160 likes | 171 Views
DOECAP Pilot Audit – Phase I The Saga of a Thorough, but Inefficient Audit. September 2016. September 2015 Annual QA Planning Session. 2016 objectives and plans set for QA organization Including audits by Larry Penfold, one scheduled for Denver lab
E N D
DOECAP Pilot Audit – Phase IThe Saga of a Thorough, but Inefficient Audit September 2016
September 2015Annual QA Planning Session • 2016 objectives and plans set for QA organization • Including audits by Larry Penfold, one scheduled for Denver lab • Audit to be done using TestAmerica (TA) SOP and checklist developed over last 15 years
January-February 2016 • Received procedure no. AD-1-2A “Conducting DOECAP Laboratory and TSDF Pilot Audits” • Denver lab informed selected to participate in a “Phase I” pilot audit • Received DOECAP checklists Happy New Year
March 2016Plan for Denver Lab Audit Objective: Dual audit covering both TA QA program requirements and all DOECAP requirements Misfit? Shouldn’t be: Based on same standard (ISO, TNI, QSM/QSAS) Only DOECAP Module 6 is not covered in TA QA audits
March 2016Compared DOECAP/TA Checklists • In most cases 1 line of inquiry satisfies both • Biggest difference is organization of checklists • TA uses separate checklist per lab section
March 2016 Each Line of Inquiry Compared • Here only 1 DOECAP line of inquiry not explicitly covered in TA checklists • Easy to modify audit to include the few extra lines of inquiry
March 2016Audit Conducted On-site effort was similar to typical time for the on-site by a DOECAP audit team: • 5 people involved, covering 10 lab areas • Total time approximately 90 hours One important difference as to what had to be done to document the audit…
Size of Completed Checklists Guess which stack is DOECAP’s and which is TA’s?
Completed Checklists In My Usual Fashion • Handwritten notes for observations and findings • But not all details entered when requirements were met and I knew where the supporting evidence could be found • Sufficient notes to conduct de-brief and prepare final report • Audit completed April 7, 2016 • Audit report issued April 25, 2016 • In May I was pulled to other projects
The Big Crunch • Crash effort to type the DOECAP checklists in early July • For each question, explained exactly how the lab is compliant or not • - Then list source of • supporting evidence, • such as SOP#, log ID, • section# QA Manual… • 20-30 hrs of work
The Bad Part • Made it unnecessarily tough for DOECAP team! • Left them only 1 week to review a 3.85 lb package
The Best Part • July 12-14 on-site audit by DOECAP • August 2016 received letter that the Denver lab (TAA) successfully completed Phase I, and approved for a Phase II limited scope audit in 2017
Observations • TestAmerica’s audit checklists cover almost all the same ground, but • DOECAP’s checklists are long and have more detail, particularly for systems requirements, with some redundant questions • DOECAP’s checklists are in-depth in some technical areas, such as radiochemistry, but also • Light in some technical areas, such as TCLP
Main Lesson Learned Make It Easy for the DOECAP Auditors • Don’t be like me • Budget enough time to do a good job on the checklists
Postscript & Additional Lessons Learned • Phase I pilot audit conducted last week at another TA lab • This time only used 1 checklist • TA’s internal audit procedure now recognizes audit conducted with DOECAP checklist + some additions • Checklist to be completely written prior to final report