday 05 + Friday 06-November-2009 : PROTEUS Platform Switch-ON + SAT NOMINAL Mode ( AOCS ; Cmd-Ctrl )

  8. LEOP Week-2 , -3 PLM Switch ON LAUNCH LEOP Week-2 : 09 / 15 November 2009 : Thrusters and Gyros Calibration + Orbit Determination Orbit Correction Manoeuvres : Altitude ; Inclination ; Eccentricity LEOP Week-3 : 16 / 21 November 2009 : PLM Switch-ON Step 1 ( 10 deg.C ) + Step 2 Tuesday 17-Nov + First X-band TM Downlinks over ESAC ( SMOS XBAS Station ) PLM Switch-ON Step 3 ( 22 deg.C ) Wednesd 18-Nov Final Orbit Trim Manoeuvre In-Plane ( Altitude ; Eccentricity ) Execution of PLM Time-tagged Test Timelines .

  9. 0 SODAP Week 1 Week 2 Week 3 • SODAP comprises the X-band RF Link Tests : • Week 1 : Tests with SMOS XBAS Station in ESAC • Week-2 : Tests with SVALBARD Stations ( SG-3 ; SG-6 , SG-22 ) . • During SODAP , MIRAS PLM is ON , since 17 / 18 November . • Weeks 1 and 2 of SODAP are in parallel with PROTEUS Platform Commissioning activities : 3 types of External Calibration Manoeuvres ( ECM’s ) were tested and validated in Week-2 ( 30-Nov / 04-December ) .

  10. PLM Observations – 1 • PLM Observation Reports raised during LEOP and SODAP , • Registered and processed in ARTS Data Base by PLM Ops Team : • Mass Memory Redundant ( MMR ) : CLOSED before and during Launch  Specific TC sent to OPEN it , before PLM Partial Switch-ON , in line with PLM Procedures initial conditions . • Nominal Heaters Lines ( ASHL-N ) of Arm C-2 not activated during LEOP , as expected : • Instead , Redundant Heaters Lines of Arm C-2 were activated , • No evidence of any failure . Explained by small differences between Nominal and Redundant Thermostats set-points , and thermal gradients between Thermistors and Thermostats N / R . • To Be Monitored Carefully by OPS Team , during next activation .

  11. PLM Observations – 2 • PLM Observation Reports raised during LEOP and SODAP , • Registered and processed in ARTS Data Base by PLM Ops Team : • CMN Local Oscillators ( LO ) Unlocking / Drifts : 9 Events to date : • Under Gathering Statistics , and Analysis • => Switch-OFF / ON Arm-A CMN’s ( Procedure created ) • => Switch-OFF / ON Complete PLM ( Existing Procedures ) • PLM Mass Memory Partitions 3 and 6 Events : • Partition 3 Events : Under Analysis • Partition 6 Latch-Up : Reset by Complete PLM Switch-OFF / ON .