140 likes | 407 Views
Eskom’s MYPD2 Tariff Application. 03 December 2009. Brian Dames – Chief Officer (Generation Business). Eskom‘s MYPD2 tariff application – setting the context. History and context – 25 years of unrealistically cheap electricity Consequences of SA’s current electricity constraints
E N D
Eskom’s MYPD2 Tariff Application 03 December 2009 Brian Dames – Chief Officer (Generation Business)
Eskom‘s MYPD2 tariff application – setting the context • History and context – 25 years of unrealistically cheap electricity • Consequences of SA’s current electricity constraints • Motivation for Eskom’s Multi-Year Price Determination (MYPD2) application • Changed assumptions and shift in Eskom’s risk profile • Funding • Risks • Overview of the MYPD2 cost base • Capital expenditure • Operating expenditure • Primary energy • Implications • Economic impact on SA • Protection of the poor • Way forward – meeting SA’s capacity requirements over the next two decades
Drivers for the change • Economic impact of price increase • Recovery from recession will be slow • Electricity not to constrain post recession growth • Price increase by 16c/kWh per year • Impact on the poor and small business • Financially sustainable Eskom and operationally efficient • Strategic shifts – We cannot do it alone • Demand reduction – reduce SA energy intensity per GDP • New sources of funding at project level and additional borrowing • Operational savings • Next coal plant – not build by Eskom • Road repair and maintenance to Government • Project phasing
Benchmarking of generation business shows Eskom’s FY09 costs to be very low compared to peers Eskom unit • 11 Eskom stations benchmarked against 100 international peers • In order to make stations comparable, technical adjustments were made to account for factors such as age of technological standard, cooling water mechanism, type of mills, boiler design, etc • Almost 100% of generation operations costs were covered by the benchmarking analysis O&M cost R/MWh, FY 2009 costs* 1st quartile 2nd quartile 3rd quartile 4th quartile Costs are relatively high as it is one of the recently ‘de-mothballed’ stations Power stations B C D E F G I J K H A 1 Dec 2008 cost projections, forecast FY 2009 station send out as at 1 Jan SOURCE: McKinsey benchmarking study 2008 3 3
New business drives the above inflation increase in operating costs, while the real cost per MW is constant New business drives the above inflation increase in operating costs While the real cost per MW is constant Rm Compound annual growth rate Total operating cost incl new business (Rm/MW) - real Existing business operating cost (Rm/MW) - real +11% 42 656 +52% 2 809 38 780 1.5 35 621 1 609 -20% 1 882 1 521 1.4 2 275 +43% 6 853 1.3 31 312 3 028 5 637 DSM 800 1.2 3 885 3 158 Cost of cover 1.1 2 361 New 1.0 0.9 0.8 +8% 31 385 28 986 0.2 27 187 Existing 24 993 0.1 09/10 10/11 11/12 12/13 09/10 10/11 11/12 12/13 4 4 SOURCE: MYPD 2 application
We have the world cheapest electricity, but just do not have enough ……and assuming no change for other counties
Residential tariffs a different story ……and assuming no change for other counties
Eskom’s new alternative • Smoothed over 3 years • 35%, per year, over 3 years • Price increase over period to 82c/kWh • R14bn peak cash shortfall in Eskom • Eskom will look into other funding interventions to address the expected shortfall • A re-opener may be necessary if our • funding assumptions do not materialise New • Smoothed over 3 years • 45%, per year, over 3 years • Price increase over period to 99c/kWh • R30bn peak cash shortfall in Eskom • Eskom will look into other funding • interventions to address the • expected shortfall Old New alternative Previous alternative Not all risks are within control of Eskom & participation of stakeholders necessary to manage these risks
Summary • We require strong partnerships to make this happen • The significant shift in risk appetite will mean the introduction of independent private producers in power generation, phasing of the supply side expansion programme, intensifying energy savings and greater cost efficiency • Eskom commits to achieve the operational efficiencies in this application. • Robust monitoring process required • Failure to reduce our energy use and introduce private participation in power generation, would require a review of strategy and will create a power generation gap in the next five years with its consequent disastrous impact on the economy. • Eskom cannot do it all alone, hence the application comes with significant risks that we as a country have to manage together • A re-opener may be necessary if we not successful
The value proposition of this application remains the same Conclusion • Ensuring the continuous supply of power • The oxygen of South Africa • Setting a foundation for a cleaner and • greener future • Build capacity for the future needs of the • country • Empower the industrial development and • economic growth of the country • Create employment opportunities • Build confidence in the future