Permits. The Process. Plans are developed by an Architect or Engineer and presented to the Municipality State Environmental Quality Review (SEQR) declaration is made by municipality
E N D
The Process • Plans are developed by an Architect or Engineer and presented to the Municipality • State Environmental Quality Review (SEQR) declaration is made by municipality • “requires the sponsoring or approving governmental body to identify and mitigate the significant environmental impacts of the activity it is proposing or permitting.” • “standardized our environmental assessments by using the Environmental Assessment Form (EAF) and special guidance documents “ • Steps
State Permits • Storm Water Pollution Prevention Plan • Must show how storm water impacts will be mitigated and water quality improved • Must have a qualified inspector on site at all times • Must have Erosion and Sediment Control Plan • Concrete Washout Area • Spill Cleanup • Weekly Inspections by Qualified Professional ($)
State Permits • Highway Access Permits • Required for construction access & final access off of a state highway • Not issued until project is approved by municipality and other state agencies • Highway Work Permits • Permits work in the right of way of state highways • Not granted until needed, valid for 1 year • Utility and non-utility work
State Permits • Sanitary Sewer Permit • DEC permit for extending a municipal sewer line • Looks at capacity of sewer lines, sewage plant • Also looks at water capacity • Water Permit • County DOH and State DEC
State Permits • Wetlands – freshwater and salt water • Buffer zone • Mining – over 750 cy per 12 month period • Historical or cultural Site • State Pollution Discharge Elimination System (SPDES) SEQR information is compiled into an Environmental Impact Study
Federal Permits • Federal Wetlands • US Army Corps of Engineers • Federal wetlands are different from State • Can work in but must mitigate
Site Plan • Planning Board • Approves all aspects of site plans • Uses state and county agencies and town engineers to determine completeness of the application • Zoning Board of Appeal • Approves variances in the zoning requested by the developer
Permits after Site Plan • Building Permit • Plumbing Permit • Electrical Permit • Sewer Permit • Water Permit • All require inspections
Inspections • SWPPP – weekly • Concrete • Asphalt • Compaction • Sewer • Water • Ponds • Others as specified in contract • MUST have documentation that inspections were completed with satisfactory results