PSD upgrade - schedule/resources: electronics and cooling system F. Guber INR, Moscow NA61/SHINEupgrade workshop, CERN3– 5 March, 2014
2013: PSD upgrade • July – September (Moscow) • Development and construction of FEE/HV/control prototype • and test at test-bench at INR - DONE • October-November (CERN) • Assembling and test of new electronics for one module at CERN - DONE • November – December (Moscow) • Mass production of new PSD electronics– DONE • - December (CERN) • Development, construction and test of the cooling system prototype for • one PSD module based on Peltierelement with real TEC controller. • - DONE
2014: PSD upgrade plans/schedule (I) • January (Moscow) • - Test of 28 FEE/HV/control for 28 modules prototype • at INR – DONE • February – March, 9 (CERN) • - Assembling, installation and test of electronics and temperature control system at 28 modules at the PSDand test its readout with old PSD electronics (one-by- one module)- DONE • ------------------------------------------------------------- • March 10 –April 5 (Moscow) • Test of FEE/HV/control for the rest of 22 modules at INR test-bench. • -Development of the PSD stand alone slow control –O.Petukhov, S.Morozov. • Development of the PSD stand alone cooling control system - O.Petukhov, S.Morozov. • 5-12 April (Dubna) -Development of the PSD slow control for NA61 DCS – • Oleg, Sergei, Tobiasz
2014: PSD upgrade plans/schedule (II) • - April, 13 - 30 (CERN)- Installation of FEE/HV/control/cooling and test of the PSD electronics and temperature control system at NA61. • June, 1 - 15 (CERN) • Test of FEE/HV/cooling/control systems for the whole PSD with old PSD readout electronics. Fight with noises! • Integration of the PSD cooling monitoring systems into NA61 DCS-O.Petukhov • Test of the PSD platform. • Development of the PSD event display in the existing event browser – O.Petukhov • - September 8 – 30 (20-26 Sep: NA61 CM) • The PSD commissioning and test on cosmic; • October 25 - December 16 • PSD run preparation and calibration (muons, protons). • Participation in the physics p-Pb run • Operation of the PSD during the run ???
PSD upgrade resources • Development and construction of the PSD FEE/HV/control • NA61 – INR agreement; • ~ 30 KCHF – INR in-kind contribution (workshop, travel, subsistence) • Development and construction of the PSD cooling & control system • ~ 12 KCHF - NA61 CF (materials) • ~ 6 KCHF – NA61 CF (subsistence, February, 2014) • ~ 12 KCHF – INR contribution(workshop, subsistence, travel) • ---------------------------------------------------- • Additional expenses are needed: • Power supply for cooling ~ 3K CHF (INR, if necessary) • Travel (tickets) ~ 9K CHF (INR) • Subsistence: ~ 50 kCHF is necessary! • - 18K CHF + (10 KCHF ??) - INR; • ~ 20 – 30 KCHF – ??