1 / 23

Mungcharoen Green Power Co.,Ltd

Mungcharoen Green Power Co.,Ltd. The Energy Long Live For Surin Province. Company Profile.

dolan
Download Presentation

Mungcharoen Green Power Co.,Ltd

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Mungcharoen Green Power Co.,Ltd The Energy Long Live For Surin Province

  2. Company Profile

  3. Our company background from Thailand energy policy, This energy policy has major objectives to promote alternative energy to complement and strengthen Thai Electricity system by using own resources from biomass such as Rice husk, Sugar cane-bagasse corn leaves, plam shell and woodchip, to reduce the import of fossil fuels and to replace Thai supply of fossils fuels which is forecasted to run short in the next 30 years

  4. Mungcharoen Green power has developed Rice Husk Power Plant since 2004 in Surin Province, Northern part of Thailand. The project started construction in January 2005 and completed in November 2006. The Project start commercial operation on January 23,2007

  5. Company Location Mungcharoen Green Power Co.,Ltd is Located at 333 Moo 7, Surin-Sikhoraphum Road, Tumbon Burusi, Muang District, Surin Province

  6. Factory Layout C 180,000ลบ.ม. A 200,000ลบ.ม. D 60,000ลบ.ม. B 400,000ลบ.ม. Factory building 4 Water storage pond

  7. Factory BuildingPlant 1 day Silo Cooling Tower Boiler Plant STG House Earth Pond Water Treatment Plant

  8. Process Electric Generation Design plant, we use rice husk is main fuel in process electrical generation for emergency case can use other biomass in process The rice husk for supply plant80% from Mungcharoen Rice mill and 20% from alliance

  9. Process Electric Generation Fuel consumption in 85,000 Ton/Year for generate Electricity 65 Million kWh / year

  10. Process Electric Generation For steam generation, we use Biomass Fire Boiler design by “ERK German” capacity 55 TPH to generated medium pressure super heated steam 40 Bar , 435 degree ‘C Furnace and combustor, we use technology from German by use combustor type “Step Grate”

  11. Process Electric Generation Turbine type “Full Condensing Steam Turbine” from HTC capacity 9,900 kW rate speed 8,540 RPM with “Gear reduction” Electricity generation by use Synchronous Generator type “Automatic Voltage Regulator (AVR)” capacity 11,560 KVA (9,900 kW at PF 0.85) and generate voltage 11,000 V

  12. Grid Connection The electricity sell to the EGAT Public Company Limited “Firm”, and connect to grids with PEA line Feeder # 5

  13. Product Electricity Mungcharoen Green power generated 9.9 MW of electric power. 8 MW of electric power to be sold to EGAT. 0.8 MW of electric power to be sold to Mungcharoen Rice Mill 0.8 MW of electric power to be used in the power plant.

  14. Product Rice Husk Ash (RHA) is by product of complete combustion of rice husk. This kind of ash is high in quality, and it is an essential raw material for steel and silica plant industries.

  15. Environmental and Management

  16. Waste Water From Process We design to zero discharge system, and over all water not reject outer factory

  17. Use the zero discharge principle to relieve the anxiety of nearby communities. In practices, waste water is treaded to have quality in accordance with the ministry of industry standard before releasing to holding pond.

  18. Air Pollution System Power plant use clean technology by use 2 system air treatment Use the first cleaning by use “Cyclone Dust Collector” and second cleaning by use “ESP”

  19. 2.Air pollution Use clean technology, first step use dust collector. For particle > 10 micron (0.01 mm)

  20. 2.Air pollution Second step use Electrostatic Precipitator (ESP). For particle < 0.1-1micron (0.0001 - 0.001mm)

  21. Third Party Certify

  22. We are Biomass Learning Center

  23. We are Modern Power Plant High Efficiency and Clean Technology

More Related