An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Inter-Agency Environmental Review Committee August 19, 2009 PMH1 – IAERC 2009-08-19

  2. Agenda • Permit and Segment Update • Works to Date, Current Works Future Works; Design, Quality, and Training Update • Fraser Heights Connector • External Communications • Environmental Monitoring • Weekly Monitoring Reports • Water Quality and Noise Monitoring; Soil Sampling PMH1 – IAERC 2009-08-19

  3. Permit Update Project-wide PMH1 – IAERC 2009-08-19

  4. Permit Update Segment 1 – West PMH1 – IAERC 2009-08-19

  5. Works to Date Segment 1 – West • Construct Site Office • Clearing between Gaglardi and BC Hydro Sub-station • Clear and Grub for Gaglardi Compensation • Pacific Water Shrew and Amphibian Salvages throughout the segment • Installed Orange silt fence at ESA’s PMH1 – IAERC 2009-08-19

  6. Current Works Segment 1 – West • Constructing Test Channel in Willingdon Compensation • Fish window works • Sprott Culvert Installation • Salvage works • Pacific Water Shrew and Amphibian Salvage at Gaglardi Compensation PMH1 – IAERC 2009-08-19

  7. Current Works (con’t) • Salvages at North side of Hwy between Gaglardi and Kensington as well. • Salvages resulted in the capture of no SAR. Dusky Shrew and non-native amphibians were the only wildlife captured. • A fish salvage was conducted at Sprottand resulted in the capture of 3 Stickleback PMH1 – IAERC 2009-08-19

  8. Future Works Segment 1 – West • Construction of Gaglardi Compensation Channels • If geotech approves test Channel the Willingdon Compensation habitat will be constructed • Fish/ Amphibian Salvage at Kensington and then install culvert and move ditches PMH1 – IAERC 2009-08-19

  9. Future Works (con’t) • Surcharge will be installed from Gaglardi to BC Hydro Substation • Fill to be placed between BC Hydro Substation and Kensington Interchange • Sprott Bridge Demo to be initiated PMH1 – IAERC 2009-08-19

  10. Design Update Segment 1 – West • Received IFC drawings for Sprott and Kensington Culverts. PMH1 – IAERC 2009-08-19

  11. Quality Segment 1 – West • Quality audits scheduled for September/October • No environmental issues identified for July • No reported incidents identified for July • No Non-Conformance Reports in July or August PMH1 – IAERC 2009-08-19

  12. Training Segment 1 – West • This month toolbox training included: DFO Authorization Compliance, Spill Response/Reporting and Contingency Planning • Upcoming training to include: Sediment and Erosion Controls and Environmental Risk Management PMH1 – IAERC 2009-08-19

  13. Permit Update Segment 2 – Central PMH1 – IAERC 2009-08-19

  14. Works to Date Segment 2 – Central • Nelson Creek North of Highway 1 • Install Highway Detour Bridge Abutments • Temporary Ditch Excavation South of Hwy 1 • Brunette Ave to CPR Overpass • Temporary CSP Installation North of Hwy 1 • Woolridge St in front of Ikea • Popeye Creek Realignment • Isolated and Dewatered PMH1 – IAERC 2009-08-19

  15. Works to Date Segment 2 – Central • Lougheed Highway Wall Construction • Installation of Anchors; Erosion Controls • Mary Hill Bypass • Clearing and Access for Ground Improvements • Cape Horn Interchange • Temporary Ditch Diversion • Clearing and Prep for Pile Installation • Surcharge Monitoring PMH1 – IAERC 2009-08-19

  16. Current Works Segment 2 – Central • Popeye Creek Realignment • Excavation and MSE Wall Construction • Como Creek Culvert Extensions North of Highway 1 • Temporary CSP Installation North of Hwy 1 • East and West of King Edward • Temporary Ditch Hydraulic Tie-ins PMH1 – IAERC 2009-08-19

  17. Current Works Segment 2 – Central • Lougheed Highway Wall • Drilling Anchors and Placing Shotcrete • Mary Hill Bypass • Stone Column Test Grid • Cape Horn Interchange • Pile Installation • Detour Construction PMH1 – IAERC 2009-08-19

  18. Red Legged Frog Salvages • Como Creek • Popeye Creek • Pacific Water Shrew Salvages • Nelson Creek • Como Creek • Popeye Creek • Fish Salvages Have been conducted throughout the segment Segment 2 Salvages 2009-08-19 PMH1 – IAERC

  19. Segment 2 Salvage Totals • Three Spined Stickleback 2685 • Bullfrog Tadpoles/Adults 322 • Carp 209 • Green Frog Tadpoles/adults 298 • Northwestern Salamander 47 • Crayfish 7 • Pumpkin Seed 7 • Lamprey 23 • Cutthroat trout 5 • Longnose Sucker 4 PMH1 – IAERC 2009-08-19

  20. Future Works Segment 2 – Central • Complete Temporary Drainage Works prior to end of Fisheries Window • Mundy Creek Compensation • Piling and Stone Columns • CPR Bridge Demolition • Highway 1 Preload and Surcharge PMH1 – IAERC 2009-08-19

  21. Design Update Segment 2 – Central • Temporary Drainage Design Completed • Popeye Creek Realignment IFC Design • Appendix E Culvert at Mundy Creek and Dawes Hill Creek PMH1 – IAERC PMH1 – IAERC 2009-08-19

  22. Quality Segment 2 – Central • Quality audits schedules for September/October • No environmental issues identified for July • Ten reported incidents identified in July • Hydraulic fluid spills to the ground less than 2L • Excavator track sunk into ditch PMH1 – IAERC 2009-08-19

  23. Quality Segment 2 – Central • 1 Non-Conformance Report closed August 4 • Notification to Authority for Environmental Incident Report was not given within 24 hours PMH1 – IAERC 2009-08-19

  24. Training Segment 2 – Central • Environmental Workplans Introduced at Weekly Foreman’s Training • “Environmental Hazard Analysis” Sheet will be filled out for each operation • Upcoming training • Sediment and Erosion Control (In Preparation for Fall and Winter Rains) PMH1 – IAERC 2009-08-19

  25. Permit Update Segment 3 – Bridge PMH1 – IAERC 2009-08-19

  26. Permit Update Segment 3 – Bridge (con’t) PMH1 – IAERC 2009-08-19

  27. Permit Update Segment 3 – Bridge (con’t) PMH1 – IAERC 2009-08-19

  28. Segment 3 – Bridge Environmental Works to Date • Surrey, South Side • Songbird and Raptor Surveys • Wildlife Salvages • Bull and Green Frogs • Fish Salvages • 2 Red-legged Frogs • Falcon Monitoring PMH1 – IAERC 2009-08-19

  29. Segment 3 – Bridge Environmental Works to Date • Fraser River • Osprey Monitoring • Hydrophone monitoring during vibratory and impact hammer use. • Fish Migration Monitoring PMH1 – IAERC 2009-08-19

  30. Current Works Segment 3 – Bridge • Surrey, South Side • Sediment and Erosion Control • Clear & Grub • Watercourse Infilling • Drainage Works PMH1 – IAERC 2009-08-19

  31. Current Works Segment 3 – Bridge • Surrey, South Side • S1 Pile Installation and Excavation • S1 Pile Pour • Pylon Mockup • Drill Shaft Test PMH1 – IAERC 2009-08-19

  32. Current Works Segment 3 – Bridge • MARINE • Marine Communication Meetings • First Nation Meetings • Bubble Curtain, Hydrophone and Environmental Monitoring PMH1 – IAERC 2009-08-19

  33. Current Works Segment 3 – Bridge • MARINE • N1 Temporary Scour Protection • N1 Pile Installation • Trestle Pile Installation PMH1 – IAERC 2009-08-19

  34. Current Works Segment 3 – Bridge • Coquitlam, North Side • Osprey Monitoring • Trestle Construction • Access improvements PMH1 – IAERC 2009-08-19

  35. Future Works Segment 3 – Bridge • Ongoing Communication and Monitoring • In stream Work – Coquitlam Side • Trestle Construction • Pier N1 Pile Driving and Excavation • Pier N5/S7/S6 Pile Driving • Pier S9/S10 Drilled Shafts PMH1 – IAERC 2009-08-19

  36. Design Update Segment 3 - Bridge • Upcoming Drainage Designs • North side Drainage and Tidal Lagoon • Both Temporary and Permanent Design for United Storm Drain under North Side of Bridge being Considered. • Attended CoS Drainage/Environmental Meeting • Inquiry to NWPA and Transport Canada on Marine and Navigation Lighting PMH1 – IAERC 2009-08-19

  37. Quality Segment 3 - Bridge • Audit • TI Corp Preformed a Field Compliance Audit July 2009 • 0 NCR’s and 3 OFI’s • Good Housekeeping PMH1 – IAERC 2009-08-19

  38. Quality Segment 3 - Bridge • Segment 3 issues for July: • 1 Terrestrial Habitat issue • 1 Air Quality and Dust Control issue • 4 Fish Habitat issues • All issues were resolved and are now closed • Two reported incidents identified in Segment 3 • Hydraulic fluid spills to the ground less than 5L PMH1 – IAERC 2009-08-19

  39. Quality Segment 3 – Bridge • 1 Non-Conformance Report closed in June • 1. No flagging of American Robin’s nest • 2 Non-Conformance Reports opened in August • Impact hammering without bubble curtain • Impact hammering occurred outside of allowable daytime hours PMH1 – IAERC 2009-08-19

  40. Training Segment 3 - Bridge • Since Last IAERC Meeting, Segment 3 has conducted the following environmental training: • 8 Toolbox Meetings (24 to date) • 5 Foreman’s Meetings (13 to date) • 1 Mass Safety Meeting (2 to date) • 4 Environmental Awareness Training PMH1 – IAERC 2009-08-19

  41. Training Segment 3 - Bridge • Example of Training Topics: • Hazardous Materials and Spill Response • Housekeeping, Fuel Storage, and Sediment Control • Environmental Sensitive Areas and Songbird Windows • In stream Works and Concrete BMP’s • Environmental Work Plans PMH1 – IAERC 2009-08-19

  42. Permit Update Segment 4 – East PMH1 – IAERC 2009-08-19

  43. Works to Date Segment 4 – East • Clearing and grubbing in median from 160th to 216th • Culvert extensions in median • Compensation channel work at 160th Street interchange PMH1 – IAERC 2009-08-19

  44. Current Works Segment 4 – East • Fish window works for 2009 – culvert extensions and compensation area tie-ins • Salvage works • Pacific Water Shrew salvages at 160th Interchange • Fish Salvages throughout median • Oregon Forest Snail salvage at Strong Pit • Amphibians have been salvaged from Landfill Creek and H1-12C PMH1 – IAERC 2009-08-19

  45. Future Works Segment 4 – East • Continued Culvert work and median earthworks • Begin overpass structures work for 160th Street interchange • Finishing of compensation area at 160th Street interchange and tie-in to Hjorth Creek by Sept. 15 • Preload work at FHC • Compensation Channel and culvert work at FHC PMH1 – IAERC 2009-08-19

  46. Design Update Segment 4 – East • Upcoming compensation designs • Windsor Plywood August 31, 2009 • Upcoming E Culvert designs • Yorkson Creek E Culvert December 15, 2009 • Latimer Creek E Culvert November 30, 2009 PMH1 – IAERC 2009-08-19

  47. Quality Segment 4 – East • Site monitoring is ongoing for compliance with various permit conditions. • Requirements areincorporated in work plans • Independent Environmental Monitor present for all sensitive works PMH1 – IAERC 2009-08-19

  48. Training Segment 4 – East • Spill response training given at mass safety meeting • Fish window and ESA sensitive area training at PTI meetings PMH1 – IAERC 2009-08-19

  49. Fraser Heights Connector (FHC) Documents • Construction Environmental Management Plan posted to FTP site July 30, 2009 • Fisheries and Wildlife Mitigation and Compensation Plan posted to FTP site July 30, 2009 • MoE Water Act posted to FTP site August 5, 2009 • FHC IAERC Meeting was held July 23, 2009 PMH1 – IAERC 2009-08-19

  50. Fraser Heights Connector (FHC) Permits • MoE Water Act Application submitted July 30, 2009 • MoE Salvage Permit Application submitted July 31, 2009 • DFO 35(2) Application submitted August 13, 2009 PMH1 – IAERC 2009-08-19