1 / 31

MRP and ERP

MRP and ERP. Chapter 12. Learning Objectives. Describe the inputs, outputs, and nature of MRP processing. Explain bill of materials Explain time-phased product structure Describe differences between MRP and ERP. MRP. Material requirements planning (MRP):

Download Presentation

MRP and ERP

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MRP and ERP Chapter 12

  2. Learning Objectives • Describe the inputs, outputs, and nature of MRP processing. • Explain bill of materials • Explain time-phased product structure • Describe differences between MRP and ERP

  3. MRP • Material requirements planning (MRP): • A computer-based information system that translates master schedule requirements for end items into time-phased requirements for subassemblies, components, and raw materials. • The MRP is designed to answer three questions: • What is needed? • How much is needed? • When is it needed?

  4. Overview of MRP How much and when finished product is desired Composition of a finished products How much inventory is on hand or on order

  5. MRP Inputs:Master Schedule • Master schedule: • States: • Which end items are to be produced • When these are needed • In what quantities (customer orders, forecasts, order from warehouses to build up seasonal inventories). Item X at beginning of week 14 and at beginning of week 18 100 at beginning of week 14 150 at beginning of week 18

  6. Cumulative Lead Time • The master schedule should cover a period that is at least equivalent to the cumulative lead time • Cumulative lead time • The sum of the lead times that sequential phases of a process require, from ordering of parts or raw materials to completion of final assembly. CLT = 9 weeks

  7. Cumulative Lead Time • Following the previous example, if CLT=9 • When should we start work for the demand on the week 14? • When should we start work for the demand on the week 18?

  8. MRP Inputs:Bill of Materials • Bill of Materials (BOM) • A hierarchical listing of all of the assemblies, subassemblies, parts, and raw materials needed to produce one unit of a product • Each finished product has its own BOM • Product structure tree • A visual depiction of the requirements in a bill of materials, where all components are listed by levels

  9. Assembly Diagram and Product Structure Tree Level 0 = end item parent component Level 1 parent Level 2 component Amount needed for assembly at the next higher level only

  10. Low-Level Coding • Low-level coding • Restructuring the bill of materials so that multiple occurrences of a component all coincide with the lowest level at which the component occurs • Example: 1 X requires: 2 B, 1 C, 6 D, 28 E, and 2 F • Level 0 • X X: 1 • Level 1 C: 1 x 1 = 1 • B(2) • C B: 2 x 1 = 2 D: 3 x 2 = 6 E: 2 x 1 = 2 • Level 2 • D(3) • F(2) • E • E(2) F: 2 x 1 = 2 E: 1 x 2 = 2 • Level 3 E: 4 x 6 = 24 • E(4)

  11. Low-Level Coding: 1 X • 1 X requires: B: 2 C: 1 D: 6 E: 2+24+2=28 F: 2 • Level 0 • X X: 1 • Level 1 C: 1 x 1 = 1 • B(2) • C B: 2 x 1 = 2 D: 3 x 2 = 6 E: 2 x 1 = 2 • Level 2 • D(3) • F(2) • E • E(2) F: 2 x 1 = 2 E: 1 x 2 = 2 • Level 3 E: 4 x 6 = 24 • E(4)

  12. Low-Level Coding: 10 Xwith on hand inventory • Level 0 • 1 X requires: B: 2 C: 1 D: 6 E: 28 F: 2 • X • Level 1 • B(2) • C • Level 2 • D(3) • F(2) • E • E(2) • Level 3 • E(4) • 10 X require: B: 2x10-4=16 C: 1x10-10=0 D: 6x10-8=52 E: 28x10-60=220 F: 2x10-0=20 • On hand inventory B: 4 C: 10 D: 8 E: 60 F: 0 Does not consider item hierarchy!

  13. Low-Level Coding: 10 Xwith on hand inventory • Level 0 • X X: 10 • Level 1 • B(2) • C C: 1 x 10 -10=0 B: 2 x 10 - 4 = 16 • Level 2 • D(3) • F(2) • E • E(2) F: 2 x 0 = 0 D: 3 x 16 – 8=40 • Level 3 • E(4) E: 4 x 40 – 60=100 “Low-level coding” E: 2 x 0 = 0 E: 1 x 16 = 16 • 10X require: B: 16 C: 0 D: 40 E: 100+16+0=116 F: 0 • On hand inventory B: 4 C: 10 D: 8 E: 60 F: 0

  14. MRP Processing • MRP processing takes the end item requirements specified by the master schedule and “explodes” them into time-phasedrequirements for assemblies, parts, and raw materials offset by lead times Part E fabrication lead-time Sub assembly lead-time Material F delivery lead-time Final assembly lead-time

  15. MRP Inputs:Inventory Records • Inventory records • Includes information on the status of each item by time period (called time buckets) • Information about • Gross requirements • Scheduled receipts • Expected amount on hand • Other details for each item such as • Supplier • Lead time • Lot size policy • Changes due to stock receipts and withdrawals • Canceled orders and similar events

  16. MRP Record • Gross requirements • Total expected demand (during each period) without regard to the amount on hand. • Scheduled receipts • Open orders scheduled to arrive (at the beginning of a period) • Projected on hand • Expected inventory on hand (at the beginning of each time period) • Net requirements • Actual amount needed in each time period • Planned-order receipts • Quantity expected to received (at the beginning of the period) • Under Lot-for-lot will equal net requirements • Planned-order releases • Planned amount to order in each time period. • Equal planned-order receipts offset by lead time. 12-16

  17. MRPProcessing • Gross requirementsare generated by exploding the bill of materials • The core of MRP processing is determining net requirements (netting) -> materials that are actually needed to meet demand Net requirements Gross requirements Available inventory = - Available inventory Projected on-hand Scheduled receipts = + Projected on hand inventory + Scheduled receipts Net requirements Gross requirements = -

  18. MRP: Development • The MRP is based on the product structure tree diagram • Requirements are determined level by level, beginning with the end item and working down the tree • The timing and quantity of each “parent” becomes the basis for determining the timing and quantity of the “children” items directly below it. • The “children” items then become the “parent” items for the next level, and so on

  19. Example MRP • Orders: • 100 units for delivery at (the start of) week 4 • 150 units at (the start of) week 8. • Assembly: • Wood sections made by the firm. Fabrication takes 1 week. • Frames are ordered. Lead time is 2 weeks. • Shutter assembly requires 1 week. • Schedule receipts: • 70 wood sections at (the beginning of) week 1. • Determine the size and timing of planned-order releases (under Lot-for-Lot ordering)

  20. MRPLot-For-Lot Ordering

  21. MRPLot-For-Lot Ordering • Shutter • [LT=1 week] • Frames (2) • [LT=2 weeks] • Wood sections (4) • [LT= 1 weeks] • Widget (1) • [LT=1 weeks] • Widget (3) • [LT=1 weeks] 330*3 200*1 600*3 300*1

  22. Updating the System • An MRP is not a static document • As time passes • Some orders get completed • Other orders are nearing completion • New orders will have been entered • Existing orders will have been altered • Quantity changes • Delays • Missed deliveries • Rolling Horizon

  23. MRP Outputs: Primary • Primary Outputs • Planned orders • A schedule indicating the amount and timing of future orders • Order releases • Authorizing the execution of planned orders • Changes • Revisions of the dates or quantities, or the cancellation of orders

  24. MRP Outputs: Secondary • Secondary Outputs • Performance-control reports • Evaluation of system operation, including deviations from plans and cost information • e.g., missed deliveries and stockouts • Planning reports • Data useful for assessing future material requirements • e.g., purchase commitments • Exception reports • Data on any major discrepancies encountered • E.g., late and overdue orders, excessive scrap rates, requirements for nonexistent parts

  25. Enterprise Resource Planning (ERP) • Many organizations use a functional structure. Information tends to flow freely within each function but less so between functions. • Enterprise Resource Planning (ERP) • ERP was the next step in an evolution that began with MRP • ERP typically has an MRP core • ERP represents an expanded effort to integrate standardized record keeping that will permit information sharing among different areas of an organizationin order to manage the system more effectively • A system to capture and make data available in real-time to decision makers throughout the organization. • ERP systems are composed of a collection of integrated modules

  26. ERP Software Modules

  27. Focused Reading (MIS Major Required) • Enterprise resource planning (ERP)—A brief history • 13 Common ERP Mistakes and How to Avoid Making Them • ERP and Business Process Re-engineering • ERP: The Business Process Re-engineering Dilemma • To BPR, or not to BPR, that is the question • Cloud ERP • What Is Cloud ERP, and How Is It Different from Traditional Solutions? • Benefits of Cloud ERP Software

  28. ERP History • MRP: focus on cost reporting, materials, manufacturing • tapes • IBM • 1960~1970 • MRPII: scheduling, procurement • 1980s • ERP • SAP, Peoplesoft, • 1990 • Client-server architecture

  29. ERP Common Mistakes • Poor Planning • Not properly vetting ERP vendors • Not understanding or using key features • Understanding the time and resources required • Not having the right people on the team from the start • Not setting priorities • Not investing in training and change management • Underestimating the importance of accurate data • Taking the kitchen sink approach • Not decommissioning legacy applications • Not having an active load testing environment • Ignoring third-party support alternatives • Not having a maintenance strategy

  30. ERP & Business Process Re-engineering • Take place before ERP system selection • Output of BPR  ERP • To be process vs. as is process • Difference ways to do business globally • Process standardization after acquisition • Legacy systems • Make sure the process lead to higher values

  31. Cloud ERP • Cloud ERP vs. traditional ERP • Traditional: • Cloud: • Outsource operation, easy to setup, monthly/annually fee • Minimal initial cost • Automate operation • cons • Less control, data security, service outage

More Related