Linac4 Ion Source Review. Design and Production. Design and Production of:. New LINAC4 Front end Chamber New LINAC4 Faraday cage LEBT + Diagnostic Support for B357 LINAC4 SPL Plasma generator + 2 Cesium oven Plasma Generator BNL Developments (2011 – 2014):

domani
Download Presentation

D. Steyaert – G. Favre

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Linac4 Ion Source Review Design and Production Design and Production of: • New LINAC4 Front end Chamber • New LINAC4 Faraday cage • LEBT + Diagnostic Support for B357 • LINAC4 SPL Plasma generator + 2 Cesium oven • Plasma Generator BNL • Developments (2011 – 2014): • New RF Plasma Generators Linac4 Ion Source Review Design and production D. Steyaert – G. Favre

  2. New LINAC4 Front end Chamber 1/4 Linac4 Ion Source Review Design and production D. Steyaert – G. Favre

  3. New LINAC4 Front end Chamber 2/4 Design of new Front end Chamber - Multi-stage Extraction - Differential Pumping - Tilt and Alignment System for Electrode 2 - Ceramic Insulator Linac4 Ion Source Review Design and production D. Steyaert – G. Favre

  4. New LINAC4 Front end Chamber 3/4 Plasma Generator Pumping Volume 2 Insolator 2 PEEK Electrode 1 (Fixe) Electrode 2 (Tilt able and Movable) Isolator 1 Ceramic 10kV Connexion 20 kV Connexion Pumping Volume 1 Electrode 3 (Fixe) Cesium Protection LEBT Einzel Lens Pumping Volume 3 Linac4 Ion Source Review Design and production D. Steyaert – G. Favre

  5. R&D Activity: tight but feasible depending on technical choices New LINAC4 Front end Chamber 4/4 Beam Optics Pre-design Details-design Raw Material Order Linac4 Ion Source Review Design and production D. Steyaert – G. Favre

  6. New LINAC4 Faraday cage 1/3 Linac4 Ion Source Review Design and production D. Steyaert – G. Favre

  7. New LINAC4 Faraday cage 2/3 Faraday Cage Lifting and manipulation systems 500 Kg Linac4 Ion Source Review Design and production D. Steyaert – G. Favre

  8. New LINAC4 Faraday cage 3/3 Lifting and manipulation systems 500 Kg Linac4 Ion Source Review Design and production D. Steyaert – G. Favre

  9. LEBT + Diagnostic Support for B357 • New LEBT Support: • Design from LINAC4 • Delivery during the summer • Installation in Sept. 2011 For Diagnostic Components see R.Scriven & U.Raich Presentation. Linac4 Ion Source Review Design and production D. Steyaert – G. Favre

  10. LEBT + Diagnostic Support for B357 Linac4 Ion Source Review Design and production D. Steyaert – G. Favre

  11. LINAC4 SPL Plasma generator + 2 Cesium oven 1/2 Modification of existing SPL Design Plasma Generator + Cesium Injection Linac4 Ion Source Review Design and production D. Steyaert – G. Favre

  12. LINAC4 SPL Plasma generator + 2 Cesium oven 2/2 Linac4 Ion Source Review Design and production D. Steyaert – G. Favre

  13. Plasma Generator BNL 1/2 • 3D models from BNL Drawings • Modification for LINAC4 fitting • New drawing • Production • Test Linac4 Ion Source Review Design and production D. Steyaert – G. Favre

  14. Plasma Generator BNL 2/2 Design Validation Linac4 Ion Source Review Design and production D. Steyaert – G. Favre

  15. New Plasma Generator (2011 – 2014) First Estimation for Design and Manufacturing Design of new plasma generator + Modification of extraction Production Design Plasma Generator proto 01 Jan- May 2012Nov 2012 Plasma Generator proto 02 Nov 2012May 2013 Plasma Generator proto 03 May 2013Nov 2013 Plasma Generator proto 04 Nov 2013May 2014 30 mA 30 mA 50 mA 50 mA Linac4 Ion Source Review Design and production D. Steyaert – G. Favre

  16. Manufacturing Summary Design First Estimation: Tight but feasible depending on technical choices Design Manufacturing 0.8 FTE/Year (CERN Staff) + 650 kChF Design Office Support 1.5 FTE/Year (CERN Staff) + 650 kChFManufacturing 500 kChF Design Office Support + Manufacturing Awaiting confirmation Linac4 Ion Source Review Design and production D. Steyaert – G. Favre