December 6, 2006 Panama City – Bay County International AirportProjectUpdate
1970 1942 1995 Source: Panama City – Bay County Airport Authority
Economic Development • Airline / General Aviation • Aviation Related Industry • Thru-the-Fence Aviation Operations • West Bay Area Sector Plan • Regional Economic Development
Feasibility Study Site Selection Study Sector Plan and DSAP State Permits FAA Environmental Impact Statement (EIS) Land Donation Agreement Design USCOE 404 Permit Permit Challenge Zoning Regulations Existing Airport Sale Finalize Funding Construction Major Milestones
Design – Percent Complete • Site Development - 95% • Paving/Lighting/Navaids – 50% • Utilities – 50% • Terminal Building – 50% • Facilities (Rental Car, ATC, Maint., General Aviation, Public Safety) – 10% • Landscaping, Irrigation, & Signage – 30%
Terminal Design • Leadership In Energy and Environmental Design (LEED) Certification • Silver Level – U.S. Green Building Council • 20% reduction in energy use required (30% design goal) • Approximately 100,000 sq. ft. (56,000 existing) • Includes Customs and Immigration