210 likes | 454 Views
Rossway Safeway system. Roof section. The Rossway Safeway Roof Safety Protection system is installed on top of roof purlins.
E N D
Rossway Safeway system Roof section The Rossway Safeway Roof Safety Protection system is installed on top of roof purlins. The Rossway Safeway system consists of a platform deck with handrail and toe board to one side, the “leading edge” and fall protection frames to the other “working edge” Method statement for the Rossway Safeway system with a composite roof panel Roof Plan
Roof section The first roof tier is placed with crane or other suitable lifting device. Access to de-sling and fix panel is gained from Rossway Safeway system Method statement for the Rossway Safeway system with a composite roof panel Roof Plan
Rossway SafeEdge Roof section The “RosswaySafeEdge” roof perimeter edge protection system is fitted on the first composite panel installed. This provides perimeter fall protection for operatives working at roof level. Method statement for the Rossway Safeway system with a composite roof panel Roof Plan
Rossway SafeEdge Roof section The Rossway Safeway system is moved on purlin trolleys the width of a roof panel Method statement for the Rossway Safeway system with a composite roof panel Roof Plan
Rossway SafeEdge Roof section The next tier of roof panels are laid Method statement for the Rossway Safeway system with a composite roof panel Roof Plan
Rossway SafeEdge Roof section Crane slings removed with access fromRossway Safeway system Method statement for the Rossway Safeway system with a composite roof panel Roof Plan
Rossway SafeEdge Roof section The Rossway Safeway system is moved on purlin trolleys the width of a roof panel Method statement for the Rossway Safeway system with a composite roof panel Roof Plan
Roof section The next tier of roof panels are laid Method statement for the Rossway Safeway system with a composite roof panel Roof Plan
Rossway SafeEdge Roof section Crane slings removed with access fromRossway Safeway system Method statement for the Rossway Safeway system with a composite roof panel Roof Plan
Rossway SafeEdge Roof section A pack of roof panels can be landed on the completed roof area. Edge protection is provided to all edges with the Rossway Safeway Roof Safety protection system to the leading edge and the RosswaySafeEdge to the perimeter Method statement for the Rossway Safeway system with a composite roof panel Roof Plan
Rossway SafeEdge Roof section The Rossway Safeway system is moved on purlin trolleys the width of a roof panel Method statement for the Rossway Safeway system with a composite roof panel Roof Plan
Rossway SafeEdge Roof section The next tier of roof panels are laid panels can be taken from the pack landed at roof level. Method statement for the Rossway Safeway system with a composite roof panel Roof Plan
Rossway SafeEdge Roof section The Rossway Safeway system is moved on purlin trolleys the width of a roof panel Method statement for the Rossway Safeway system with a composite roof panel Roof Plan
Rossway SafeEdge Roof section The next tier of roof panels are laid Method statement for the Rossway Safeway system with a composite roof panel Roof Plan
Rossway SafeEdge Roof section The Rossway Safeway system is moved on purlin trolleys the width of a roof panel Method statement for the Rossway Safeway system with a composite roof panel Roof Plan
Rossway SafeEdge Roof section The next tier of roof panels are laid Method statement for the Rossway Safeway system with a composite roof panel Roof Plan
Rossway SafeEdge Roof section At the end of the roof the fall protection frames are removed by removing the fixing brackets on one side which enables the frames to rotate on the other side. The other side can then be released and the frame taken off with access from the platform deck. Method statement for the Rossway Safeway system with a composite roof panel Roof Plan
Rossway SafeEdge Roof section With access from the completed roof…… Method statement for the Rossway Safeway system with a composite roof panel Roof Plan
Rossway SafeEdge Roof section …..the platform deck and handrail can be moved on to the completed roof providing edge protection……. Method statement for the Rossway Safeway system with a composite roof panel Roof Plan
Rossway SafeEdge Roof section …from the platform deck…… Method statement for the Rossway Safeway system with a composite roof panel Roof Plan
Rossway SafeEdge Roof section …the final tier of roof panels are installed Method statement for the Rossway Safeway system with a composite roof panel Roof Plan