EARTH-ROCK FILL DAM. RIGHT SIDE REGULATOR. SPILL WAY. INDIRA SAGAR PROJECT (POLAVARAM) (Head Works). PUDIPALLI. POWER HOUSE. LEADING CHANNEL. SADDLE DAM. TAIL RACE CHANNEL. DEVARA DONDI. RAMAIAH PETA. TUNNEL SADDLE DAM. PRPOSED TUNNEL 12M DIA. FREE FLOW 918 M LONG. REGULATOR.
E N D
EARTH-ROCK FILL DAM RIGHT SIDE REGULATOR SPILL WAY INDIRA SAGAR PROJECT (POLAVARAM) (Head Works) PUDIPALLI POWER HOUSE LEADING CHANNEL SADDLE DAM TAIL RACE CHANNEL DEVARA DONDI RAMAIAH PETA TUNNEL SADDLE DAM PRPOSED TUNNEL 12M DIA FREE FLOW 918 M LONG REGULATOR POLAVARAM KADIAMMA DRAIN RIVER NAVIGATION CANAL RIGHT MAIN CANAL SADDLE DAM PURUSHOTHA PATNAM LEFT MAIN CANAL EXISTING OUT FALL SLUICE OF KADIAMMA DRAIN REGULATOR GOVERNMENT OF ANDHRA PRADESH I & CAD DEPARTMENT POLAVARAM PROJECT INDEX MAP OF HEAD WORKS AT RAMAIAHPETA SITE (G G’ D) Design by D.Raj Kumar
Head Works (Polavaram (V)) Right Main Canal (174.00 KM) Left Main Canal (181.50 KM) • Utilisation :89.54TMC • Ayacut : 3.21Lakh Acs. • No. of Packages : 7 • Bids value (7 Pkgs.) : Rs. 1773.71 Crs. • Works awarded to all packages. • Components : • No. of packages : 8 Nos. • Awarded (packages): 7 Nos. • Bid value (7 Pkgs) : Rs. 1117.29 Crs. • Earth-cum-rock fill dam and Power house with tail race channel.: Bids invited on annuity basis and revised under evaluation. • Utilisation : 103.70TMC. • Ayacut : 4.00Lakh Acs. • No. of Packages : 8 • Works awarded to 7 • Works for 8th Package rejected and recalled. (162.409 to 181.50Km) : under finalisation with evaluation committee • Bid value (8 Pkgs): Rs. 1583.54 Crs. INDIRA SAGAR PROJECT (POLAVARAM PROJECT)(Utilisation : 301.00TMC, Irrigation : 7.21Lakh Acres, Power Generation : 960MW diversion to Krishna river 80TMC, industrial and drinking water for Visakhapatnam town 23.44TMC Evaporation losses 4.70TMC )
To draw water : 301 TMC • Left Main Canal : 127.14 TMC (irrigation= 103.70 TMC) (water supply to vizag = 23.44 TMC) • 4.00 Lakh Acres • Right Main Canal : 174.24 TMC (irrigation= 89.54 TMC) (Krishna basin (inc. Evap. Loses) = 84.70 TMC) • 3.20 Lakh Acres • Power Generation : 960 MW ( 12 x 80MW) • F R L : 45.72m (150’) • Gross Storage : 194.60 TMC • Discharge : 17500 cusecs (LMC & RMC each)
12 Forest Clearance Total extent involved : 3,223 Ha./7961 acres dereservation proposals sent to PCCF : 2/2005 Compensatory afforestation identified in • Vishakapatnam : 1052 Ha./2590 acres • East Godavari Dist. : 2915 Ha/7200 acres
13 Status of R & R Scope of work • 276 Villages are designated as affected Villages under fore shore of Indira Sagar Project • ANDHRA PRADESH
INDIRA SAGAR PROJECT LEFT MAIN CANAL PKG-8 Km 19.091 PKG-2 Km 26.00 PKG-5 Km 17.30 PKG-6 Km 25.00 PKG-7 Km 26.409 PKG-4 Km 24.555 PKG-3 Km 17.545 PKG-1 Km 25.60 POLAVARAM BARRAGE KM 0.00 KM 51.60 KM 25.60 KM 181.50 KM 93.70 KM 111.00 KM 136.00 KM 69.145 KM 162.409 CATEGORY-I
INDIRA SAGAR PROJECT LEFT MAIN CANAL Pkg.No. 1 /Cat-I: Excavation of main canal, lining and construction of CM & CD works including investigation, design of Indira Sagar LMC from Km.0.00 to KM 25.600 Name of the Contractor : M/s.Progressive Const.Ltd. Agreement Amount : Rs.254.88 Crs. Agreement Date : 20-03-2005 Period of Completion : 24 Months (8 Milestones) Target date of completion : 3/2007 • Investigation : Completed • Designs : In progress • Execution (main canal) : 7.20 Km length in progress against 25.6 Km. • Qty. of earth work done : 28,95,734 cum against 1,19,36,000 cum • Expenditure : 2004-2005 - Rs. 12.74 Crs. • 2005-2006 - Rs. 38.86 Crs. • Cum. Inc. Mob. Adv. only - Rs. 51.60 Crs. • Land Acquisition : Required 2042 Acres, Requisitioned 2042 acres, Acquired 612 acres
INDIRA SAGAR PROJECT LEFT MAIN CANAL Pkg.No. 2 /Cat-I: Excavation of main canal, lining and construction of CM & CD works including investigation, design ofIndira Sagar LMC Km 25.600 to Km. 51.60 Name of the Contractor : M/s.Patel-Soma(JV) Agreement Amount : Rs.242.54 Crs. Agreement Date : 17-03-2005 Period of Completion : 24 Months (8 Milestones) Target Date of Completion : 3/2007 • Investigation : Completed • Designs (Structure) : In progress • Execution (Canal) : In progress • Qty. of earth work done : 37,57,000 cum against 1,70,44,000 cum • Qty. of concrete work done : (lining) 40,100 cum against 1,70,600 cum • Machinery : deployed 34 Nos. (Excavators 13, Tippers 21 etc) • Expenditure : 2004-2005 - Rs. 12.13 Crs. • 2005-2006 - Rs. 19.48 Crs. • Cum. Inc. Mob. Adv. only - Rs. 31.61 Crs • Land Acquisition : Required 2042 Acres, Requisitioned 2042 acres, Acquired 612 acres
INDIRA SAGAR PROJECT LEFT MAIN CANAL Pkg.No. 3 /Cat-I: Excavation of main canal, lining and construction of CM & CD works including investigation, design ofIndira Sagar LMC Km 51.60 to 69.145 Name of the Contractor : M/s. Maytas-NCC(JV) Agreement Amount : Rs. 212.94 Crs. Agreement Date : 19-03-2005 Period of Completion : 24 Months (8 Milestones) Target Date of completion : 3/2007 • Investigation : Completed • Designs approved: 17.45 Kms length against 17.545Kms • Execution : 1.15 KM against 17.545 Kms • Qty. of Earth work done : 3,62,000 cum against 80,95,063 cum • No. of Machinery : 13 deployed (dumpers 10, Excavators 2, Dozers-1) • Expenditure : 2004-2005 - Rs. 10.65 Crs. • 2005-2006 - Rs. 1.75 Crs. • Cum. Inc. Mob. Adv. only - Rs. 12.40 Crs • Land Acquisition : Required 2042 Acres, Requisitioned 2042 acres, Acquired 612 acres
INDIRA SAGAR PROJECT LEFT MAIN CANAL Pkg.No. 4 /Cat-I: Excavation of main canal, lining and construction of CM & CD works including investigation, design of Indira Sagar LMC Km .69.145 to Km.93.70 Name of the Contractor : M/s. Sabir Dam & Water works Const. Co. Agreement Amount : Rs. 206.80 Crs. Agreement Date : 23-03-2005 Period of Completion : 24 Months (8 Milestones) Target date of completion : 3/2007 • Investigation : Completed • Execution : 8.06 Km length against 24.555 Km • Qty. of earth work done : 18,28,000 cum against 70,00,000 cum • No. of Machinery : 25 (proclains 5 Nos., Tippers 20 Nos.) • Expenditure : 2004-2005 - Rs. 10.65 Crs. • 2005-2006 - Rs. 1.75 Crs. • Cum. Inc. Mob. Adv. only - Rs. 12.40 Crs • Land Acquisition : Required 1253 acres, Requisitioned 779 acres, Acquired 394 acres
INDIRA SAGAR PROJECT LEFT MAIN CANAL Pkg.No. 5 /Cat-I: Excavation of main canal, lining and construction of CM & CD works including investigation, design of Indira Sagar LMC Km 93.70 to Km 111.00 Name of the Contractor : M/s. Sabir Dam & Water works Const. Co. Agreement Amount : Rs. 181.60 Crs. Agreement Date : 23-03-2005 Period of Completion : 24 Months (8 Milestones) Target date of completion : 3/2007 • Investigation : Completed • Designs : 6.00Kms length against 17.30Kms • Execution : 5 Km length against 17.30 Km • Qty. of earth work done : 12,78,000 Cum against 85,00,000cum • No. of Machinery : 17 (Excavators 4 Nos., Tippers 10 Nos., Dozers 2 Nos., tractor 1 No.) • Expenditure : 2004-2005 - Rs. 9.08 Crs. • 2005-2006 - Rs. 10.48 Crs. • Cum. Inc. Mob. Adv. only - Rs. 19.50 Crs • Land Acquisition : Required 1034 Acres,Requisitioned 374 acres , Acquired 118 Acres
INDIRA SAGAR PROJECT LEFT MAIN CANAL Pkg.No. 6 /Cat-I: Excavation of main canal, lining and construction of CM & CD works including investigation, design ofIndira Sagar LMC Km.111.00 to Km136.00. Name of the Contractor : M/s. Madhucon-Sino Hydro (JV) Agreement Amount : Rs. 196.20Crs. Agreement Date : 23-03-2005 Period of Completion : 24 Months (8 Milestones) Target date of completion : 3/2007 • Investigation : Completed • Designs : 21 Kms length against 25 Kms • Execution : 3.030 Kms length against 25Kms • Qty. of earth work done : 6,37,500 Cum against 1,11,00,000cum • No. of Machinery : 41 (Excavators 7 Nos., Dozer 3 No., Dumpers 28 Nos., Compressors 3 Nos.) • Expenditure : 2004-2005 - Rs. 9.81 Crs. • 2005-2006 - Rs. 3.02 Crs. • Cum. Inc. Mob. Adv. only - Rs. 12.83 Crs • Land Acquisition : Required 1260 Acres, Requisitioned 1027 acres,Acquired 312 Acres
INDIRA SAGAR PROJECT LEFT MAIN CANAL Pkg.No. 7 /Cat-I: Excavation of main canal, lining and construction of CM & CD works including investigation, design of Indira Sagar LMC Km136.00 to Km.162.409. Name of the Contractor : M/s.KCL-JCCG(JV) Agreement Amount : Rs. 175.00 Crs. Agreement Date : 14-03-2005 Period of Completion : 24 Months (8 Milestones) Target date of completion : 3/2007 • Investigation : Completed • Designs : 23 Kms length against 26.409 Kms. Structures : Nil against 75 Nos. • Execution : 7.30 Kms length against 26.409Kms • Qty. of earth work done : 16,46,700 Cum against 62,00,000cum • No. of Machinery : 64 (Excavators 3 Nos., Tippers 21 Nos., Dozer 2 No. etc.) • Expenditure : 2004-2005 - Rs. 8.75 Crs. • 2005-2006 - Rs. 18.33 Crs. • Cum. Inc. Mob. Adv. only - Rs. 27.08 Crs • Land Acquisition : Required 1211 acres, Requisitioned 1100, Acquired 361 acres,
INDIRA SAGAR PROJECT LEFT MAIN CANAL Pkg.No. 8 /Cat-I: Excavation of main canal from 162.409 to KM 177.809 and improvements to existing water supply canal from KM 10.902 to KM 33.609 and excavation of water supply canal from KM 0.00 to KM 10.85 including CM & CD works. Name of the Contractor: M/s IVRCL – SEW - PRASAD Tender accepted in Government Memo No. 7029/Bids of Open Category (3 Bids) dated 31-12-2005 for Rs. 113.38 Crs. Agreement is to be concluded.
INDIRA SAGAR PROJECT (POLAVARAM) HEAD WORKS CATEGORY-I
INDIRA SAGAR PROJECT HEAD WORKS Pkg.No. Spillway : Construction of Spillway of length 985.50M consisting of 48 vents each of size 16 m x 15 m on right bank of discharge 36 Lakhs cusecs with FRL at +45.72 m for ISP across river Godavari at Ramayyapeta (V) in WG (D). Name of the Contractor : M/s Madhucon-Sino Hydro(JV) Agreement Amount : Rs. 633.60 Crs. Agreement Date : 23-03-2005 Period of Completion : 36 Months (12 milestones) Target date of completion : 3/2008 • Investigation : Completed • Designs : Under scrutiny & approval • Execution (progress) : 0.50 Kms length against 0.985Kms • Qty. of earth work done : 7,68,353 cum against 72,76,500 cum • No. of Machinery : 26 deployed • Expenditure : 2005-2006 - Rs. 44.14 Crs. (Inc. Mob.adv.) • Land Acquisition : Required 238.96 acres, Acquired 124.12 acres • Bottle Necks : DN Published for 114.84 acres.
INDIRA SAGAR PROJECT HEAD WORKS Pkg.No. 62 : Construction of right flank regulator and off take regulator, saddle dam including it’s construction for right side connectivities. Name of the Contractor : M/s. Hindustan-Ratna(JV) Agreement Amount : Rs. 79.00 Crs. Agreement Date : 05-03-2005 Period of Completion : 24 Months(8 Mile Stones) Target date of Completion : 3/2007 • Investigation : Completed • Designs : in progress • Execution : in progress • Qty. of earth work done : 51,500 cum against 6,22,253 cum • Expenditure : 2004-2005 - Rs. 3.95 Crs. • 2005-2006 - Rs. 0.06 Crs. • Cum. Inc. Mob. Adv. only - Rs. 4.01 Crs • Land Acquisition : Required 124.12 Acres, Acquired 29.76 acres
INDIRA SAGAR PROJECT HEAD WORKS Pkg.No. 63 : Construction of tunnel of about 900m long excavation of entry and exit channels Name of the Contractor : M/s. SMSL-UANRCL(JV) Agreement Amount : Rs. 72.81 Crs. Agreement Date : 09-03-2005 Period of Completion : 24 Months (8 Mile Stones) Target Date of Completion : 3/2007 • Investigation : Completed • Designs : In progress • Execution : yet to be started • Qty. of earth work done : 33,000 cum against 5,49,829 cum • No. of Machinery deployed : 5 Nos. (Dozer-1, Excavators-1, Tippers-3) • Expenditure : 2004-2005 - Rs. 3.64 Crs. • 2005-2006 - Rs. 7.89 Crs. • Cum. Inc. Mob. Adv. only - Rs. 11.53 Crs • Land Acquisition : Required 139.219 acres, Acquired 24.69 acres • Forest Land : Required 24.25 acres
INDIRA SAGAR PROJECT HEAD WORKS Pkg.No. 64 : Construction of tunnel of about 880m long excavation of entry and exit channels Name of the Contractor : G.Venkata Reddy & Co., Agreement Amount : Rs. 73.89 Crs. Agreement Date : 11-03-2005 Period of Completion : 24 Months(8 Mile Stones) Target date of Completion : 3/2007 • Investigation : Completed • Designs : In progress • Execution : 0.1 Kms length against 1.488 Kms • Qty. of earth work done : 1,43,405 cum against 11,31,790cum • No. of Machinery deployed : 16 Nos. (Tippers-10, proclainers-2, generators-2 etc.) • Expenditure : 2004-2005 - Rs. 3.69 Crs. • 2005-2006 - Rs. 12.35 Crs. • Cum. Inc. Mob. Adv. only - Rs. 16.04 Crs • Land Acquisition : Required 102.32 Acres, Acquired 24.53 • Forest Land : Required 32.69 acres
INDIRA SAGAR PROJECT HEAD WORKS Pkg.No. 65 : Construction of tunnel of about 919m long and left flank regulator Name of the Contractor : M/s. Unity Infra Projects Agreement Amount : Rs. 90.99 Crs. Agreement Date : 16-03-2005 Period of Completion : 24 Months (8 milestones) Target date of completion : 3/2007 • Investigation : Completed • Designs : In progress • Execution : 0.90 Kms length against 3.115 Kms • Qty. of earth work done : 2,65,000 cum against 14,98,736cum • No. of Machinery : 22 deployed (Excavators 5 Nos., dumpers 13 Nos., etc) • Expenditure : 2004-2005 - Rs. 4.55 Crs. • 2005-2006 - Rs. 8.89 Crs. • Cum. Inc. Mob. Adv. only - Rs. 13.44 Crs • Land Acquisition : Required 92.58 Acres, Acquired 32.23 acres • Forest Land : Required 34.60 acres
INDIRA SAGAR PROJECT HEAD WORKS Pkg.No. 66 : Construction of tunnel of about 890m long, saddle dam long “KL”, off-take regulator. Name of the Contractor : M/s. Aventika & Sai Venkata Agreement Amount : Rs. 90.00 Crs. Agreement Date : 14-03-2005 Period of Completion : 24 Months (8 Milestones) Target date of completion : 3/2007 • Investigation : Completed • Designs : In progress • Execution : Length 0.59 Kms against 3.515Kms • Qty. of earth work done : 1,29,000 cum against 21,57,671 cum • No. of Machinery : 25 deployed (Excavators 1 No, tippers 10 Nos., tractors 3 Nos. etc.) • Expenditure : 2004-2005 - Rs. 4.50 Crs. • 2005-2006 - Rs. 2.97 Crs. • Cum. Inc. Mob. Adv. only - Rs. 7.47 Crs • Land Acquisition : Required 124.77 Acres, Acquired 30.77 acres • Forest Land :Required 41.53 acres
INDIRA SAGAR PROJECT HEAD WORKS Pkg.No. 67 : Construction of navigation lock left side and navigation canal leading to river Godavari. Name of the Contractor : M/s. Jaya K. Siva Rao Agreement Amount : Rs. 77.00 Crs. Agreement Date : 05-03-2005 Period of Completion : 24 Months (8 milestones) Target date of completion : 3/2007 • Designs : In progress • Execution : 0.50 Kms length against 4.00Kms • Qty. of earth work done : 80,000 cum against 22,59,058cum • No. of Machinery : 6 deployed (procliner – 1No., tippers 5 Nos.) • Expenditure : 2004-2005 - Rs. 3.15 Crs. • 2005-2006 - Rs. 3.05 Crs. • Cum. Inc. Mob. Adv. only - Rs. 6.20 Crs • Land Acquisition : Required 91.22 Acres, Acquired 30.17 acres
INDIRA SAGAR PROJECT RIGHT MAIN CANAL PACKAGE-7 PACKAGE-6 PACKAGE-5 PACKAGE-4 PACKAGE-1 PACKAGE-3 PACKAGE-2 POLAVARAM BARRAGE KM 28..70 KM 14.80 KM 23.399 KM 33.301 KM 33.60 KM 22.70 KM 17.50 KM 0.00 KM 14.80 KM 38.199 KM 71.50 KM 105.10 KM 133.80 KM 156.50 KM 174.00 CATEGORY-I
INDIRA SAGAR PROJECT RIGHT MAIN CANAL Pkg.No. 1: Earth work excavation, forming embankments, constructions of CM & CD works from km. 0.00 to km.14.80. Name of the Contractor : M/s. Patel Soma (JV) Agreement Amount : Rs. 241.50 Crs. Agreement Date : 21-10-2004 Period of Completion : 24 Months ( 8 Mile Stones) Target Date of Completion : 2/2007 • Investigation : Completed • Designs : Completed • Execution (canal) : 2.4 Km length against 14.08 KM • Qty. of earth work done : 37,68,013 cum against 1,44,45,129 cum • No. of Machinery : 46 deployed (tippers 30, Proclaims 9Nos, Dozers – 7Nos.) • Expenditure : 2004-2005 - Rs. 12.07 Crs. • 2005-2006 - Rs. 43.80 Crs. • Cum. Inc. Mob. Adv. only - Rs. 55.87 Crs • Land Acquisition : Required 1257 Ac, Acquired 859 Ac. • Bottle Necks : Ryoths are obstructing the survey for the announcement of compensation.
INDIRA SAGAR PROJECT RIGHT MAIN CANAL Pkg.No. 2: Earth work excavation, forming embankments, constructions of CM & CD works from km. 14.80 to 38.199. Name of the Contractor : M/s. Progressive Const. Ltd. Agreement Amount : Rs. 236.25 Crs. Agreement Date : 20-10-2004 Period of Completion : 24 Months (8 Mile Stones) Target date of Completion : 2/2007 • Investigation : 11.90 Km length against 23.399Kms • Designs approved : 11.90 Kms length against 23.399Kms • Execution (canal) : 0.4 Km length against 23.399 Km. • Qty. of earth work done : 43,62,289 Cum against 1,91,78,193 Cum • No. of Machinery : 159 (tractors 127, Dozers-15 Nos., Proclaims-13, etc.,) • Expenditure : 2004-2005 - Rs. 23.62 Crs. • 2005-2006 - Rs. 28.53 Crs. • Cum. Inc. Mob. Adv. only - Rs. 52.15 Crs • Land Acquisition : Required 2041.91 Ac, Acquired 704 Ac. • Bottle Necks : Ryoths are obstructing the survey for the announcement of compensation.
INDIRA SAGAR PROJECT RIGHT MAIN CANAL Pkg.No. 3: Earth work excavation, forming embankments, constructions of CM & CD works from km. 38.199 to Km.71.50 Name of the Contractor : M/s.Hindustan Constn.Co. Ltd. Agreement Amount : Rs. 321.30 Crs. Agreement Date : 23-10-2004 Period of Completion : 24 Months (8 Milestones) Target Date of completion : 2/2007 • Investigation : Completed • Designs : Completed Structures : in progress • Execution : Works started • Qty. of earth work done : 18,71,432 cum against 1,21,21,276 cum • No. of Machinery : 53 Nos. (Tippers -35, Proclains-16Nos,Dozers-2 Nos) • Expenditure : 2004-2005 - Rs. 16.06 Crs. • 2005-2006 - Rs. 16.55 Crs. • Cum. Inc. Mob. Adv. only - Rs. 32.61 Crs • Land Acquisition : Required 3657 Ac, Acquired 476 ac • Bottle necks : Ryoths are obstructing the survey for the announcement of compensation.
INDIRA SAGAR PROJECT RIGHT MAIN CANAL Pkg.No. 4 : Earth work excavation, forming embankments, constructions of CM & CD works from km. 71.50 to 105.10 Name of the Contractor : M/s. Jaiprakash Gyatri(JV) Agreement Amount : Rs. 301.30 Crs. Agreement Date : 23-10-2004 Period of Completion : 24 Months (8 Milestones) Target date of completion : 2/2007 • Investigation (progress) : 28 Kms length against 33.60 Kms • Designs approved: 28 Kms length against 33.60 Kms. • Execution : 0.350 Length Km against 33.6 Km. • Qty. of earth work done : 24,35,000 cum against 86,82,139cum. • No. of Machinery : 43 (Tippers-31, Proclains-8,JCB-2Nos etc.,) • Expenditure : 2004-2005 - Rs. 15.06 Crs. • 2005-2006 - Rs. 8.79 Crs. • Cum. Inc. Mob. Adv. only - Rs. 23.85 Crs • Land Acquisition : Required 2645 Ac, Acquired 569 ac. • Bottle Necks : Ryoths are obstructing the enjoyment survey for the announcement of compensation.
INDIRA SAGAR PROJECT RIGHT MAIN CANAL Pkg.No. 5 : Earth work excavation, forming embankments, constructions of CM & CD works from km. 105.10 to 133.80 Name of the Contractor : M/s.IVRCL SEW&Prasad(JV) Agreement Amount : Rs. 295.92 Crs. Agreement Date : 23-10-2004 Period of Completion : 24 Months (8 Milestones) Target date of completion : 2/2007 • Investigation : 27.7 Kms length against 28.7 Kms • Designs approved : 27.7 Kms length against 28.7Kms. Structures : Nil against 26 Nos. • Execution : 14,77,650 cum against 90,55,503 cum • Expenditure : 2004-2005 - Rs. 14.80 Crs. • 2005-2006 - Rs. 7.15 Crs. • Cum. Inc. Mob. Adv. only - Rs. 21.95 Crs • Land Acquisition : Required 1847.00 Acres, Acquired 177 acres. • Bottle Necks : Ryoths are obstructing the enjoyment survey for the announcement of compensation.
INDIRA SAGAR PROJECT RIGHT MAIN CANAL Pkg.No. 6: Earth work excavation, forming embankments, constructions of CM & CD works from km. 133.80 to Km.156.50 Name of the Contractor : M/s.Progressive Const.Ltd. Agreement Amount : Rs. 196.74 Crs. Agreement Date : 20-10-2004 Period of Completion : 24 Months (8 Milestones) Target date of completion : 2/2007 • Investigation : Completed • Designs : Completed Structures : in progress • Execution : 0.6 KM length against 22.7 KM. • Qty. of earth work done : 19,90,000 cum against 85,19,000cum • No. of Machinery : 60 Deployed (tractors – 48, Tippers-6, Proclains-2Nos etc) • Expenditure : 2004-2005 - Rs. 9.84 Crs. • 2005-2006 - Rs. 19.66 Crs. • Cum. Inc. Mob. Adv. only - Rs. 29.50 Crs • Land Acquisition : Required 1343 acres, Acquired 366 acres • Bottle Necks : Ryoths are obstructing the enjoyment survey for the announcement of compensation.
INDIRA SAGAR PROJECT RIGHT MAIN CANAL Pkg.No. 7: Earth work excavation, forming embankments, constructions of CM & CD works from km. 156.50 to 174.00. Name of the Contractor : M/s. Larson&TOUBRO Ltd. Agreement Amount : Rs. 180.70 Crs. Agreement Date : 25-10-2004 Period of Completion : 24 Months (8 Milestones) Target date of completion : 2/2007 • Investigation : 12.0 Kms Length against 17.5 Kms • Designs approved : 12.0 Kms length against 17.50 Kms Structures : in progress • Execution : 4,21,000 cum against 76,05,554 cum • Expenditure : 2004-2005 - Rs. 9.04 Crs. • 2005-2006 - Rs. 4.70 Crs. • Cum. Inc. Mob. Adv. only - Rs. 13.74 Crs • Land Acquisition : Required 1132 acres, Acquired 131 acres • Bottle Necks : Ryoths are obstructing the enjoyment survey for the announcement of compensation.