1 / 17

U.S. ATLAS TDAQ FY06 M&O Planning

U.S. ATLAS TDAQ FY06 M&O Planning. A.J. Lankford UC Irvine. ATLAS TDAQ Overview. Overview of FY06 TDAQ M&O Activity. TDAQ Construction Project continues beyond CD-4A. Most hardware acquisition and installation in FY06-07 Much software development, esp. HLT, continues.

dmitri
Download Presentation

U.S. ATLAS TDAQ FY06 M&O Planning

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. U.S. ATLAS TDAQFY06 M&O Planning A.J. Lankford UC Irvine

  2. ATLAS TDAQ Overview

  3. Overview of FY06 TDAQ M&O Activity • TDAQ Construction Project continues beyond CD-4A. • Most hardware acquisition and installation in FY06-07 • Much software development, esp. HLT, continues. • TDAQ M&O activity overlaps with Construction in FY06-07. • Construction Project ‘labor’ is ramping down quickly. • FY06 is first year of ‘significant’ M&O activity. • FY06 M&O activity focuses on DAQ & HLT Infrastructure s/w. • TDAQ M&O activities can be classified as: • Hardware commissioning • Hardware maintenance • Software commissioning • Software maintenance • Operations • Detector support • TDAQ support

  4. HLT/DAQ Component View

  5. Pre-series Hardware

  6. FY06 Hardware Commissioning & Maintenance • Hardware Commissioning • Complete commissioning of Pre-series system • 10% scale of final system w/ components of final specs • Commission final RoI Builder hardware • Commission DAQ infrastructure • Network infrastructure (large central switch)- connectivity to ROS’s • DAQ processors - SFI’s, SFO’s, L2SV’s, pROS’s • Racks & rack instrumentation • Initial complement of HLT processors - late in year • Hardware Maintenance • Pre-series system • RoI Builder • DAQ infrastructure • Test beds - particularly “performance testbed”

  7. Software Development: Transition to M&O • The Combined Test Beam Release of HLT/DAQ software was nearly complete with respect to DAQ and HLT Infrastructure functionality. • This release was commissioned, operated, and maintained for the 2004 ATLAS CTB Run. • Subsequent development of this HLT/DAQ software consists of: • Added functionality (e.g. fault tolerance & error recovery) • HLT selection algorithm development • Refinement of existing code based upon CTB and subsequent experience and feedback • Development of added functionality and algorithms is Construction Project activity. • Refinement of existing code is M&O activity. • Starting in FY05, software development is increasingly M&O. • After first physics run, software development will be entirely M&O.

  8. FY06 Software Commissioning & Maintenance • Software Commissioning • Commissioning of new functionality • Examples of U.S. activity: • LVL2 Supervisor and RoI Builder software • DAQ software • Monitoring • Inter-process communication and Information Services • Message passing • HLT Infrastructure software • Run Control & Supervision • LVL2 Steering • EF Dataflow • Software Maintenance • Maintenance of above (bug fixes, releases, TDAQ/Offline consistency) • Incorporate new functionality based upon experience

  9. FY06 Operations • Operating DAQ infrastructure in USA15 and SDX1 in support of Detector (and TDAQ) commissioning • Network administration • System administration (DAQ and HLT computer systems) • TDAQ support teams will start rotations once level of activity at Point 1 demands

  10. FY06 Detector & TDAQ Support • Detector Support • ROD Crate DAQ maintenance and support • Support for: • Detector-specific software development, e.g.: • ROD software • Online histogramming & monitoring • Detector commissioning • Detector calibrations (and test beam runs ?) • TDAQ Support • Support development & commissioning of other TDAQ subsystems • Examples: • SRB support for commissioning LVL1 trigger subsystems • Integration of HLT vertical slices • Network support for Dataflow performance tests

  11. FY05 M&O Activities • Hardware Commissioning • Pre-series system, including pre-series RoIB • DCS for TDAQ racks • Planning for TDAQ infrastructure commissioning • Hardware Maintenance • Set up RoIB test bench • TDAQ test bed maintenance & administration • Software Commissioning • Releases, release testing, release testing procedures • Software Maintenance • Maintain code authored by U.S. members, e.g.: • Message passing, Information Services, Online Histogramming, • HLT Steering, HLT Control, Monitoring • Synchronization of releases with Offline • Adapt/port code to new compiler and new CERN Linux

  12. FY05 M&O Activities – p. 2 • Operations • Completion of CTB run • System administration planning • Detector Support • TileCal beam test • Monitoring • Support of production and simulation of test beam data • TDAQ Support • Support integration with RoIB in CTB • Support of HLT algorithm integration • Test bed setup in UK, Dubna

  13. M&O Planning Methodology/History • Experience in FY04, particularly CTB, indicated prior estimates of M&O effort were low. • New bottoms-up estimate of M&O effort in Jan. 2005 • By “new kid on block”, w/ input from all involved • Based on effort needed for commissioning and ongoing maintenance of hardware & software components delivered by U.S. • Constructed matrix of effort per component vs. time • Estimate larger than prior estimate => add Management Reserve • MR added covers ~1/2 of increase in estimate • Checked total estimate w/ 20% of top-down estimate for ATLAS • Coordinated w/ TDAQ Management Team

  14. 3.6.1 Preoperations – FY06 3.6.1.1 Supervisor – RoI Builder 28k$ 3.6.1.1.1 ANL: 15k$; Dawson/Drake; TDAQ Support 3.6.1.1.2 MSU: 12k$; Ermoline; TDAQ Support 3.6.1.2 Communications & Travel (16k) 3.6.1.1.1 ANL: (8k) 3.6.1.1.2 MSU: (8k) 3.6.1.3 Programming Support 103k$ (201k) 3.6.1.3.1 ANL: 59k$; Schlereth/TBN; S/w Comm, Detector Supp 3.6.1.3.2 MSU: 44k$ (17k); Ermoline/TBN; H/w+S/w Comm, Det Supp 3.6.1.3.3 UCI: 0k$ (104k); Stancu/Kolos/Negri; H/w+S/w Comm, Det+TDAQ Supp 3.6.1.3.4 UWisc: 0k$ (80k); Wiedenmann/dosAnjos/Xu; S/w Comm, Det+TDAQ Supp

  15. 3.6.2 Operations – FY06 3.6.2.1 Supervisor – RoI Builder 137k$ 3.6.2.1.1 ANL: 97k$; Dawson/Drake/Schlereth; H/w+S/w Maint, TDAQ Support 3.6.2.1.2 MSU: 40k$; Ermoline; H/w+S/w Maint, Ops, TDAQ Support 3.6.2.2 Communications & Travel 51k$ 3.6.2.2.1 ANL: 13k$ 3.6.2.2.2 MSU: 13k$ 3.6.2.2.3 UCI: 13k$ 3.6.2.2.4 UW: 13k$ 3.6.2.4 Test Facilities 3.6.2.4.1 ANL: 10k$ 3.6.2.4.2 MSU: 11k$

  16. 3.6.2 Operations – FY06 (p. 2) 3.6.2.3 Programming Support 668k$ (241k) 3.6.2.3.1 ANL: 248k$ Schlereth/TBN; S/w Maintenance, Detector Support 3.6.2.3.2 MSU: 90k$ (22k) Ermoline/Hauser/TBN; S/w Maintenance, Ops 3.6.2.3.3 UCI: 205k$ (206k) Stancu/Ciobotaru/Unel/Kolos/Wheerler/Negri/Rogge H/w+S/w Maintenance, Ops, Detector+TDAQ Support 3.6.2.3.4 UW: 126k$ (13k) Wiedenmann/dosAnjos/Xu; S/w Maintenance, Det+TDAQ Support

  17. FY06 Management Reserve • FY06 MR priorities (in rough priority order): • Hardware commissioning: 0.25 => 0.5 FTE • Software commissioning: 0.25 => 0.5 FTE • Hardware maintenance: 0.5 => 1 FTE • TDAQ support: 0.4 => 1 FTE • Operations: 0.3 => 1 FTE • Detector support: 1 => 2 FTE • SRB: 1 => 1 FTE; Software maintenance: 2.5 => 2.5 FTE • Total: 6.2 => 9.5 FTE ~458k$ • Impact of MR: • Improved readiness of TDAQ for cosmics and beam • Improved efficiency of detector commissioning • Improved tools for detector monitoring • More efficient HLT/DAQ operations • Improved efficiency of operations due to s/w enhancements • Without MR funds, either or both: • Reduced DAQ support for detectors, with delays in detector commissioning • Reduced effort on ongoing HLT/DAQ development, with delays in completing critical software

More Related