1 / 5

Fri day 11.6

Fri day 11.6. Initial plan for the Friday: Morning: Collimator setup at 3.5 TeV . Afternoon: controlled longitudinal emittance blow-up. Night: Transverse feedback system commissioning. 09: 0 0 : Cold compressor failure in Pt2 Recovery not expected before 15:00. Giving access until noon:

Download Presentation

Fri day 11.6

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Friday 11.6 • Initial plan for the Friday: • Morning: Collimator setup at 3.5 TeV. • Afternoon: controlled longitudinal emittance blow-up. • Night: Transverse feedback system commissioning. • 09:00 : Cold compressor failure in Pt2 • Recovery not expected before 15:00. Giving access until noon: QPS boards RCD.A45B2 and RCBXH1.R1. RQS.A12B2 QPS cable repair in IR1. MKI timing in Pt8. Cryo in Pt2 and Pt4. Noisy reading of temperature at current lead of DFBX.R8 – RD1.  BI in Pt4 for installing new photo multiplier for abort gap monitor. RF in Pt4 • Finishing 10 A/s commissioning test in S78. 8:30 meeting

  2. Friday 11.6 • 15:30: Cryo back in Pt2  revised planning: • Transverse damper studies for afternoon. • Ramp and Squeeze with separated beams at night. • Collimator setup at 3.5 TeV Saturday morning • 16:00 : Pre-Cycle: • RCBXH2.R8 trip during recycle. • Access needed in UX45 for a problem on the BQM crates power supply. • Vacuum fault on the dilution kicker, acknowledged by the kicker piquet. • 18:30: Cryoproblems in sectors 78 and 81 (turbine in Pt8)  bothsectors need to be switched off. • 02:45 :Cryo back in S78 and S81: • Starting pre-cycle in both sectors. • 03:13: Lost cryo maintain in arc 81. 8:30 meeting

  3. Transverse damper studies • 02:45 : Cryo maintain back for arc in S81: • Starting pre-cycle of sector 81. • RCS.A45B1 QPS not OK; need to switch to board B. • 05:45 : Ready for injection: • 06:00: Problem with power converter in TI 8 (RBIH.80407). The DCCT returns zero, even though it is on and the correct function is loaded. • Injecting Beam1 only for the time being. • Revised planning after loss of 30 hours (tbc): • Collimator setup at 3.5 TeV Saturday morning • Transverse damper studies for afternoon. • Ramp and Squeeze with separated beams at night. 8:30 meeting

  4. TI8 Transfer Line Fault ✔ LMC report

  5. Program for the next 2 weeks ✔ LMC report

More Related