1 / 5

Choosing JOC Services: Important Considerations, Costs, and Comparisons

Learn about the key factors to consider when deciding to utilize Job Order Contracting (JOC) services, including design level, scheduling flexibility, project delivery time, cost assessment, resource availability, and accountability. Compare project costs between JOC and Design-Bid-Build methods. Contact Bob Bourg, Claims and Disputes Manager, for questions and discussions.

dcrabtree
Download Presentation

Choosing JOC Services: Important Considerations, Costs, and Comparisons

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. JOB ORDER CONTRACTING (JOC)Things to Consider When Making the Choice to Utilize JOC Services

  2. CONSIDERATIONS • Level of Required Design • Flexibility of Scheduling • Expediency of Project Delivery • Cost and Value Assessment • Staff and Resource Availability • Accountability • Buy-In to the JOC Process

  3. Relative Schedule Comparisons Between Contracting Methods Assume: $200,000 Construction Cost + Non-Elective Change Orders/Basic Design Requirements/120 Day Construction Duration DESIGN-BID-BUILD JOB ORDER CONTRACTING

  4. Relative Total Project Cost Comparisons Between Contracting Methods Assume: $200,000 Construction Cost + Non-Elective Change Orders/Basic Design Requirements/120 Day Construction Duration DESIGN-BID-BUILD DESIGN COST: $30,000 CONSTRUCTION COST (Including Non-Elective Change Orders): $225,000 TOTAL PROJECT COST: $255,000 JOB ORDER CONTRACTING DESIGN/SCOPING EFFORT COST: $20,000 CONSTRUCTION COST (Including Non-Elective Change Orders): $240,000 TOTAL PROJECT COST: $260,000

  5. Thank you Questions and Discussion BOB BOURG Claims and Disputes Manager (360) 407-9370 bob.bourg@des.wa.gov

More Related