70 likes | 90 Views
Michigan Public Service Commission. MPSC Staff PURPA Technical Advisory Committee Avoided Cost Administrative Process Proposal (For Discussion at February 10, 2016 PURPA TAC Meeting). PURPA TAC Recommendations.
E N D
Michigan Public Service Commission MPSC Staff PURPA Technical Advisory Committee Avoided Cost Administrative Process Proposal (For Discussion at February 10, 2016 PURPA TAC Meeting)
PURPA TAC Recommendations • Report issued on April 8, 2016 will evaluate and recommend an avoided cost methodology to the Commission. • Utilities with “all-requirements” supply arrangements would likely have their avoided cost rate based on those purchases. • Report will recommend detailed filing requirements for each utility according to Section 292.302.
Path to Satisfy Act 304 6(j) (13) Assumptions: • The initial Commission proceeding to approve the capacity charges and avoided cost methodology must be a contested case. • Approving an avoided cost methodology and calculation in a contested case for each utility may satisfy the need for contested case capacity approval for each PURPA contract.
PURPA Administrative Process • MPSC issues Order establishing the following: • Establishing separate docket numbers for each rate-regulated utility with the following filings made within 30 days: • cost information pursuant to Section 292.302 of the PURPA regulations • avoided cost calculation based on the methodology recommendations in the PURPA TAC report • Docketed cases are processed in a consolidated manner following the contested case guidelines by one Administrative Law Judge • Parties may contest the methodology, calculation and inputs to the calculation of avoided cost • Commission approves methodology, calculation and inputs to the calculation for each utility and directs utilities to file standard tariffs for QFs 100 kW and smaller • Order directs each utility to file updated avoided cost and calculation inputs every two years
PURPA Contract Approval Process • Utility files executed QF contracts for approval under Act 304 6(j) (13), outside of a PSCR case. • Most likely, at the time of each contract filing, the Commission will determine whether a contested case is needed.
Biennial Process • Assumes that a contested case is not required unless the methodology is being changed. • Electric providers file the following: • FERC Section 292.302 cost data • Inputs and calculations based on previous avoided cost methodology order • Updated avoided cost schedules for the standard rate • Updated information is approved ex parte. • Intervenors can request a contested case.
Possible Timeline • PURPA TAC Report filed April 8, 2016 • Commission issues Order – June 2016 • Within 2 months, utilities make filings pursuant to the Order to kick-off docketed contested cases • Final Order issued within 9 months or earlier if there are settlement(s) – May 2017 • Executed PURPA contracts are filed for approval outside of PSCR case filings. The Commission will determine whether the case can proceed on an ex parte basis.