Follow the journey of a major loss through the first 30 days, as experienced by the Major & Complex Loss team at Crawford Global Technical Services. Explore preliminary enquiries, causation, liability decisions, loss mitigation, and business continuity.
E N D
Insurance Institute of LeicesterThe Life of a Major LossThe first 30 days…
Kevin Dinsdale Regional Director, Major & Complex Loss team Crawford Global Technical Services Geraldine O’Donaghue Senior Investigator, Major & Complex Loss team Crawford Global Technical Services
Programme – First on the Scene! Property/BI/Forensics First on the scene Preliminary Enquiries Causation / Policy Liability Background Checks Prepare Preliminary Report Liability Decision Loss Mitigation (Property) Business Continuity (BI)
First on the Scene Emergency Services Fire Investigation Control Unit BuildingControl EmergencyContractors Other Govt Agencies Press Manager / Owner Loss Adjusting Team Forensics
Preliminary Enquiries Initial Site Meeting Team Approach Policy Documentation Drones / Technology Contact Insurers from site Initial advice Update all Parties
Causation / Policy Liability Identify potential causes: Electrical Work Cooking Related Fireworks
Policy Liability Issues Insurable Interest Maintenance Records Warranties Adequacy of Sums Insured: Is it Adequate?
Types of Screening Commercial Domestic Construction Engineering Casualty Good in Transit Liability BI Overall, we will look at anything.
For Screening The searches primarily completed are Land Registry Financial Searches Internet searches Telephone enquiries Which in turn produces a Screening Report.
The Screening report will Excluding warranties, conditions etc, Allow Insurers to make a decision on liability either for or against, based on information uncovered. Allow Insurers to investigate further if need be. Turnaround aimed for 48 hours.
When there is no screening or limited screening Blue Chip / Global entity Famous person Claim nearly complete or ongoing for a long time The Companies are based overseas
Our aims with screening Does the risk insured correspond with what we can see in the information we are looking at. Plus Any Claims Issues
Loss Mitigation (Property) Buildings Appointment of Consultants Establish Design Team Brief Identify Scope of Works Planning Considerations Contents
Business Continuity (Business Interruption) Adequacy of the Sums Insured Initial Information Request Discuss Mitigation Strategies Consider Early Interim Payment
30 Days Policy Liability Accepted Interim Payment Made Recovery Proceedings Initiated Action Plan Agreed