PANTHER VILLAGE Phase II. Construction Update. 11/16/2012. PANTHER VILLAGE. CURRENT WORK West Wing - Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework installed, tile and grout installed
E N D
PANTHER VILLAGE Phase II Construction Update 11/16/2012
PANTHER VILLAGE • CURRENT WORK • West Wing • - Exterior: Masonry and shingles finished, fascia and soffit work ongoing- 1st Floor: Final coat of paint, casework installed, tile and grout installed • - 2nd Floor: Final coat of paint, tile and casework installed • - 3rd Floor: Tile and casework installed • - Attic: doors installed (no hardware yet) • East Wing • - Exterior: Masonryand shingles complete, fascia and soffit work ongoing • - 1st Floor: Final coat of paint, casework and counter tops being installed • - 2nd Floor: Painting, tile work mostly completed, casework being installed • - 3rd Floor: Mudding and taping drywall, rough sanding • Central Lounge Area • - Masonry completed • West Parking Lot • - Paving completed
PANTHER VILLAGE Brick and cast stone completed at Northwest lounge and stair area, curtain walls nearing completion .
PANTHER VILLAGE Northwest lounge area curtain walls nearing completion.
PANTHER VILLAGE Brick and cast stone complete on East wing. Northeast stair curtain wall not yet installed, flashing has started.
PANTHER VILLAGE Brick and cast stone completed at central lounge and stair. Weather barrier also installed on cornice.
PANTHER VILLAGE Temporary exterior enclosures installed.
PANTHER VILLAGE Temporary heat installed throughout entire building to accommodate acceptable working conditions and protection for products.
PANTHER VILLAGE First floor West corridor study/lounge area, metal stud framing completed.
PANTHER VILLAGE First floor West corridor four bedroom apartment, kitchen cabinets and some counter tops installed.
PANTHER VILLAGE First floor West corridor bedrooms, final coat of paint applied, visual display rails installed, shelving installed.
PANTHER VILLAGE First floor East corridor studio apartment, kitchen cabinets installed, counter tops soon to be installed.
PANTHER VILLAGE First floor East corridor bathrooms, tile floor and cabinets installed.
PANTHER VILLAGE Cabinet Unit Heater installed in West corridor staircase.
PANTHER VILLAGE West corridor third floor, curtain walls installed in private study room.
PANTHER VILLAGE East corridor two bedroom corner apartment ready for first coat of paint.
PANTHER VILLAGE Third floor central lounge area drywall being installed.
PANTHER VILLAGE Forms set for stoops located at the Northwest entrance. Will soon be pouring concrete.
PANTHER VILLAGE Bioswale located between the West wing of the building and the West parking lot.
PANTHER VILLAGE Storm sewer line running from West parking lot to bioswale in place.
PANTHER VILLAGE West parking paving complete.
PANTHER VILLAGE Concrete work completed at loading dock area.