Bilan and Objectives SU Dominique Missiaen
Departures-Arrivals • Arrivals • Francis Klumb (ST) • Philippe Dewitte (ST) • Christophe Podevin • Sebastian Waniorek (FE) • Mathieu Duquenne (FE) • Petre Radut (VIA) • Michael Udzik (FSU) • Mehdi Belhay (FE) • Ales Hrabe (TECH) • Olivier Ggouabre Seri (TL) • Bruno Perret (TL) • 13 personsfrom the contract c201 • Departures : • Joanna Hulboj (FE) • Sylvain Griffet (FE) • Juha Kemppinen (FE) • Sylvain Mico (FSU) • Yann Bailly (VIA) • Mohamed Khamfir (TL) • Montse Montero (FE) • Christophe Podevin (end of August) • Bernard Noël (TL) ABP group meeting D. Missiaen
Before LS1 • Alignment of K12 and Na62 : • 1st beam in November 2012 • Linac4 : • Fiducialisation of Components : RFQ, CCDTL, DTL, etc • 3MEV test stand : RFQ, diagnostic line • Tunnel : marking on the floor, alignment of the source and LEBT • LHC • Fiducialisation of 15 dipoles and 3 SSS • Levelling tests in sector 67 to prepair LS1 NA62 LAV, STRAW, MUV ABP group meeting D. Missiaen
Before LS1 • low beta quads • Loadsensorsunder • Installation at PT 5 (100 %) and 2 (80%) • Visualisation under PVSS • Irradiation tests performedwithsuccess • Design of remote validation units for the HLS and WPS alignmentsystems • Prototypes validated (mechanics, electronics, acquisition and control) ABP group meeting D. Missiaen
Experiments ALICE DCAL : Load test CMS : YE4 assembly LHCb Magnet : Photogrammetry With and without B ATLAS IBL / New beam pipe: Mock-up scale1 (H180) LEB : Preparation of beam pipe changes (ATLAS, CMS, LHCb LS1, ALICE LS2) ABP group meeting D. Missiaen
NA62 – COMPASS – ALPHA – CAST – NA61 – ISOLDE – Others Non-LHC Experiments ALPHA Full installation • Survey in multiple areas • All along the year ISOLDE Survey of all lines CAST Grid, Dynamic survey COMPASS: New RPD, RICH, Liquid H target … HIE-ISOLDE Intégration 3D Scan Réunionannuelle 2012 D. Missiaen
LS1- accelerators LHC : -Fastlevelling - Network machine-exp. for Atlas and CMS PSB : Vertical shape SPS : Vertical realignment of the «hole» of sextant 6 TI2: V and H realignment ABP group meeting D. Missiaen
LS1 – accelerators (comingnext) • LHC : • LSSs and alignment of new components • Smoothing of the arcs fromSummernextyear • Maintenance of the permanent monitoring system of low beta quads • Installation of loadsensors and of validation systems for HLS and WPS in PT1 and 5 • SPS : • H and V realignment of all components • TI8 : H and V realignment of all components • TT10 • PS : Measurement/re-alignment of the PSR • Linac4 : • alignment of the components 3 MEV test stand in the L4 tunnel • Duringassemblychecks of CDDTL and DTL ABP group meeting D. Missiaen
LS1 -Experiments • Main survey done • Geodetic networks • Stabilities ATLAS – CMS • Experiment Opening surveys • ATLAS EE Muon alignment completed • CMS Pixel / bulkhead-YE1 3D scanning CMS Pixel Survey CMS Bulkhead/YE1 3D Scan • Some tasks for the next future • ATLAS: Muon Barrel / Install. Muon Sector 13 / Start of Open Close Monitoring installation • CMS: MABs Calib. / YE4 assembly start / Upgrade BCAM / Prepa insertion beam pipe and Pixel CT • ALICE: Installation DCAL and new TRD mod. • LHCb: Installation of new Beam Pipe (Full length) • And many others operations foreseen in 2014 ATLAS: Muon Barrel ABP group meeting D. Missiaen
Projects • CLIC • LAMBDA : validation of solution on short range • Development and validation of cammovers • Compact • Standard • Validation of the alignmentstrategy on the TBTM mock-up • Comparison of movementmeasuredwith CMM, WPS and AT401within 10 microns • Fiducialisation and active alignment : important progress • AbsolutemeasurementswithcWPS and oWPSwithin a few microns ABP group meeting D. Missiaen
Projects • HIE-Isolde • Bcam monitoring system • Open/Close monitoring system for Atlas • CLIC • Development of cammovers: • Standard and compact to betestedunder 5 DOF • Compatibility withstabilization solution to bechecked • Lambda project: • Validation of the concept on short range using a veryaccuratedisplacement table • Dimensional control, fiducialisation and alignment on test setups: • On the TBTM (including control of alignmentduring thermal and transport tests) ABP group meeting D. Missiaen
Projects • HIE-Isolde • Bcam monitoring system • Open/Close monitoring system for Atlas ABP group meeting D. Missiaen
Projects (future) • CLIC • Development of cammovers: • Lambda project: • Validation of the concept on short range using a veryaccuratedisplacement table • Dimensional control, fiducialisation and alignment on test setups: • On the TBTM (including control of alignmentduring thermal and transport tests) • Collaboration with NIKHEF: • Inter-comparisonbetweenalignmentsystems on short & long range • Follow-up of the spoke design in MDI area • PACMAN project (Particle Accelerator Components’ Metrology and Alignment up to the Nanometrelevel) • Marie Curie Initial Training Network, Innovative Doctoral Programme ABP group meeting D. Missiaen
Software and Database • The development of the APEX interface has been continued • Calculation menu • Measurements menu • Several versions of • Post-processing : LGC++, CHaBa++, • Data acquisition : SFB, PFB, carnet, Pctopo32 • Somedevelopmentswillbecontinuedduring LS1 ABP group meeting D. Missiaen
Conclusions • A huge LS1 ahead of us • A good start for the first 4 months • Motivation willbevery the mostdifficultthing to maintain all along the 20 months • But not only LS1 • LC and HIE-Isolde studiesstill continue • Software and databasedevelopments as well ABP group meeting D. Missiaen