An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Kunstsilo og KulturskolenInformasjonsmøte om byggearbeidene

  2. Hva skjer? Bygging av kunstsilo og ny kulturskole

  3. Anleggsområdet

  4. Hovedfremdrift • September–Desember 2019 – Rivearbeider • Desember 2019 – Grunn og gravearbeider • November 2019-November 2020 – Betongrehabilitering • Januar 2020-Juni 2020 – Grunnarbeider betong • Mars 2020 – Glideforsakaling/ betongarbeider skiftarbeid • Sommer 2020 – Oppstart kulturskolen • Oktober 2020 – Tett bygg • Oktober 2020-Desember 2021 – «normale bygningsarbeider»

  5. Hva skjer frem mot jul? • I dag – Lukking av anleggsområdet og oppstart av rivningsarbeider.

  6. Rivningsarbeidene • Uke 40-41 - Rivning av trappetårn • Uke 41-43 – Rivning av silotak • Uke 42-43 – Maskinriving av stålbygg

  7. Rivningsarbeidene • Uke 44-47 – Maskinriving av kaibygg • Uke 48-49 – Maskinriving riving av trappetårn • Uke 49-50 – Knusing og opprydding

  8. Betongrehabilitering • Den gamle betongen skal gjennomgå en elektrokjemisk prosess, slik at holdbarheten blir bedre. • Vanlig prosedyre for bevaring av gamle betongkonstruksjoner

  9. Grunnarbeider • Graving for nye fundamenter under siloen • Fundamentering av nytt sidebygg • Håndtering av masser på området

  10. Etter jul Videre arbeid i grove trekk • Glidestøp – Arbeid døgnet rundt i tre uker

  11. Reising av havnebygg og nybygg på baksiden av silo

  12. Oppstart av Kulturskolen