An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. V363 – All hands review Sept 13th , 2012.

  2. Agenda Program Build Event timing Cosma part content Schedule A summary Facility update Tool order Status Part Feasibility Status Die tooling timing Status Assembly tooling Status Tier 2 Status PPAP Projections per build event Quality team update Next steps

  3. Program Build Event timing Open question on TTO build, when will this take place? 2 weeks prior to TT MRD or at start of TT MRD? Need confirmation on build event vehicle quantity

  4. Cosma part content DS73-F281B09-AG

  5. Schedule A Summary EXAMPLE ONLY

  6. Facility update - Milestones • June • Groundbreaking: 25th • July • Pad Built: 13th • August • Foundations Poured: 10th • Structural Steel: 31st • Utilities Installed: 31st • September • Roof Constructed: 14th • October • Warehouse Electrical: 26th • November • Ready for Equipment Installation: 15th • December • Office Construction in Process • January • Office Build Out: 25th • February • Final Occupancy: 15th

  7. Facility update

  8. Tool Orderstatus (Cosma Toolorder) • Tool orders pending due to: • Ford sourcing decisions • VTA approval (Ford finance) • Tooling is not quoted at latest design level • No Tier 2 pricing provided to Cosma • * CK41-V80925-BA funded to 35%, commitment was 100%

  9. Part feasibility Daily meeting schedule • Mon / Wed / Fri 1 hour meeting with PD/Cosma Plant/Toolmakers etc.on Underbody Issues • Tue / Thur 1 hour meeting with PD/Cosma Plant/Toolmakers etc. on Upperbody Issues Help needed: Feedback from the meeting is most of the feasibility changes that are approved are caught up in a ‘CAD queue’ – in some instances for some weeks? Where Cosma see issues with a part being made in EU with ‘no-issues’ support is required in clarifying process/simulation etc.??

  10. Die tooling status (Summary PTS matrix) • Stamping Feasibility: 84- Stampings • 54 green • 19 yellow (workable solution-waiting on released CAD) • 11 red • 10 no TO’s • PCF1 Feasibility: 39-Stampings • 26 green • 7 yellow • 6 red • 28 partial TO’s • 9 no C/Fixture TO’s • Stamping and Assembly Check Fixtures: • 56 sourced • 57 with LD/MP, need sourced • 55 no Locator Drawing / Measuring Points • 8 no feasibility • 94 no TO’s

  11. Assembly Tooling Status & Timing Risks • Timing Risks • LOI’s only due to lack of progressive payment agreement • MRD for Stampings from Assembly Suppliers • Working through a number of feasibility issues • Need Phase II PCF1 assembly list

  12. Tier 2 Supplier Status

  13. Tier 2 Supplier Status • Help Need with the following open items • Per meeting June 28th , Ford was to supply BOM with Tier 2 and costing details for each item by July 31st. • Based on this, the following process has been used to make progress • Obtain directive T2 listing from FNA Purchasing (8/10) • Confirm T2 List with PD (8/13-8/17) • Confirm T2 List with each supplier for agreed parts for sourcing status. (8/17-todate) • FMC terms approval to buy parts from T2 off FMC owned tooling. • NA complete, EU pending • Commercial terms to be agreed with each T2 • Transportation/handling fee needs to be agreed upon • Tier 2 pricing, transportation, handling need to be updated into pricing. • Flat release notification in Aug, 2012 needs further study and clarification from FMC.

  14. Open Concern Notices – Road Blocks NoticePN. IssueRoad Block / FMC Help Required C12536023 CK41-V200K27-A T2 Cannot meet PPAP dates due to no tooling KO C12555876BK31-V25081-B No NA Suppliers Identified C12560747CK41-V114B12-B New Assy – Cosma Quoted – awaiting sourcing direction C12562377 CK41-V/H103B73-A No NA Suppliers Identified C12591697BK31-V28442/3-A No NA Suppliers Identified BK31-V40984/5-A No NA Suppliers Identified BK31-V41058/9-A No NA Suppliers Identified BK31-V45108/9-A No NA Suppliers Identified C12588942BK31-B10746-B No NA Suppliers Identified C12574066BK31-17K755-A No NA Suppliers Identified BK31-V114A66-A No NA Suppliers Identified CK41-V101A14-B No NA Suppliers Identified CK41-5B498-A No NA Suppliers Identified BK31-B104A86-A No NA Suppliers Identified BK31-B612W70-A No NA Suppliers Identified BK31-B612W70-C No NA Suppliers Identified CK41-17K755-A No NA Suppliers Identified BK31-V114A66-AB No NA Suppliers Identified C12602935 BK31-B10912-A No NA Suppliers Identified CK41-V40C92-A No NA Suppliers Identified Current direction within PD is to ‘AC’ all open concerns with engineering estimates for cost and timing prior to Cosma submitting the related 12 Questions / Support Plan.

  15. PPAP Projections per build event

  16. Quality team update • Quality Manager and Senior QE in place. • QM: Will Drambour: Aug 1, 2013 • SQE: Ron Saylor: Aug 25, 2013 • Participating in process design reviews with engineering and integrators. • Development of Core Documentation. Pre-launch phase pFlow, pFEMA, Control Plan • Prodomax: 11/5/13-2/1/13 Massive: 11/9/13 – 2/25/13 • Paslin: 11/30/13-2/21 Cims: 11/15/13 – 1/31/13 • Amending Magna Supplier Quality Manual. • Pre-Launch Activity: 12 weeks • Burst Run 1 & Q loop • Burst run 2 & Q Loop • Phase 0 Run • 30 piece Layout, Phase 1/2 • Early Launch containment planning. Clear pass/fail Criteria to confirm upstream controls are effective in preventing quality problems from getting shipped to the customer. • Regularly communicating with Ford Kansas City key stakeholders.

  17. Wrap up • Next Steps follow up items • Thank you for your time!