1 / 14

PRESENTATION OUTLINE

MASIBAMBANE CO-ORDINATING COMMITTEE MEETING PROGRESS REPORT ON THE RURAL HOUSEHOLD INFRASTRUCTURE PROGRAMME (RHIP) 22 nd JUNE 2012. PRESENTATION OUTLINE. RHIP Overview RHIP Objectives Progress per Province – 2010/11 Challenges – 2010/11 Progress per Province – 2011/12

dennis-holt
Download Presentation

PRESENTATION OUTLINE

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MASIBAMBANE CO-ORDINATING COMMITTEE MEETINGPROGRESS REPORT ON THE RURAL HOUSEHOLD INFRASTRUCTURE PROGRAMME (RHIP)22nd JUNE 2012

  2. PRESENTATION OUTLINE • RHIP Overview • RHIP Objectives • Progress per Province – 2010/11 • Challenges – 2010/11 • Progress per Province – 2011/12 • Financial Performance – 2011/12 • Job Creation – 2011/12 • Health and Hygiene – 2011/12 • Challenges – 2011/12 • Way Forward – 2012/13 & 2013/14

  3. RHIP OVERVIEW • The RHIP is a special four year programme to provide basic sanitation (and water) to rural communities. • It has been allocated a total budget of R1.2 billion. • The budget is allocated to the NDHS as a Schedule 7 Grant - NDHS appoints IAs & enters into SLAs with WSAs. • The budget split over the MTEF is: • 2010/11: R100 million; • 2011/12: R231,5 million; • 2012/13: R479,5 million and • 2013/14: R389 million.

  4. RHIP OBJECTIVES • To support municipalities to address rural basic sanitation (and water supply) backlogs. • To improve the quality of life in rural communities. • To contribute to the rural development priority of government. • To contribute to job creation and Local Economic Development. • To contribute towards meeting the sanitation (and water supply) MDG targets of South Africa. • To accelerate delivery of sanitation (and water supply) to meet the 2014 target.

  5. PROGRESS PER PROVINCE - 2010/11

  6. CHALLENGES - 2010/11 • Programme started in Oct 2010 (procurement delays). • Some WSAs did not fully grasp the nature of Schedule 7 Grant and delayed signing SLAs with NDHS as they wanted to implement the programme themselves. • Excessive rainfall was experienced during December 2010 and January 2011 which caused delays. • Implementing Agents struggled to source building material and have it delivered on site on time. • Some contractors struggled with difficult ground conditions i.e. hard rock and high water table.

  7. Progress Per Province – 2011/12 Draft and Confidential

  8. FINANCIAL PERFORMANCE - 2011/12

  9. JOB CREATION - 2011/12

  10. HEALTH & HYGIENE - 2011/12

  11. CHALLENGES - 2011/12 • The 2 appointed Implementing Agents (Mvula Trust and IDT) were not sufficient to implement such a programme at scale and achieve the outcomes set. • The existing SLAs between the NDHS and the Programme Management Support PSP (Maxima Global/TranSpace) on one hand and Mvula Trust and IDT on the other were not consistent with each other. • The process of handling claims of the Implementing Agents needed to be restructured to assist them with improved cash-flow management.

  12. CHALLENGES - 2011/12 cont… • The recovery plans submitted in Sept 2011 by the 2 Implementing Agents were too optimistic. • The IAs ability to procure building materials from suppliers in large quantities posed a serious challenge to the outcomes of the programme. • The scope of work approved for the IDT was at high risk of not being completed by end of the 2011/12 financial year. • In December 2011 NDHS re-allocated 7,098 units from IDT and negotiated with Mvula Trust to complete these units by the end of the 2011/12 financial year.

  13. WAY FORWARD - 2012/13 & 2013/14 • NDHS has reduced the previously budgeted allocations of IDT and Mvula Trust to a total of +/-60% of the 2012/13 budget (in line with NDHS Portfolio Committee recommendations). • NDHS is currently in process of putting the +/- 40% balance of the 2012/13 budget to tender for additional Implementing Agents to be added to the programme. • The SLA of the Programme Management Support PSP is to be aligned to the performance of the IAs. • In 2012/13 both machinery & manual labour will be used in difficult ground conditions where needed.

  14. THANK YOU

More Related