Report to JMPB

Report to JMPB. Topics: Progress Hall Clearance Programme Hall Layout Beam Line RF Power System MICE Management Structure Common Funds. 14 th October 2003. Progress B&I. Beam Line Layout in synchrotron hall Target design R&D Hall Civil

Download Presentation

Report to JMPB

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Report to JMPB Topics: Progress Hall Clearance Programme Hall Layout Beam Line RF Power System MICE Management Structure Common Funds 14th October 2003

  2. Progress B&I Beam Line Layout in synchrotron hall Target design R&D Hall Civil Clear Hall & prepare for 2004 shutdown

  3. Progress

  4. Progress Sheffield - Target

  5. Progress

  6. Hall Clearance • Crane upgraded • lighting maintenance done • Hall partly stripped out • disposal of old power supplies (keep for CMS) • preserving magnets • … on schedule – expect to complete end of October • No problems encountered • CMS disturbance minimal – still in place • discussed inevitability of moving (with BB)

  7. RF Power Sources • Identified some £900k+ savings on equipment! • CERN • 2 power amps (I expect CERN to refurbish & test) • LBNL • 2 power amps (need to be cleaned, modified & tested) • This can be done at/by RAL – risk of incurring disposal cost • 3 driver amplifiers (need to be cleaned & tested) • Los Alamos • 2 HV power supplies (loan – ~new) • 4 driver amplifiers (working – timescale not known) • Total RF cost is estimated @ 1.8M+ after savings

  8. Beam Line • Matching • Extra elements for MICE? • Looking CERN/DESY/TRIUMF/…RAL

  9. of MICE & Management • MICE management tree • Collaboration Board – Chair* • Executive Board* • technical board* (PD) • Level 2 Level 3 Level 4 • Process of (design & baseline) change control* • Funding Matrix* status • Common Funds proposal* • MICE constitution* • *For review at Collaboration meeting • ISIS/RAL Technical Contacts agreed • ISIS & ED resource group leaders Formal Project ManagementMethodology RAL Technical Liaison RAL Technical Advisory Committee

  10. MICE WBS (XX) = Management - Not necessarily a financial responsibility