1 / 7

SORCER

SORCER. Coordinators meeting. November 14, 2011. SORCER. Stimulating Obtaining Results in Communities in relation to Energy-efficiency and Renewables Integrated Project Call FP6-2005-TREN-4 CONCERTO II Contract nr: TREN/07/FP6EN/S07.70576/038588 SORCER. Apeldoorn

deon
Download Presentation

SORCER

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SORCER Coordinators meeting. November 14, 2011

  2. SORCER Stimulating Obtaining Results in Communities in relation to Energy-efficiency and Renewables Integrated Project Call FP6-2005-TREN-4 CONCERTO II Contract nr: TREN/07/FP6EN/S07.70576/038588 SORCER

  3. Apeldoorn Sewagedigester, withpoultrysludge (1.5 MWe) District heatingZuidbroek (2500 dwellings) EPC (shellbased) of 0.8 2.65 GJ/dwelling*yearadditionalenergysaving (e.g. 400 Wp PV/dwelling) Woodchipspeak boiler Hillerød Low temperature district heating Solar collectors 6000 m2 Class 1 Ecobuildings (-50%) 20000 m2 Class 2 Ecobuildings (-25%) Biomassgasifier Renovated buildings PV Sorcer content

  4. Zuidbroek54 months highlights • About 800dwellings delivered • Biogas CHP complete • PV grant setup for developers and house owners complete, about 50 kWp done, agreements on about 40 kWp, preliminary agreement on 135 kWp for housing corporations • Successful congress in Apeldoorn • Monitoring gives valuable results both for dwellings as for district heating system • (Temporary) Permit for 2.8 MW woodchips boiler (construction can start)

  5. Hillerød54 months highlights 3000 m2 solar thermal field complete Biomass boiler finished and in operation Class 1 buildings completed New buildings added to WP8. These include town hall, city college, office administration building, conference centre, dormitory 1500 m2 of low energy class 2 buildings reporting measurements PV plants on Town Hall, Klaverfabrikken, Hillerød Varme head quarter completed Gasifier under construction Control of low temperature district heating nearly implemented

  6. Yet to do • Complete PV plans in Zuidbroek and Hillerød • Complete refurbishment activities in Hillerød • Energy efficient street lighting • Complete woodchips boiler and municipal building in Apeldoorn • Monitoring • Extension to 6 years has been asked

  7. Progresssummary

More Related