150 likes | 162 Views
EPC: data collection and baseline creation. Coordination Berlin Energy Agency Französische Str. 23 D-10117 Berlin Germany Fon: +49 (30) 29 33 30 – 0 Fax: +49 (30) 29 33 30 – 99 eurocontract@berliner-e-agentur.de Main Project Contact: Alexandra Waldmann Waldmann@berliner-e-agentur.de
E N D
Coordination Berlin Energy Agency Französische Str. 23 D-10117 Berlin Germany Fon: +49 (30) 29 33 30 – 0 Fax: +49 (30) 29 33 30 – 99 eurocontract@berliner-e-agentur.de Main Project Contact: Alexandra Waldmann Waldmann@berliner-e-agentur.de Project Website: http://www.eurocontract.net EPC: data collection and baseline creation Project Partners: Austria: Grazer Energy Agency, Austrian Energy Agency UK: MidWales Energy Agency, Sweden: Swedish Energy Agency Norway: Norwegian Energy Efficiency Inc. Finland: Motiva Oy, France: ADEME, Italy: Regional Energy Agency of Liguria Italian Federation for the Rational Use of Energy Greece: Centre for Renewable Energy Sources Berliner Energieagentur GmbH
EPC: data collection and baseline creation • Background: Dipl.-Ing. Susanne Berger, Berliner Energieagentur GmbH project management and monitoring of existing EPC, focus Energiesparpartnerschaft Berlin • Outline: 1. introduction: step-by-step instructions 20 min 2. baseline-training 25 min 3. discussion15 min • Material: - presentation - baseline data sheet Berliner Energieagentur GmbH
period X invoices for energy and water I. correction for baseline year II. baseline year fuel/heat consumption electricity consumption water consumption connection power connection power kWh heat consumpt. kWh electr. consumpt. m³ water consumpt. III. IV. prices of baseline year EPC: data collection and baseline creation I. baseline overview BASELINE Berliner Energieagentur GmbH
EPC: data collection and baseline creation • STEP I collection and list of invoices • collect all energy bills for each building with consumption in the baseline year • baseline year = last finished year with complete metering and billing • list meter by meter, building by building into one data sheet • note extra information (provider, metering number, factors, date of fitting, extra meters..) • compare to own meter readings of building management DONT: • use of automatic estimations from energy invoices • list of extra meters for suppliers, that will not be affected by energy saving measures (example: caretakers flat, storage buildings, ...) • list of fuel amount ( litres of fuel oil, m³ of gas ) – instead use kWh (if necessary calculate by caloric values) Berliner Energieagentur GmbH
EPC: data collection and baseline creation • STEP II correction for baseline year • calculated in the data sheet • from bills counting time/consumption before/after baseline year, baseline consumption has to be excised ELECTRICITY / WATER consumption is corrected by number of days: example: kWh Baseline = kWh bill x 60/100 Berliner Energieagentur GmbH
EPC: data collection and baseline creation • STEP II correction for baseline year HEAT • everydays consumption is not constant, but depending on outsides temperatures consumption is corrected by median temperature of days example: kWh Baseline = kWh bill x ∑ (median temperatures) 60 days / ∑ (median temperatures) 100 days Berliner Energieagentur GmbH
EPC: data collection and baseline creation • STEP III prices correction • prices of the baseline year are reference prices for the hole EPC period constant calculation basis for the invests • each building / meter may have different prices / mix prices just if necessary • list in data sheet: • prices for consumption • fix prices (connection power, metering, ...) • tax parts of prices • further information (changes in price system) • tax parts of prices are not fixed for the EPC period share of risks DONT: • use prices per litres oil or m³ gas – always calculate per kWh (fuel switch) • use gross prices – calculation is done in net, also baseline is net Berliner Energieagentur GmbH
EPC: data collection and baseline creation • STEP IV baseline calculation • costs baseline: calculation based on reference price and baseline consumption • formula: • baseline calculated net – exclusive of VAT, VAT is just rated per each yearly accounting • verification /check for representativeness • comparison with other years • comparison to benchmarks • check for special events /changements in the baseline year Berliner Energieagentur GmbH
EPC: data collection and baseline creation • STEP IV baseline documentation • part of the baseline documentation, beside its calculation, are: • information about work time (opening hours for public buildings, work schedule, class schedule in schools) • scheme of yearly events • information about facilities and technical equipment (large-scale consumers of power, IT-equipment, lightning) • number of employees, pupil, students in each building • further special utilisations all equipment and activities in baseline year should be documented • baseline documentation should be part of the contract Berliner Energieagentur GmbH
period X invoices for energy and water I. correction for cleared year II. cleared year heat consumption electricity consumption water consumption corrected energy costs climate correction III. A costs heat III. B utilisations correction Baseline savings costs electricity kWh heat consumpt. kWh electr. consumpt. m³ water consumpt. costs water V. prices of baseline year IV. EPC: data collection and baseline creation Yearly accounting of energy savings - overview Berliner Energieagentur GmbH
EPC: data collection and baseline creation • STEP III A climate correction • yearly heat consumption is depending on climate (years may be colder/warmer than baseline year) • to calculate the savings in comparison to the baseline, a neutralisation of climate influences has to be done • useful is official statistical climate data • Germany: Gt15 if day colder than 15°C , than Gt15 = 15- median temperature of the day, else 0 • heat consumption for hot water generation is not climate depending • formula (example): • regulations for climate correction are part of the EPC-contract Berliner Energieagentur GmbH
EPC: data collection and baseline creation STEP III B utilisations correction BASELINE ADAPTION afternoon Berliner Energieagentur GmbH
EPC: data collection and baseline creation • Summary • baseline calculation is done based on energy bills • calculation method should be part of the EPC contract • changements in utilisation influencing consumption are very common – a method to their calculation / neutralisation should be agreed • for climate correction a calculation method based on official climate data should be fixed in the contract Berliner Energieagentur GmbH
Thank you for your attention and Good luck with your BASELINES! Berliner Energieagentur GmbH