V.E. of Selecting Flooring Materials. KING FAHAD UNIVERSITY OF PETROLEUM & MINERALS College of Environmental Design Construction Engineering & Management CEM 512 – Value Engineering. Presented by: Mustafa Al-Humood. OUTLINE. Introduction Description Objectives V.E. Phases
E N D
V.E. of Selecting Flooring Materials KING FAHAD UNIVERSITY OF PETROLEUM & MINERALSCollege of Environmental Design Construction Engineering & Management CEM 512 – Value Engineering Presented by: Mustafa Al-Humood
OUTLINE • Introduction • Description • Objectives • V.E. Phases • Study Summary Information Functional Creative Judicial Development Implementation
INTRODUCTION • Flooring has a deep impact on the total space of the building, it adds wideness and effects the vision if it is very well selected in a way that reflects your style and matches the general style of the building.
INTRODUCTION • Good planning & choosing the flooring materials could save your time and money, therefore it is important to determine the function of each space of your building.
DESCRIPTION An owner would like to cover his apartment’s floor with suitable materials . The total space of the apartment is 87 sm for which the floor to be covered. The apartment consists of : 2 bedrooms (3.5x5 m /ea), 1 kitchen (3.5x3.5m) , 1 bathroom (3.5x2m), a living room (6x5m) and an entrance (1.5x2m).
OBJECTIVES • To cover the floor with good looking materials • To stay within a reasonable budget • To complete the work in a short time • To provide comfort the users
FUNCTIONAL PHASE What must it do? Verb Noun Provide Appearance Provide Comfort
CREATIVE THINKING • Cover with Carpet • Cover with Natural Marble • Cover with Artificial Rubber • Cover with Tiles • Cover with Ceramic • Cover with Wood • Cover with Granite
Total Easy to clean Health and Safety Wastage Fixing Time Appearance Initial Cost Rank Carpet 5 8 9 8 3 3 36 6 Natural Marble 3 10 5 5 7 7 37 5 Artificial Rubber 10 3 9 8 7 8 45 2 Tile 10 2 4 5 8 8 37 5 Ceramic 9 10 5 6 7 9 46 1 Wood 3 10 7 6 8 4 38 4 Granite 6 9 7 6 6 6 40 3
Total Easy to clean Health and Safety Wastage Fixing Time Appearance Initial Cost Rank Idea 1 2 7 3 4 5 6 27 6 Idea 2 10 10 5 6 7 9 47 1 Idea 3 9 9 7 7 5 7 44 4 Idea 4 3 9 5 6 7 9 36 5 Idea 5 7 8 7 7 8 8 45 3 Idea 6 9 8 7 7 8 7 46 2
Determining Weights Score Assigned Wt A. Initial cost 5 8 B. Appearance 6 10 C. Fixing time 2 3 D. Easy to clean 1 1 B C D E F A A / B A - 2 A - 2 B - 3 B - 2 B C - 2 C 3 Major performance 2 Medium Performance 1 Minor performance D E
Total Evaluation Matrix Easy to clean Fixing Time Initial Cost Appearance 10 8 3 1 Idea 1 7 2 3 6 101 Idea 2 10 10 5 9 204 Idea 3 9 9 7 7 190 Idea 4 9 3 5 9 138 Idea 5 8 7 7 8 165 Idea 6 8 9 7 7 180
Savings • Idea# 2 to Idea # 1 195% saving • Idea# 2 to Idea # 3 92% saving • Idea# 2 to Idea # 4 185% saving • Idea#2 to Idea # 5 117% saving • Idea#2 to Idea # 6 88% saving
Summary • The proposed Idea will meet the criteria and will save time and money • Subjective