GWRS Final Expansion Project and SP-173 Update. GWRS Steering Committee Meeting April 11, 2016. Groundwater Replenishment System (GWRS) Projects. GWRS Project (Completed 2008) Construction of 70 MGD Treatment Facility with future expansion capacities , Injection Wells, and Pipeline
E N D
GWRS Final Expansion Project and SP-173 Update GWRS Steering Committee Meeting April 11, 2016
Groundwater Replenishment System (GWRS) Projects • GWRS Project (Completed 2008) • Construction of 70 MGD Treatment Facility with future expansion capacities, Injection Wells, and Pipeline • GWRS Initial Expansion (Completed 2015) • Expansion of 70 MGD Treatment Facility to 100 MGD including SEFE pump station & storage tanks • GWRS Final Expansion (Completion TBD) • Expansion of 100 MGD Treatment Facility to 130 MGD including water supply pipeline, EQ tanks, pump station & treatment process reconfigurations at OCSD
GWRS – Advanced Water Treatment Facility (AWTF) Improvements Three New UV Trains Six New RO Units Microfiltration West Bldg Expansion (1.5 new trains) New Decarbonator and Cartridge Filter New Product Water and BW Supply Pumps N
GWRS Source Water • To produce 130 MGD of GWRS water – approximately 174 MGD of Secondary Effluent is required from OCSD (including 4 MGD of GAP source water) • OCSD combined Plant No. 1 & Plant No. 2 total influent flows are currently 182 MGD • Santa Ana Regional Interceptor (SARI) discharges to OCSD Plant No. 2 are currently ~30 MGD • OCWD is currently not permitted to use SARI source water for GWRS by the Division of Drinking Water (DDW) • GWRS Expert Panel initial evaluation of recycling SARI water through GWRS deemed feasible with recommendations. DDW will have to provide approval and conditions for SARI to be recycled.
OCSD/GWRS Final Expansion Flows • Assumes 4 MGD Secondary Effluent for GAP and 85% RO Recovery; • Exact diversion flows are currently being evaluated by OCSD; • Potential additional source flows include Extraction Well Discharges, MF Cleaning Wastes, Additional SARI WW Diversions
405 Freeway OCWD GWRS Facility OCSD Plant No. 1 Exist 66-inch Pipeline to be Rehabilitated Santa Ana River OCSD Plant No. 2 New EQ Tank New Pump Station
GWRS Final Expansion Implementation Plan Plant No. 1 Plant No. 2
GWRS Final Expansion Preliminary Cost Estimate *Represents total costs for OCWD. Planned OCSD & OCWD CIP Projects not included
Initial Draft GWRS FE Project Unit Cost Estimate 1) Unit cost based on increased production of 31,000 af/year; 2) Melded unit cost combines current operating unit costs with GWRS FE unit costs for total production of 134,000 af/year
Next Steps • Staff to review Draft SP-173 Implementation Report in May 2016 • Final SP-173 Implementation Plan complete in July 2016 • OCWD Complete CEQA & Engineer’s Report to establish project in August 2016 and pursue grant funding opportunities • OCSD present SP-173 findings to July Operations Committee Meeting • OCSD & OCWD to prepare amendment to joint agreement • Implementation plan & each agencies responsibilities to be included • Initiate MF Pilot Studies at OCSD Plant No. 2 to evaluate water quality impacts • OCWD staff and GWRS Expert Panel will continue refining recommendations for recycling SARI