1 / 13

UPDATE Montana Pipeline River Crossings PHMSA\Office of Pipeline Safety 2/8/2012

UPDATE Montana Pipeline River Crossings PHMSAOffice of Pipeline Safety 2/8/2012. Focus. Petroleum pipelines (crude oil and refined products) Major river crossings (greater than 100 feet) Located in Montana and rivers flowing into Montana Constructed with open-trench technology

devika
Download Presentation

UPDATE Montana Pipeline River Crossings PHMSA\Office of Pipeline Safety 2/8/2012

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. UPDATEMontana Pipeline River CrossingsPHMSA\Office of Pipeline Safety2/8/2012

  2. Focus • Petroleum pipelines (crude oil and refined products) • Major river crossings (greater than 100 feet) • Located in Montana and rivers flowing into Montana • Constructed with open-trench technology • Exposed or lack of depth-of-cover • River characteristics

  3. Information Collected or Obtained • Depth of Cover Surveys • Mainline Valve Alignment Sheets & Actuation Method • Worst Case Discharge • Integrity Threats Reports/Studies • Analysis Used for Remedial Actions (stream flow, depth-of-cover Remedial Actions taken in 2011 • Short-term Remedial Action Schedule • Long-term Remedial Action Schedule • Procedures to Monitor During Flood Conditions

  4. Progress Since July 2011 Release • ExxonMobil • HDD completed: Yellowstone River (Laurel) • HDD completed: Rock Creek • HDD completed: Clark’s Fork • CHS • Musselshell River: sandbag and increased patrolling • 3rd party analysis on Musselshell River • HDD will be complete before spring runoff

  5. EMPL - Preparing Pipe for Installation Under Yellowstone River - 8/27/11

  6. CHS Musselshell HDD – 2/6/12

  7. Progress Since July 2011 Release Cont. • ConocoPhillips • Depth-of-Cover surveys conducted for all major crossings • Belt Creek: added cover • Judith River: Grout bags/spring monitoring • Beauvais Creek: HDD completed • Coure d’Alene River: Grout bags/temporary repairs (Campground Rd, Sliver Bridge & Mile Post 476) • Beaver Creek: Line lowered (Refrigerator Canyon & Winston) • Tongue River (WY): Grout bags/spring monitoring

  8. Progress Since July 2011 Release Cont. • KinderMorgan • Clark Fork of Yellowstone River; Greybull River; Musselshell River: depth-of-cover surveys • Marathon (Wyoming) • Shoshone River; Wind River; Big Horn River: depth-of-cover surveys • True (Bridger Pipeline) • Poplar River/Missouri: Took out of service during flooding event • Yellowstone River and Poplar River: 2011 depth-of-cover surveys conducted and show adequate cover

  9. Montana River Crossings * Note: Montana Refining less than 5 miles with no water crossings

  10. Planned Remediation Measures • ExxonMobil • Monitor as normal (3 crossings were HDD’d since July 2011). Implement procedures to monitor during flooding • CHS • Musselshell River: HDD planned before 2012 spring runoff • Tongue River: HDD planned in 3-5 years • KinderMorgan • Monitor as normal. Implement procedures to monitor during flooding conditions • Marathon • Monitor as normal. Implement procedures to monitor during flooding conditions

  11. ConocoPhillips • Yellowstone Pipe Line: HDD across Clark Fork River at MP 319.1 (just east of Missoula) before Spring runoff • Yellowstone Pipe Line: stabilize with grout bags across East Gallatin River at MP 148.3 and install MOV before 2012 spring runoff & plan HDD in 2012 • Glacier Pipe Line: stabilize with grout bags across Judith River at MP 207.5 before 2012 spring runoff; 2012 HDD • Glacier Pipe Line: Monitor & plan future mitigation across Missouri River at MP 269.3 (stable bedrock trenched crossing) • Seminoe Pipe Line: Big Horn River – 2012 HDD • Other Remediation has been risk ranked for completion • True (Bridger Pipeline) • Yellowstone River and Poplar River: Continue to monitor through depth of cover surveys and ILI

  12. PHMSA’s Immediate Area of Focus • What is PHMSA’s immediate focus for 2012 Spring Runoff: • CHS • Musselshell River: Exposed line. FinishHDD by end of 2/2012 • Conoco Phillips • Clark Fork: Install HDD prior to 2012 runoff • East Gallatin River (MP 148.3): Exposed line. 2012 plan to install motor-operated valve before spring runoff. HDD later in 2012 • Missouri River (MP 269.3): Exposed line in stable bedrock trenched crossing. 2015 plan - Either HDD, New Trenched Crossing, Armoring, or Line Lowering

  13. Next Steps • Continue collecting and aggregating data • Monitor planned on-going remediation activities • Inspect new construction and remediation activities of water crossings • Ongoing information exchange with State, including the need for safety enhancements at water crossings • Develop enforcement actions for operator’s not following remedial action plans

More Related