1 / 15

Reducing Engineering standards: GOOD OR Bad?

AASHTO Subcommittee on Design July 14, 2008 David C. O’Hagan, PE Florida DOT State Roadway Design Engineer. Reducing Engineering standards: GOOD OR Bad?. SITUATION AASHTO ”Greenbook” FDOT Plans Preparation Manual (PPM) GOAL

dixons
Download Presentation

Reducing Engineering standards: GOOD OR Bad?

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. AASHTO Subcommittee on Design July 14, 2008 David C. O’Hagan, PE Florida DOT State Roadway Design Engineer Reducing Engineering standards: GOOD OR Bad?

  2. SITUATION AASHTO ”Greenbook” FDOT Plans Preparation Manual (PPM) GOAL To reduce the cost of DOT projects without sacrificing safety and operational/functional characteristics. ANALYSIS DOT’s Costs: Pre-construction, right of way, construction, maintenance. Maintenance: Insignificant differential. User Costs: Safety AASHTO vsppm

  3. AASHTO VS PPM OPTIONS • Maintain Status Quo: Use Variations Process to justify reduced criteria • Reduce PPM Criteria: Eliminates need for some Variation submittals • Revise Variation Requirements: Include a safety analysis to quantify impacts of reduced criteria.

  4. AASHTO VS PPM RECOMMENDATION Option 3: Require a safety analysis with Design Variations for all new and reconstruction projects when reductions in critical design elements are being considered. JUSTIFICATION • Variations Process already working well. • Means to quantify safety impacts of cross-section decisions. • Consistent with including non-DOT costs in our decisions (user costs in pavement-type selection).

  5. AASHTO vs. PPM • 2007 Study by Roadway Design Office • Construction Cost Differences Only • Interstate Widening (1.2%) • New Rural Freeway (8%) • New Rural Arterial (7%) • New Urban Arterial (10%) • New Overpass (21%)

  6. AASHTO vs. PPM • 2008 Study by Roadway Design Office: Include right of way and maintenance costs with construction costs. • Rural Arterial Widening • Urban Arterial Widening • Interstate Widening • New Overpass Construction

  7. SR 43 (US 301): Balm Rd to Gibsonton Dr. • Hillsborough County, 6.16 miles • Currently: Two-lane rural • New Design: Six-lane rural with sidewalk and shared-use path. • Design at 90% Complete when studied • Several Variations to eliminate ROW acquisition for typical section

  8. SR 43 (US 301): Balm Rd to Gibsonton Dr. As designed PPM Design • Construction: $82,200,000 • Right of Way: $10,200,000 (Ponds) • DOT Costs: $92,400,000 • Crash (20 yr): $95,600,000 • DOT+User Costs (20 yr): $188,200,000 • Construction: $82,800,000 (+0.7%) • Right of Way: $26,300,000 (+158%) • DOT Costs: $109,100,000 (+18%) • Crash (20 yr): $88,000,000 (-8%) • DOT+User Costs (20 yr): $197,300,000 (+5%)

  9. SR 50: US 19 TO CR 587 • Hernando County, 3.73 miles • Currently: Four-lane rural • New Design: Six-lane rural with sidewalk and shared-use path. • Design at 30% Complete when studied • Several Variations to eliminate ROW acquisition for typical section • Closed conveyance drainage system

  10. SR 50: US 19 TO CR 587 AS DESIGNED PPM DESIGN • Construction: $49,200,000 • Right of Way: $0 • DOT Costs: $49,200,000 • Crash(20 yr): $85,600,000 • DOT+User Costs (20yr): $134, 800,000 • Construction Cost: $58,100,000 (+18%) (Walls were +17%) • Right of Way: $0* • DOT Costs: $58,100,000 • Crash(20 yr): $79,100,000 (-8%) • DOT+User Costs (20yr): $137,200,000 (+2%) * $32,800,000 if open conveyance & excluding business damages.

  11. SAFETY IMPACT DIFFERENCES • SR 43 (Hillsborough) Side Slope: • HSM: +$6.6M • RSAP: +$9.4M Median Width: • HSM: +$1.0M • DOT Research: +$3.0M Combined: • HSM: +$7.6M SR 50 (Hernando) Side Slope: • HSM: +$6.0M • RSAP: +$9.7M Median Width: • HSM: +$0.5M • DOT Research: +$0.5M Combined: • HSM: +$6.5M

  12. Accident Modification Factors • Undivided Divided

  13. CONCLUSIONS Rural Widening: • Cost Savings are in ROW not construction. • Variations procedure working well. • AASHTO minimum criteria has significant safety impacts. • Recommend including typical section safety analysis in Variation process for non-3R projects. Additional Work: • Study Urban & Interstate Widenings • Study Overpasses • Review crash data of AASHTO-only states & compare to Florida

More Related